National Labor Relations Board v. Getlan Iron Works, Inc.

377 F.2d 894, 65 L.R.R.M. (BNA) 2398, 1967 U.S. App. LEXIS 6260
CourtCourt of Appeals for the Second Circuit
DecidedMay 23, 1967
Docket30918_1
StatusPublished
Cited by11 cases

This text of 377 F.2d 894 (National Labor Relations Board v. Getlan Iron Works, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Labor Relations Board v. Getlan Iron Works, Inc., 377 F.2d 894, 65 L.R.R.M. (BNA) 2398, 1967 U.S. App. LEXIS 6260 (2d Cir. 1967).

Opinion

FEINBERG, Circuit Judge:

The National Labor Relations' Board petitions for enforcement of its order requiring respondent Getlan Iron Works, Inc. (“the Company”), inter alia, to bargain with one union and to withdraw recognition from another. Because this is one of those rare instances where we find a lack of substantial evidence to support one of the Board’s key findings, we decline to enforce the order to bargain and remand for further findings; as to the latter portion of the order, we grant enforcement.

The pertinent facts as stated by the Board 1 were as follows: The Company, controlled by its president Marvin Getlan, manufactures iron and steel building construction products. The working force consists of shopmen who fabricate the products and crews who install them in buildings. The unit involved in this proceeding is the former; it varies from five to twelve men. In 1959, these shop employees were organized by Shopmen’s Local Union No. 455 of the International Association of Bridge, Structural and Ornamental Iron Workers, AFL-CIO, which signed a contract with respondent that year. Another contract was signed thereafter, covering July 1961 to June 30, 1964. This contract was the general agreement Local 455 had with about 200 employers in the area; half belonged to a trade association which did the principal bargaining with Local 455. In the past, non-member employers (“independents”) like respondent accepted the terms agreed upon by the association and Local 455.

In April 1964, Local 455 wrote all employers giving notice of termination in June; during June, it gave copies of a proposed new agreement to them, stating that “independents” would no-longer be able to await the outcome of the bargaining with the trade association. No serious negotiations were conducted during June, and on July 1, Local 455 notified the employers that the old contract was being extended to July 10, the terms of the new contract to be retroactive to July 1. On July 2, respondent, met with representatives of the local and approved part and rejected part of the proposed agreement; a future meeting,, with no date set, was agreed upon. Since negotiations with the trade association were pending and the employees were working under the expired contract, there was no urgency. A somewhat changed proposed agreement was sent, to the independents on July 15.

On July 22, Local 455 voted to strike-those employers who had not signed the; extension, and the following morning,, with no prior notice to the Company,, its employees gathered outside the plant. On arriving, Getlan asked the shop steward what had happened; the latter told him that since the Company-had not signed a contract, the employees: were on strike. The steward assured' Getlan that a business agent would be-there later in the day to straighten, things out, but he never arrived. Regular picketing continued for two weeks,, and then became intermittent; meanwhile the Company’s other employees, worked and material left the plant. On: the day the strike began, the Company had eight workers in the unit, and a foreman who resigned that day. Five were members of Local 455; all struck except one employee who was not a member of the local.

Up to this point, it would be difficult to characterize what had taken place as; serious bargaining by Local 455 with, the Company, a small independent. The: local was focussing its efforts on the trade association and the larger independents. Indeed, the Board concedes, that the Company had not yet done any *896 thing wrong, and the strike against it was at that time economic in nature.

However, on July 27, Local 455 asked respondent to be at a previously scheduled arbitration meeting (dealing with a grievance) a little early to carry on negotiations. Getlan arrived early at the meeting the next day, settled the grievance, and began negotiating. Some proposals by the union would have continued provisions of the old contract; Getlan agreed to some of those and objected to others. There was also disagreement about the term of the new contract. During the few weeks after July 28, Getlan and his general manager made efforts to persuade various employees to return to work.

About a week after the July 28 meeting, respondent advertised for workers in a local newspaper. One Iacono was subsequently hired on August 15, and told that the job was permanent. For the two weeks beginning August 27, most of respondent’s employees worked. Late in August, Getlan talked with his general manager about a new union, Industrial Production Employees Union, Local 42, AFL-CIO, and its president Gerald Lasky. A few days later, Getlan introduced Lasky to his manager and told him that he and Lasky were “bargaining” for a contract. Thereafter, the manager encouraged the employees to sign up with Local 42. Lasky obtained signed authorization cards from four of the eight employees working in the shop, and shortly thereafter the Company executed a contract with Local 42. The contract contained union security and check-off provisions; in accordance with it, the Company subsequently began withholding monies from the pay checks of the shop employees for union dues and initiation fees and paid these sums over to Local 42.

On these facts and others discussed in greater detail below, the trial examiner and the Board found that the Company had, inter alia, violated sections 8(a) (5) and (1) of the Act by its failure to bargain in good faith with Local 455 on and after July 28, by its execution of a contract with Local 42 when that union was not the authorized representative of the employees, and by its solicitation of and promise of benefits to striking employees to abandon the strike. The Board also found that the Company violated section 8(a)(1), (2) and (3) of the Act by aiding and assisting Local 42 in its attempts to secure authorization cards from employees and by enforcing the union security and checkoff provisions of the contract with Local 42. The Board entered the usual cease and desist and posting of notice order and affirmatively required the Company to withdraw and withhold recognition from Local 42 and to bargain upon request with Local 455. The Board also ordered the Company to reimburse all employees for dues and other sums collected under the Local 42 contract. In addition, the Board, having determined that the Company’s actions converted the July 23 strike into an unfair labor practice strike on July 28, ordered it to reinstate striking employees, discharging, if necessary, persons hired since July 28. 155 N.L.R.B. 1052 (1965).

We need not tarry long over the portion of the order involving Local 42. Respondent conceded in this court that its recognition of that local violated section 8(a)(2) of the Act. That section prohibits contributing financial or other support to a union, which respondent obviously did. The Board was therefore correct in requiring respondent to cease and desist from recognizing Local 42 and prohibiting respondent from giving effect to the Local 42 contract, including enforcing the check-off. 2 Respondent contends that the order requiring reimbursement of employees for dues and other monies ■ collected under the illegal contract with Local 42 should be enforced only vis-á-vis one employee as to whom coercion to join the union by respondent is admittedly supportable on the record. However, it was within the *897

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
377 F.2d 894, 65 L.R.R.M. (BNA) 2398, 1967 U.S. App. LEXIS 6260, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-labor-relations-board-v-getlan-iron-works-inc-ca2-1967.