National Surety Co. v. Grant County Board of Education

279 S.W. 662, 212 Ky. 475, 1926 Ky. LEXIS 177
CourtCourt of Appeals of Kentucky (pre-1976)
DecidedJanuary 19, 1926
StatusPublished

This text of 279 S.W. 662 (National Surety Co. v. Grant County Board of Education) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky (pre-1976) primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Surety Co. v. Grant County Board of Education, 279 S.W. 662, 212 Ky. 475, 1926 Ky. LEXIS 177 (Ky. 1926).

Opinion

Opinion op the 'Court by

Commissioner Sandidge

Affirming.

On July 11, 1919, appellee, Grant county board of education, let to Merriman & Willoughby a contract to erect a school building at Crittenden, Kentucky, in accordance with plans and specifications made part of the contract, at the price of $20,100.00. Appellant, National Surety Company, as surety, guaranteed the faithful performance of the contract to the extent of $5,OOOvOO This action was instituted by appellee against appellant upon that bond to recover $2,500.00, damages alleged to have been suffered by it as a result of the failure of Merriman & Willoughby to perform the contract. Appellant denied liability, and, after having been transferred to equity, the trial of the case below resulted in a judgment for appellee for $2,234.71. Appellant has appealed.

The bond executed by appellant, by its terms, recited that it was executed, among others, upon the following express condition, which should be precedent to the right of recovery:

“If at any time during the prosecution of the work specified in said contract to be performed *477 there come to the notice or knowledge of the obligee the fact that any claim for labor performed or for materials furnished the said principal m or upon said work remains unpaid or that any lien or notice of lien for such work or materials has been filed or served, the obligee shall withhold payment from the principal of any moneys due or to become due to the principal under said contract until the payment of such claim or the cancellation and discharge of such lien or notice of lien, if any, and will so notify the company, giving a statement of the particular facts and amount of each such claim, lien or notice of lien. ’ ’

Appellant claims to have been relieved of liability under the bond by appellee’s noncompliance with the conditions quoted. It is insisted that on September 18, 1919, it was brought to the attention of appellee that claims for labor performed for and materials furnished to the contractor were unpaid and that appellee failed to notify appellant and to withhold payment from the contractor until the payment of such claims, because of which appellant contends it is relieved of liability under the provisions of the contract quoted, supra. The evidence on that, question discloses that at that time a difference arose between the contractors and a subcontractor for the brick work as to how much was then due the latter for the work then done. That. difference was settled between the parties after a full discussion of it between them in the presence of the members of the Grant county board of education, and after the agreement was reached the amount found due the subcontractor on the order of the contractor was paid by appellee directly to the former and charged to the latter. The evidence clearly establishes that nothing with reference to that transaction was required by the quoted provision of the bond, supra, to be reported to appellant, and appellee’s failure to do so in no wise violated any of its provisions.

Again it is insisted that on November 21,1919, knowledge of the fact that claims for labor and materials, owing by the principal contractor were unpaid and that notices of lien for such had been filed and served upon appellee, and that it in violation of the provisions of the contract quoted supra, failed to notify appellant of those facts and to withhold payment from the contractor of *478 moneys due him, and thereby released it of its obligation under the contract. It relies on a letter of that date written by the. subcontractor for the brick work as furnishing evidence to sustain its contention. That letter introduced in evidence herein reads:

“Lexington, Ky., Nov. 21, 1919.
“■Beard of Education, Crittenden, Ky.
“Gentlemen: We attach herewith asknowledgment of H. T. Merriman, general contractor, for the erection of your school, for a balance due me as subcontractor under him for the brick work which I did, amounting to nineteen hundred forty-seven dollars and fifty-three cents ($1,947.53).
“I wish to take advantage of the protection given me under the mechanic’s lien law for this account and hereby request that you pay the above amount to me direct. All the above amount is for labor and materials used in the construction of the brick work.
“Yours truly,
O. B. Bishop. >r

The contents of the letter make it to appear that the general contractor and the subcontractor for the brick work had had a settlement and that it was found that $1,947.53 was due the latter for the brick work. A written, signed acknowledgment of that fact by the general contractor was inclosed with the letter. The closing paragraph of the letter speaks for itself. Immediately after receipt of the letter appellee, on the order of the contractor, paid $1,374.00 to that claimant, and subsequently paid to him the balance due. The amount so paid was charged to the general contractor in part settlement of the contract price of the building. Clearly this is not a case of claims for labor or materials remaining unpaid or of liens or notice of liens for same, within the provisions of the quoted portion of the contract such as required appellee to notify appellant. The amount due the subcontractor for the brick work seems then to have been ascertained for the first time and the greater part of it on the order of the g’eneral contractor was paid immediately by appellee and the remainder subsequently paid. It did not remain a claim unpaid within the pro *479 visions of the contract quoted, supra, requiring notice to appellant or withholding of funds. See National Surety Company v. Price, 162 Ky. 632, 172 S. W. 1072, where, in discussing this exact question, the court said:

“It will he observed that the bond does not fix a time that the claims shall remain unpaid. If the words should be held to apply to every claim remaining unpaid, without regard to time or demand on the part of the claimant, it is manifest that the very purpose of the bond would be defeated. It would impose upon the obligee the absolute duty of protecting the obligor, relieve the obligor of all liability under the bond. In our opinion, the claim must be due. There must be a demand for payment and either a refusal or a neglect to pay, for an unreasonable length of time, and the obligee should have notice or knowledge of these facts.”

No other instance in which it is claimed appellee violated the quoted portion of the terms of the bond is discussed by brief for appellant.

It is next insisted by appellant that the record contains no evidence of loss or damage by appellee with which it is chargeable under the terms of the bond, and that therefore the chancellor erred in awarding a judgment against it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

National Surety Co. v. Price
172 S.W. 1072 (Court of Appeals of Kentucky, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
279 S.W. 662, 212 Ky. 475, 1926 Ky. LEXIS 177, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-surety-co-v-grant-county-board-of-education-kyctapphigh-1926.