National Surety Co. v. Rogers

257 S.W. 651
CourtCourt of Appeals of Texas
DecidedNovember 1, 1923
DocketNo. 1528.
StatusPublished

This text of 257 S.W. 651 (National Surety Co. v. Rogers) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Surety Co. v. Rogers, 257 S.W. 651 (Tex. Ct. App. 1923).

Opinions

This suit was brought by Rogers against Dan La Roe, and the National Surety Company, to recover the sums of $3,125.04, $878.50, and $4,510. He obtained judgment for the first two sums, and the surety company appeals.

The material facts are as follows:

In October, 1920, La Roe entered into a contract with the United States authorities to build about 10 miles of highway in Arizona, and gave bond for the performance of the contract with the appellant as surety. One of the conditions of the bond was that La Roe would pay all persons furnishing labor or material in the construction of the highway. The appellee worked as a subcontractor upon this highway, and at the time of its completion claimed a balance due in said sum of $3,125.04.

At the same time La Roe had contracts with the state of New Mexico for the construction of certain highways in that state; one being known as the Artesia-Hope road, project No. 29. For the performance of these contracts La Roe gave bonds with appellant as surety. These bonds did not protect subcontractors.

At the time the Arizona work was completed, the New Mexico work was still in progress, and according to the contention of Rogers it was agreed between himself and La Roe that the latter might use in the completion of the New Mexico contracts the said sum of $3,125.04; the same to be paid upon the completion of the New Mexico work. Rogers then moved onto the Artesia-Hope job and performed services for La Roe, for which he claims an unpaid balance in said sum of $878.50.

La Roe had in his employ A. O. Peabody, who was his general agent in charge of the road building operations.

While engaged upon the New Mexico contracts, La Roe became financially involved and unable to complete same. Thereupon the New Mexico authorities called the surety company, through its agent, E. L. Early, to perform the obligation of its bonds in connection with the New Mexico contracts. Thereupon Early went to Silver City, N.M., and conferred with Peabody and La Roe. Those three then went together to Santa Fe N.M., and conferred with the New Mexico, authorities, and as a result of this latter conference La Roe executed and delivered to the state highway commission an instrument, in substance, as follows:

Reciting the contracts existing between the state of New Mexico, by its state highway department, for the construction and completion of certain road contracts and that on November 2, 1921, the state highway engineer, as executive officer of the commission, had notified La Roe it would be necessary to take over the contracts and have the bonding company complete same, and that on November 9, 1921, La Roe had acknowledged his inability to complete the contracts. That the same required 10 days' notice to La Roe before it could take over the contracts; therefore, it was agreed that La Roe should and did waive the 10 days' notice and authorized the highway engineer to take over his equipment and use the same for the completion of the contracts, and that nothing in the agreement should affect the rights of the state highway commission under the original contracts, bonds, etc., except as above indicated. Thereupon a written agreement was entered into between the state highway commission, the surety company, and A. O. Peabody, reciting all of the facts, and that it was to the mutual benefit of the parties to that agreement that the road contracts should be carried to completion under the existing organization, wherefore it was agreed that La Roe was in default, that Peabody should be substituted for him as a contractor under the original *Page 652 contract, and that Peabody should carry out the same to completion, and that current estimates and all estimates theretofore and thereafter accruing should be used in the payment of the legitimate debts and expenses accrued and to accrue in the completion of the contracts. It was further agreed that Peabody was to receive $500 per month for his services, together with 50 per cent. of the net profits, if any, and the remaining 50 per cent. to be paid to La Roe, and the moneys earned on the contract to be disbursed on voucher checks signed by the three parties to the agreement.

It is shown by the evidence that La Roe turned over his entire outfit, equipment, and supplies to Peabody, valued at about $250,000, and same was used in the completion of the contracts. There also became available and was used by Peabody $44,250.58, due upon current estimates for work already done, and retained estimates in the sum of $38,109.57 for work theretofore done, all of which was subsequently used by Peabody and paid upon checks signed by him, a representative of appellant, and the representative of the highway authorities of New Mexico.

According to the testimony of La Roe, at the conference held in Silver City with the representative of appellant, Early, the latter told him the surety company would have to take over the work; that it was subsequently agreed between himself and Early that, if La Roe would execute the waiver above quoted and turn over his outfit, equipment, and supplies, the surety company would complete the contracts, and pay the debts owing by La Roe; that it was in pursuance of this agreement that he executed the waiver and turned over his outfit, etc.

There is also evidence that, prior to the expiration of the time within which Rogers might have sued appellant upon its bond to recover the money earned upon the Arizona contract, the agent of appellant agreed to pay same if Rogers would wait until the completion of the New Mexico work.

The plaintiff sought to recover the said sums of $3,125.04 and $878.50 upon the alleged agreements above stated of appellant's agent, Early.

The findings of the jury were adverse to appellee as to the item of $4,510, and this feature of the case need not be noticed. Upon the issues arising as to the other items, the questions submitted and answers are as follows:

"Question No. 1: Do you find that after November 10, 1921, A. O. Peabody was carrying on the work of completing the New Mexico contracts, described in plaintiff's petition, as the agent of the defendant National Surety Company, by the authority and consent of such defendant? Answer `Yes' or `No.' Answer: Yes.

"Question No. 2: Do you find that on the 7th day of November, 1921, the defendant Dan La Roe was indebted to the plaintiff for the items described in plaintiffs petition, aggregating $878.50, or a part thereof? Answer `Yes' or `No.' Answer: Yes.

"If you answer `Yes' to the preceding question, then answer:

"Question No. 3: How much of such amount, if any, was Dan La Roe then indebted to plaintiff Rogers on said items? Answer: $878.50.

"Question No. 4: Do you find that the defendant, National Surety Company, agreed with Dan La Roe that if he would waive the 10 days' notice provided for in his contract, turn over to it his outfit, together with his materials and supplies on hand, and together with the 15 per cent. earned by said La Roe but retained by the state of New Mexico, and together with his certain unpaid estimates, that it would complete said work according to said contracts, and would pay all that said La Roe owed for road work, including $3,125.04 and $878.50, and that said La Roe accepted said proposal made to him by said National Surety Company of New York, and did waive said notice and did turn over to said defendant surety company all of his outfit, together with his materials and supplies on hand, and together with the 15 per cent. earned by said La Roe, but retained by the state of New Mexico, and together with his certain unpaid estimates? Answer: Yes.

"Question No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fort Worth & D. C. Ry. Co. v. Amason
239 S.W. 359 (Court of Appeals of Texas, 1922)
Texas v. Harrington
235 S.W. 188 (Texas Commission of Appeals, 1921)
Peveto v. Texas & N. O. Ry. Co.
238 S.W. 892 (Texas Commission of Appeals, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
257 S.W. 651, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-surety-co-v-rogers-texapp-1923.