National Landscaping Co. v. Continental Casualty Co.

238 F. Supp. 793, 1965 U.S. Dist. LEXIS 6427
CourtDistrict Court, W.D. Missouri
DecidedMarch 5, 1965
DocketNo. 1996
StatusPublished
Cited by2 cases

This text of 238 F. Supp. 793 (National Landscaping Co. v. Continental Casualty Co.) is published on Counsel Stack Legal Research, covering District Court, W.D. Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Landscaping Co. v. Continental Casualty Co., 238 F. Supp. 793, 1965 U.S. Dist. LEXIS 6427 (W.D. Mo. 1965).

Opinion

JOHN W. OLIVER, District Judge.

This case presents a question not heretofore decided in any of the other Fort Leonard Wood Capehart cases. Consistent with the pattern of pre-trial procedures that has been followed in connection with the numerous cases involved in that litigation, the parties have entered into a stipulation of fact and have isolated for pre-trial determination the particular question of law presented in order that further proceedings be simplified.

Briefly stated, the stipulation establishes that plaintiff, National Landscaping Company, Inc. was awarded the $80,000.00 seeding and sodding subcontract by D & L, the prime contractor, who in turn was bonded by defendant Continental Casualty Company, Inc.

National’s complaint alleged that “the plaintiff complied with the terms and conditions of the [subcontract] and furnished labor and materials on [the] project in the amount of $80,000.00” (paragraph 8 of plaintiff’s complaint) and that D & L, the prime contractor, “failed and refused to pay the balance due and owing the plaintiff on said contract in the amount of Forty Thousand, Six Hundred, Twenty-Four and 2%oo Dollars ($40,-624.23)” (paragraph 9 of plaintiff’s complaint). Judgment for that amount, of course, is prayed for against the defendant surety on its bond.

The answer of the defendant expressly denied that “plaintiff complied with the terms and conditions of the [subcontract] and affirmatively alleges that this plaintiff breached, failed and refused to carry out and perform the obligations incumbent upon it under the terms of said contract, the damages proximately resulting therefrom to defendant’s principal and the cost to said principal in completing and remedying such defaults and failure far exceeding any sums otherwise due this plaintiff for the performance thereof” (paragraph 8 of defendant’s answer).

[794]*794The question presented for pre-trial decision is whether, under the stipulated facts and applicable law, National, the subcontractor, is entitled to recover for labor and material furnished by it on the job after D & L, the prime contractor, allegedly declared a default and allegedly terminated the subcontract.

Various paragraphs of the stipulation detail the sad history relating to the execution of the subcontract. Paragraph 17(a) of the stipulation and the exhibits referred to therein establish that “D & L and National were involved in disputes over the manner, extent, and timeliness of the performance of the work of the subcontract almost from its inception.” The subcontract was executed August 19, 1959 (Exhibit 3).

Paragraph 17(b) of the stipulation and exhibits 13 and 14 reflect that finally “D & L notified National on or about September 5, 1962, of certain alleged deficiencies in the performance of the work by National and of its intent to declare a default under the terms of the aforesaid subcontract on or about September 10, 1962.” That paragraph also states that on September 11, 1962, D & L advised National that it had “failed to correct [its] default set forth in [¶] & L’s] letter of September 5, 1962,” and that “therefore, any rights you may have had under such subcontracting agreement are hereby terminated.” As will be later noted, the action above taken had been threatened many times before.

It is also stipulated, however, that in spite of the alleged declaration of default and termination, National in fact continued to perform certain work on the job until December 7, 1962, and that D & L had actual knowledge of and permitted that work to be performed. The parties further agree that the factual basis for their respective and conflicting contentions are fully set out in certain correspondence exchanged by them and attached to the stipulation as Exhibits 15, 16 and 17, all of which we will discuss later in detail.

Paragraph 17(b) (iv) of the stipulation fairly outlines the mixed question of fact and law presented for our pretrial decision. It is there stated that:

“National urges that these communications [Exhibits 15,16 and 17] constituted a novation or modification of the original subcontract or a waiver by D & L of its rights to the remedies provided therein on default by National. Continental, on the other hand, submits that the continuance by National on the job was permitted under such correspondence ‘in order to minimize damages’ resulting from National’s default, and in exercise of the rights conferred on D & L by the subcontract to get the work done. (Exhibit 3, Paragraphs 4 and 16).”

The parties also agree that “should the Court conclude that the circumstances and documents * * * constitute a novation or modification of the subcontract, or waiver by D & L of its rights thereunder, then the extent, manner and timeliness of National’s performance of the subcontract would be of importance only in measuring the value of National’s work for purposes of recovery on the Continental bonds sued upon (Exhibits 1 and 2), if the Court should find and rule that National is entitled to only the value of its work performed and not the balance due under the contract.”

The parties further agree that should such a finding and determination be made, then “National would be entitled to recover the value [of its work] (not to exceed the unpaid balance of the contract price), after allowing the expenses incurred by D & L in completing the work of the subcontract as a credit” (Paragraph 17(a) of the stipulation).

As will be made more apparent when we discuss Exhibits 15, 16 and 17 in detail, it is clear that the basic contention of defendant Continental is that it is entitled to the full benefit of the alleged default and termination declared by D & L and that it is in no way liable for any work done after that time by National. National’s basic contention is that either by way of “novation,” “modification,” or by “waiver,” or perhaps by a combina[795]*795tion of the legal theories expressed by those or similar words, it has the right to recover in accordance with what it claims is the agreement of the parties ■spelled out in Exhibits 15, 16 and 17.

We have reviewed all of the lengthy correspondence and the voluminous documentary evidence attached to the stipulation but do not find it necessary to make specific comment on the details revealed by that mass of material. By way of general and introductory comment, we believe it is only necessary to refer to what was said in Carrier Corp. v. United States, (Ct. of Cl.1964) 328 F.2d 328, for an apt description of what all of the .stipulated facts establish beyond reasonable doubt. Chief Judge Jones there stated that “[i]n the tangled skein of facts and chaos of discussion and letters, it is difficult to weave anything other than a confused pattern” (page 334 of 328 F.2d).

Exhibit 15, however, established that in .spite of the default and termination allegedly declared in early September, 1962, National was nevertheless permitted to ■continue to work on the job and that the parties did in fact attempt to bring some order out of the general chaos of the job in their telephone conversation of October 30,1962.

Exhibit 15 is a letter from Mr. Fitzpatrick, Continental’s attorney, dated October 31, 1962. In that letter Mr. Fitzpatrick confirmed that in the telephone conversation of October 30, 1962, with National’s president, Mr. Slattery, “it was agreed” that National “would furnish the trees necessary to replant dead trees in Mortgage Area C-9 and all the trees in mortgage area C-10.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Burden v. Hummel (In Re Hummel)
23 B.R. 8 (W.D. Missouri, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
238 F. Supp. 793, 1965 U.S. Dist. LEXIS 6427, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-landscaping-co-v-continental-casualty-co-mowd-1965.