National Steel Service Center, Inc. v. Wollin Silos & Equipment, Inc.

284 N.W.2d 606, 92 Wis. 2d 133, 27 U.C.C. Rep. Serv. (West) 1246, 1979 Wisc. LEXIS 2183
CourtWisconsin Supreme Court
DecidedNovember 6, 1979
Docket77-222
StatusPublished
Cited by5 cases

This text of 284 N.W.2d 606 (National Steel Service Center, Inc. v. Wollin Silos & Equipment, Inc.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Steel Service Center, Inc. v. Wollin Silos & Equipment, Inc., 284 N.W.2d 606, 92 Wis. 2d 133, 27 U.C.C. Rep. Serv. (West) 1246, 1979 Wisc. LEXIS 2183 (Wis. 1979).

Opinion

Heffernan, J.

The principal question on this appeal is whether the failure of defendant, Wollin Silos & Equipment, Inc., to plead the defense of the statute of frauds as an affirmative defense precludes it from asserting that defense for the first time by a motion for directed verdict at the close of the case of the plaintiff, National Steel Service Center, Inc. We conclude that, under the rules of procedure applicable to this case, commenced prior to January 1, 1976, the defense of the statute of frauds was timely asserted. Because the statute of frauds was not satisfied, we affirm the judgment dismissing National Steel’s cause of action.

The plaintiff, National Steel, commenced this action on July 18, 1975, to collect an account arising out of a sale of steel. The action was brought against Wollin Silos and Becker Equipment Corporation. Becker Equipment declared bankruptcy in May of 1975 and a judgment of the bankruptcy court was entered on September 29, 1975, which appointed a receiver and enjoined all creditors, including National Steel, from proceeding further against Becker Equipment. Accordingly, in its present posture, the cause of action is only against Wollin Silos.

The trial was to a jury. At the close of National Steel’s case, however, the defendant, Wollin Silos, moved for a directed verdict on the ground that National Steel had failed to show as a matter of law that the sales contract complied with the statute of frauds, secs. 401.206 and 402.201, Stats. The trial court withheld its ruling on the motion. Wollin Silos renewed the motion for directed verdict after the presentation of its case and after National Steel had the opportunity to present some additional testimony. The court then withdrew the case from the jury, granted the motion on the grounds that there had been no compliance with the statute of frauds, and *136 entered judgment dismissing the action. It is from this judgment that National Steel appeals.

The record shows that Wollin Silos was in the business of manufacturing and erecting concrete silos. Its principal place of business was at Lake Mills, Wisconsin. Becker Equipment produced steel conveyors and farm feeding equipment and had its principal place of business at New London, Wisconsin. It was a user of unfabricated steel; Wollin Silos was not. Prior to the sale at issue in this case, Wollin Silos purchased a controlling interest in Becker Equipment; and Albert C. Wollin, Jr., who was the principal officer of Wollin Silos, became vice president of Becker Equipment. Gordon Becker remained as the president of Becker Equipment but was not an officer, employee, or agent of Wollin Silos.

The transactions giving rise to this lawsuit commenced in March or April of 1974, when Albert Wollin telephoned National Steel and spoke to William Wymelenberg, who was the inside sales manager. Wollin told Wymelenberg that he was an officer of Wollin Silos. Whether Wollin then disclosed his association with Becker Equipment is disputed. Wollin stated in general the type and amount of steel desired, but explained to Wymelenberg that Gordon Becker would call National Steel to detail the specifications of the steel. Wollin told Wymelenberg that the steel should be shipped to Becker Equipment in New London. Gordon Becker followed up on the call and discussed the details of the purchase of the steel. Becker detailed the specifications in a document captioned “Purchase Order, Becker Equipment Corporation, Steel Fabricators” and mailed it to National Steel.

Before the steel could be shipped, Wymelenberg was required to get the approval of Robert Tully, National Steel’s local credit manager. Wymelenberg testified that he told Tully that Albert Wollin had placed the order and had done so on behalf of Wollin Silos. The credit department did a credit check on Wollin Silos. The sale on credit was then approved, and the steel was shipped to Becker *137 Equipment in New London. National Steel mailed its invoice to Wollin Silos. The invoice, a computer print-out, stated that the steel was sold to Wollin Silos but shipped to Becker Equipment. No credit check was run on Becker Equipment at that time, and on its books National Steel never showed Becker Equipment as a customer.

Several sales followed thereafter, and in each case Albert Wollin called Wymelenberg and discussed the order, and Gordon Becker called later to provide the exact specifications. In each instance Becker then sent National Steel a document captioned “Purchase Order, Becker Equipment Corporation, Steel Fabricators.” National Steel shipped all the orders to Becker Equipment but sent the invoices to Wollin Silos.

This course of conduct continued and the same procedure was used in placing the order in this case in June of 1974. The order was filled and shipped in September of 1974. Because two shipments were made to fill that order, separate invoices were sent to Wollin Silos in the amounts of $4,420.31 and $3,633.47. These invoices were not paid.

According to National Steel’s credit manager, he called Wollin several times in October and November about the account, and on each occasion Albert Wollin promised payment. Wollin denied that he promised to pay National Steel and claims that he told Tully that the billing was incorrect and that the invoices should have been directed to Becker Equipment Corporation. The account was never paid, and this action was commenced on July 18, 1975, against both Wollin Silos and Becker Equipment. After the bankruptcy court’s order enjoining further proceedings against Becker Equipment, the trial proceeded only against Wollin Silos.

The answer of Wollin Silos denied that Albert Wollin ever ordered any steel on behalf of either Wollin Silos or on behalf of Becker Equipment.

The defense of the statute of frauds was not raised in the pleadings and was asserted for the first time at the *138 close of the plaintiff’s case. On this appeal, National Steel argues that the trial court erred when it took the case from the jury on motion for directed verdict, because the defense of the statute of frauds came too late and because the evidence at trial could reasonably have led the jury to find that an oral contract was made between Wollin Silos and National Steel which was valid in the absence of a timely statute of frauds defense. Alternatively, National Steel argues that, were this court to hold that the statute of frauds defense was timely asserted, nevertheless, the statute was satisfied, because the purchase order mailed by Becker Equipment to National Steel constituted “a writing in confirmation of the contract” “between merchants,” as provided by sec. 402.201(2), Stats.; and, additionally, the shipment of the steel to Becker Equipment made the contract enforceable, because the goods were “received and accepted” by Wollin Silos within the meaning of sec. 402.201 (3) (c).

Initially, we point out that there was evidence which, if believed, was sufficient for the jury to have concluded that there was an oral contract between National Steel and Wollin Silos. Wymelenberg testified that Albert Wollin called him, identified himself as a representative of Wollin Silos, and placed an order. This evidence, when examined in the light most favorable to the plaintiff, National Steel, would have been sufficient to defeat the motion for directed verdict had the defense of statute of frauds not been interposed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pilar Domer v. Menard, Inc.
116 F.4th 686 (Seventh Circuit, 2024)
Carl Wilson v. Leonard Reed
Court of Appeals of Wisconsin, 2023
Heideman v. Wirsing
840 F. Supp. 1285 (W.D. Wisconsin, 1992)
Weber v. Weber
485 N.W.2d 447 (Court of Appeals of Wisconsin, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
284 N.W.2d 606, 92 Wis. 2d 133, 27 U.C.C. Rep. Serv. (West) 1246, 1979 Wisc. LEXIS 2183, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-steel-service-center-inc-v-wollin-silos-equipment-inc-wis-1979.