National Lumber Co. v. Walsh

2007 Mass. App. Div. 65, 2007 Mass. App. Div. LEXIS 41

This text of 2007 Mass. App. Div. 65 (National Lumber Co. v. Walsh) is published on Counsel Stack Legal Research, covering Massachusetts District Court, Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Lumber Co. v. Walsh, 2007 Mass. App. Div. 65, 2007 Mass. App. Div. LEXIS 41 (Mass. Ct. App. 2007).

Opinion

Coven, J.

Plaintiff National Lumber Company (“National Lumber”) supplied lumber and building materials to defendant Jess Walsh (‘Walsh”) for use in connection with improvements to the home of defendants Arthur and Murielle Berke (the “Berkes”). To recover payment for the goods sold, National Lumber brought this action against Walsh for breach of contract damages and against the Berkes to enforce a mechanic’s lien on their property. Walsh was defaulted. After trial, judgment was entered for the Berkes. This appeal by National Lumber followed.

The material facts are not in dispute. In April of 2002, Walsh established a credit line with National Lumber that allowed him to purchase lumber and building materials from the plaintiff. Walsh personally guaranteed the payment of all charges. In March of 2003, Walsh signed a “Material Supply Contract” with National Lumber in which Walsh expressed his intention to purchase construction materials to be used on a project at 26 Crestwood Road in Newton. The property identified is owned by the Berkes. Between April and July, 2003, National Lumber sold and delivered lumber and building materials to Walsh on credit for use at the Berkes’ property.

On September 15,2003, National Lumber recorded in the Registry of Deeds its G.L.c. 254, §4 notice of contract against the Berkes’ property. On September 29, 2003, it recorded its sworn statement of claim pursuant to G.L.c. 254, §8. The claimed amount listed in both filings was $7,423.53. There is nothing in the trial evidence to indicate when National Lumber informed the Berkes of its filing of the notice of contract.3

This action was commenced on December 18, 2003. As noted, Walsh was defaulted and the case against the Berkes proceeded to trial on December 19, 2005. National Lumber’s Chief Executive Officer and Walsh testified on behalf of the plaintiff at trial. The Berkes did not call any witnesses. Walsh testified as to his execution of a written building contract with the Berkes for improvements to their home with a construction starting date in September, 2002. He indicated that the Berkes then terminated the contract because the pace of construction was “approximately nine/ten months late.” Walsh stated that the balance due on the [66]*66general contract at the time of its termination was $30,000.00.4

The Berkes eventually recovered an arbitration award against Walsh, which was confirmed in a superior court action. Walsh testified in that action that some of the building materials upon which National Lumber based its asserted lien in this case were not used at the Berkes’ residence.

1. The Berkes raised as a defense at trial National Lumber’s failure to introduce the general contract into evidence and to prove the dollar amount of its lien. Both the Berkes and National Lumber argue on this appeal that G.L.c. 254 requires, and the judge so found, that a subcontractor must introduce into evidence the written contract between a homeowner and the general contractor in order for judgment to be entered in favor of the subcontractor on its claim to enforce a mechanic’s lien.5 We disagree that this issue was the basis of the trial court’s judgment for the Berkes.

BloomSouth Flooring Corp. v. Boys’ & Girls’ Club of Taunton, Inc., 440 Mass. 618 (2003), supports the result reached by the trial judge in this case. At the time National Lumber gave notice to the Berkes of the filing of its subcontract, no amount was due or to become due under Walsh’s contract with the Berkes. In BloomSouth, there was a written agreement between the defendant-Club and a general contractor for the construction of a child care facility on the Club’s property. The general contractor abandoned the project, and its contract was terminated by the Club. The unpaid balance on the general contract exceeded $170,000.00, of which nearly $75,000.00 was retained by the Club pursuant to contract provisions. BloomSouth, the plaintiff-subcontractor, filed the required notice of subcontract after the termination of the general contract and within the time then allowed by statute.6 The issue before the Court was whether a motion for summary judgment was properly allowed in favor of the Club because, as of the date of the filing of the notice of subcontract, there was no “amount ‘due or to become due’ under” the contract between the general contractor and the Club. Id. at 620.7 The Supreme Judicial Court in BloomSouth construed the §4 phrase “due or to become due” in accordance with the ordinary meaning of those words.

Webster’s Third New Inti Dictionary 699 (1993) defines the adjective ‘due’ as ‘(1): owed or owing as a debt; (2) (obs.): owed or owing as a [67]*67necessity ... (3) a: owed or owing in accordance with natural or moral right.’ Black’s Law Dictionary 499 (6th ed. 1990) defines ‘due’ as [o]wing; payable; justly owed. That which one contracts to pay or perform to another; that which law or justice requires to be paid or done.’

Id. at 622-623. Concluding that “the phrase ‘to become due’ means ‘to become owed’ or ‘to become payable,”’ Id. at 623, the Court held that “[b]y abandoning the project... [the general contractor] committed a wilful default that terminated any right it may have had to further payment under the contract.” Id. The Court also noted that there was no argument that the general contractor had “performed substantially under the contract so as to justify further payment.” Id.

This case is similar. Nothing in the evidence compelled the trial court to believe that any money was due under the general contract between Walsh and the Berkes at the time National Lumber gave notice of its filing of its subcontract. Walsh testified that he began his contract work in September of 2002 and was terminated some nine or ten months later because of delays in project completion. National Lumber’s notice, presumably,8 was provided two to three months after termination of the general contract. Given the judgment against Walsh, it would appear that he had no money due or to become due to him after the date of contract termination. In other words, the evidence permitted the conclusion that at the time of National Lumber’s notice to the Berkes of the filing of its subcontract, there was no amount “[o]wing, payable; [or] justly owed” to Walsh. Nor was there any evidence that Walsh substantially completed the general contract work so as to be entitled to any payment.

2. National Lumber also charges error in the denial of its pretrial motion to amend its complaint. That motion, supported by exhibits, indicates that on October 28, 2003, the Berkes initiated a G.L.c. 142A arbitration proceeding against Walsh alleging numerous contract breaches by him. The Berkes filed a statement of damages in the amount of $60,949.72, which included a claim for National Lumber’s mechanic’s lien damages in the amount of $7,423.53.

The Berkes and Walsh agreed on the entry of an arbitration award of $61,000.00 against Walsh, and then entered into a settlement agreement in May, 2004 secured by a mortgage given by Walsh on property owned by him and his wife. The settlement agreement provided that if Walsh paid $45,000.00 within 120 days of settlement, the Berkes would agree to accept that sum as full payment. If Walsh failed to make a timely offer, the arbitration award of $61,000.00 would stand.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rae v. Air-Speed, Inc.
435 N.E.2d 628 (Massachusetts Supreme Judicial Court, 1982)
Hamed v. Fadili
556 N.E.2d 1020 (Massachusetts Supreme Judicial Court, 1990)
Choate, Hall & Stewart v. SCA Services, Inc.
392 N.E.2d 1045 (Massachusetts Supreme Judicial Court, 1979)
Harvard Law School Coalition for Civil Rights v. President & Fellows of Harvard College
595 N.E.2d 316 (Massachusetts Supreme Judicial Court, 1992)
Bloomsouth Flooring Corp. v. Boys' & Girls' Club of Taunton Inc.
800 N.E.2d 1038 (Massachusetts Supreme Judicial Court, 2003)
Smola v. Higgins
679 N.E.2d 593 (Massachusetts Appeals Court, 1997)
Mancuso v. Kinchla
806 N.E.2d 427 (Massachusetts Appeals Court, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
2007 Mass. App. Div. 65, 2007 Mass. App. Div. LEXIS 41, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-lumber-co-v-walsh-massdistctapp-2007.