National Labor Relations Board v. Local 825, International Union of Operating Engineers, Afl-Cio

326 F.2d 213, 55 L.R.R.M. (BNA) 2112, 1964 U.S. App. LEXIS 6798
Court of Appeals for the Third Circuit·Decided January 8, 1964·No. 14331_1·Published·Cited by 25 cases

Opinion

STALEY, Circuit Judge.

The National Labor Relations Board has found that respondent, Local 825, International Union of Operating Engineers, AFL-CIO, violated § 8(b) (4) (i) and (ii) (D) of the National Labor Relations Act, as amended. 1 More particularly, the Board found that respondent engaged in conduct proscribed by that section with the object of forcing or requiring Nichols Electric Company to assign certain work to it rather than to electricians employed by Nichols. 140 N.L. R.B. No. 48 (1963). The case is here on the Board’s petition for enforcement of its order entered pursuant to that determination.

The events giving rise to this dispute occurred at the site of the construction of a reservoir in Clinton, New Jersey. Elmhurst Contracting Company was the general contractor on this project. It subcontracted the drilling and excavation work to Selby Drilling Company. Elmhurst and Selby each had a collective bargaining agreement with respondent in which that union was recognized as the exclusive bargaining representative of all employees engaged in the operation of power equipment specified in a schedule attached to that agreement. Included in the specified list were winch trucks and post hole diggers. Each agreement purported to bind all subcontractors of any *215 employer who was a party to it and stated that any employer who sublet any of his work did so subject to the terms and conditions of the agreement.

Selby subcontracted the erection of certain electrical transmission lines on the project to Nichols. Nichols had no collective bargaining agreement with respondent; its employees were represented by the International Brotherhood of Electrical Workers (“IBEW”). On May 3, 1961, six of these employees came upon the construction site to erect and wire electrical pole lines. In brief, this requires digging a hole in the ground, standing the pole firmly in it, and stringing electrical transmission lines from pole to pole. As was its usual practice, Nichols proposed to do this with the aid of a line truck equipped with a power-driven auger and winch. In this operation, the auger, which is attached to the rear of the truck, is set in position and, by means of power supplied from the truck or from another source, advances into the hole and removes the dirt. A power driven A-frame and winch is then set in position on the rear of the truck and is used to place the electric line pole into the hole.

As the operation was about to begin, Gatti, the shop steward of Local 825 employed by Elmhurst, informed O’Brien, Nichols’ foreman, that the devices could not be operated without operating engineers. When O’Brien disputed this, further discussion was had with Bates, the lead engineer employed by Elmhurst. Bates cited respondent’s contract with Selby as showing that the operating engineers were entitled to the work. In the meantime a number of operating engineers gathered around the vicinity of the power auger. At the instance of Bates, two operating engineers were sent to the job site, but O’Brien refused to hire them because the business agent for the electricians had informed him by telephone that the electricians were entitled to the work. O’Brien discussed the problem with Kangas, Selby’s job superintendent, who suggested that the holes be dug by hand.

The machines were removed from the job site, and no work was done that day, but the Nichols crew returned on May 9, again with the line truck, to commence drilling operations. Gatti then summoned various operating engineers employed by Elmhurst and Selby and told them to prevent the operation of the auger. 2 The operating engineers gathered around the machine and cited their contract with Selby as indicating that they were entitled to the work. O’Brien again discussed the problem with Kan-gas who was unable to resolve it with Gatti. Kangas repeated his suggestion that the holes be dug manually. O’Brien removed the machine from the job site, and subsequently completed the digging by hand.

On May 11, 1961, Nichols filed the unfair labor practice charges which resulted in the order of the Board presently under consideration. In addition, Nichols filed other charges alleging that the same conduct on the part of respondent constituted a violation of the secondary boycott provisions of the Act. 29 U.S. C.A. § 158(b) (4) (i) and (ii) (B). The Board agreed, and its petition for enforcement of the order entered in that case was consolidated with this proceeding for the purpose of oral argument in this court. However, though the cases *216 arise out of the same set of factual circumstances, they pose distinct legal issues which require consideration in separate opinions. Accordingly, except where specifically noted, we deal in this opinion only with the questions raised by the finding of a violation of the jurisdictional dispute section of the statute. 29 U.S.C.A. § 158(b) (4) (i) and (ii) (D).

In accordance with § 10 (k) of the Act, 29 U.S.C.A. § 160(k) 3 the Board first conducted a hearing to determine the merits of the jurisdictional dispute. This resulted in a determination that the electricians were entitled to the work. When respondent refused to comply with this determination, the complaint alleging a violation of § 8(b) (4) (i) and (ii) (D) was filed. The parties agreed that the only evidence to be adduced at the hearing on that complaint would be the record in the § 10 (k) proceeding, together with the record in the secondary boycott hearing. They further stipulated that the trial examiner should credit the testimony of the General Counsel’s witnesses, notwithstanding the testimony of any witnesses for respondent. The trial examiner’s finding of a violation of § 8(b) (4) (i) and (ii) (D) was adopted by the Board.

We are met, in limine, with respondent’s contention that the Board’s determination in the § 10 (k) proceeding was invalid for the reason that Local 825 had submitted the dispute to the National Joint Board for the Settlement of Jurisdictional Disputes which had rendered a decision assigning the work to the operating engineers. However, Nichols had previously notified the Joint Board that it would not recognize any decision rendered by it, and the IBEW reaffiliated with the Joint Board in 1956 upon the express condition that it would not be bound by decisions involving electrical line transmission work. Accordingly, the Board found that the parties had not agreed upon a method for adjusting their dispute.

In essence, respondent argues that both Nichols and the IBEW were without power to refuse to submit the dispute to the Joint Board because of their affiliation with it. But the rules of that body require contractors first to file a stipulation in which they agree to be bound by the decision of the Joint Board. No such stipulation was filed by Nichols- or the contractors’ association of which it is a member. Moreover, not only had the IBEW expressed its refusal to be bound by Joint Board decisions of this nature, but the record indicates that it was never notified of the submission of this dispute, nor did it participate in the proceedings. Certainly, in these circumstances, it cannot be held to be bound by the decision rendered by the Joint Board.

Free access — add to your briefcase to read the full text and ask questions with AI

National Labor Relations Board v. Local 825, International Union of Operating Engineers, Afl-Cio, 326 F.2d 213, 55 L.R.R.M. (BNA) 2112, 1964 U.S. App. LEXIS 6798 (3d Cir. 1964).

326 F.2d 213 (National Labor Relations Board v. Local 825, International Union of Operating Engineers, Afl-Cio) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Bechtel Corp. v. Local 215, Laborers' International Union
405 F. Supp. 370 (M.D. Pennsylvania, 1975)
No. 21299
378 F.2d 33 (Ninth Circuit, 1967)