National Quarries Co. v. Detroit, T. & I. R.

91 F.2d 80, 1937 U.S. App. LEXIS 4155
CourtCourt of Appeals for the Sixth Circuit
DecidedJuly 3, 1937
DocketNo. 7206
StatusPublished

This text of 91 F.2d 80 (National Quarries Co. v. Detroit, T. & I. R.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Quarries Co. v. Detroit, T. & I. R., 91 F.2d 80, 1937 U.S. App. LEXIS 4155 (6th Cir. 1937).

Opinion

MACK, Circuit Judge.

On this appeal from a judgment for defendant in an action for breach of contract, tried by the court after waiver of jury, the sole question is, as it was in the trial court, the proper interpretation of paragraph 3 of the contract dated June 14, [81]*811927.1 The special findings made in support of the court’s conclusion are for the most part restated in substance in the opinion of the late Judge Hahn from which we quote as follows:

“The contract is one of settlement between the parties. Plaintiff’s quarry lands lie on both sides of defendant’s track. Its crushing plant is located on the west side; * * * it could not work its property on the east side of the track without tunneling under defendant’s railroad track. This it did about 1922, without the consent of the defendant. * * * Defendant brought an action against plaintiff to quiet title to the lands that had been tunneled. Defendant was successful in that action in the lower court, and at the time [the contract] was executed, the action was pending in the state court of appeals on an application for a rehearing.
“Defendant had for several years prior to the execution of the contract of settlement contemplated improvements in its system, the making of a cutoff, which involved the use of 10.71 acres out of about 33 acres of plaintiff’s land lying east of defendant’s track. During the latter part of 1924, defendant brought an action to condemn this part of plaintiff’s land. Plaintiff then brought an action in this court seeking to enjoin further proceedings in the condemnation action. * * * This action terminated unfavorably to plaintiff. * * * Pending the proceeding in this court, plaintiff continued to operate its quarry, such operations involving to some extent the 10.71 acres defendant sought to condemn for railroad purposes.
“ * * * Defendant brought an action for an injunction to prevent further operation of the quarry, in the Court of [82]*82Common Pleas of Allen County, Ohio. An injunction was granted on condition that defendant furnish a bond against wrongful damages accruing to plaintiff here in the amount of $100,000.00. The bond was furnished and plaintiff’s quarry operations were stopped from about August 5, 1926, to April 22, 1927. At about that time, on deféndant’s own motion, the injunction theretofore granted was modified so as to permit plaintiff to operate that portion of its quarry lands lying east of defendant’s track which was not involved in the condemnation proceedings.
“Briefly and roughly, this was the background of. the parties when the contract of June 14, 1927, was executed. Various claims were being asserted against each other by the parties to that contract.
“ * * * The contract of June 14, 1927, has been fully executed and performed on both sides, with the exception only that the plaintiff claims that the defendant has not performed and fully car-, ried out its obligation under paragraph 3 of the contract. * * *'
“Within several weeks after the execution of the contract, engineers designated by the parties met and, agreed upon the area to be stripped in accordance with the parenthetical clause of paragraph 3. The area is that included within red lines upon [a map which] bears the legend: ‘Area to be stripped to rock within red boundary’ [and] the approval of the authorized engineers of both companies. A letter from Mr. Visscher, of the Legal Department of the defendant company [dated July 22, 1927] in referring to [this map] contains the following statement: ‘This blueprint shows the extent of the stripping which is agreed to be done under our settlement agreement, and is in compliance with paragraph 3 of the letter,’ etc.
“* * * The progenitor of paragraph 3 of the contract is found in paragraph 5 2 of a letter from the National Quarries Company to a member of the Legal Department of the defendant company. It proposed a settlement along the lines finally consummated [and] was sent on April 4, 1927.
“On June 14, 1927, the parties held a conference at Detroit, Michigan, [which resulted in the proposal in appellee’s letter of that date accepted by appellant].
“At the time this contract was entered into, plaintiff expected to continue in the business of quarrying stone and the defendant company fully expected to make an improvement by way of a cut-off, and this paragraph of the contract would have been mutually beneficial to the parties; whether there would be an excess of benefit to one or the other of the parties does not appear from the evidence.
“Some time after the contract of settlement was entered into between the parties, there was a change of management in the defendant company, and the defendant company in good faith changed its plans and decided not to build the cut-off for the building of which it might have required at least some of the dirt provided for by paragraph 3 of the contract.
“The plaintiff’s case was tried solely and only upon the theory that the defendant was absolutely required to strip the area within the red lines of Exhibit 2 and to take the dirt resulting from such stripping. There is no evidence upon which to base a recovery except upon that theory. It is undisputed that in the performance of the contract the defendant stripped 36,700 cubic yards of overburden. It also appears' that part of this dirt was used for diking purposes in accordance with the provisions of the contract. There is no showing in the evidence that defendant’s actual requirements exceeded this . amount, nor is there any showing that if defendant had not changed its plans as to the making of the improvement, further dirt would have been required.”

The following findings of fact supplement the foregoing statement:

“8. That part of plaintiff’s land which lay east of defendants original line * * * while suitable for quarrying purposes, had an overburden of dirt which had to be removed or stripped to uncover the surface of the stone.
“9. It was expected by both parties that when the new improvement would be [83]*83built, the defendant probably would need a large amount of dirt for fills and roadbeds between the point which the new improvement was to cross the existing Pennsylvania tracks and a point at the village of Cairo, Ohio.
“14. At the time this agreement was executed the defendant had acquired a part of the land which it needed for its new right-of-way, as appears by plaintiff’s Exhibit No. 4 in evidence. It did not know how much dirt would be required for fills and roadbeds between the village of Cairo and the Pennsylvania tracks, hut the parties expected that more would be needed for that purpose than the plaintiff’s lands could supply.
“21. On January 10, 1929, the defendant, by letter, requested plaintiff to relieve it from stripping the southwest corner of the area agreed upon, in consideration of defendant’s stripping an equal area southeast of the area agreed upon. This was by letter agreed to.
“22.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re United Cigar Stores Co. of America
72 F.2d 673 (Second Circuit, 1934)
In Re United Cigar Stores Co. of America
8 F. Supp. 243 (S.D. New York, 1934)
Consolidated Dairy Products Co. v. Irving Trust Co.
293 U.S. 617 (Supreme Court, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
91 F.2d 80, 1937 U.S. App. LEXIS 4155, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-quarries-co-v-detroit-t-i-r-ca6-1937.