National Group for Communications & Computers Ltd. v. Lucent Technologies International Inc.

331 F. Supp. 2d 290, 2004 U.S. Dist. LEXIS 16165, 2004 WL 1825228
CourtDistrict Court, D. New Jersey
DecidedMarch 1, 2004
DocketCivil Action 00-86 (JLL)
StatusPublished
Cited by6 cases

This text of 331 F. Supp. 2d 290 (National Group for Communications & Computers Ltd. v. Lucent Technologies International Inc.) is published on Counsel Stack Legal Research, covering District Court, D. New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Group for Communications & Computers Ltd. v. Lucent Technologies International Inc., 331 F. Supp. 2d 290, 2004 U.S. Dist. LEXIS 16165, 2004 WL 1825228 (D.N.J. 2004).

Opinion

LINARES, District Judge.

Plaintiff National Group for Communications and Computers Ltd. (“NGC”) filed suit against Lucent Technologies International, Inc. (“Lucent”) for the alleged breach of a telecommunications construction subcontract. Because significant aspects of Plaintiffs claim hinge upon an interpretation of Saudi Arabian law, in October 2002 Magistrate Judge Hedges directed the parties to submit their respective experts’ opinions on how Saudi Arabian law would construe Plaintiffs claim for damages stemming from the termination of its Projects Department as a result of the alleged contractual breach. In accordance with its September 25, 2003 Order, this Court conducted a hearing on December 15 & 17, 2008 wherein expert testimony was heard from both parties regarding the application of Saudi Arabian law to the circumstances in this case. This Opinion constitutes the Court’s Findings of Fact and Conclusions of Law regarding said hearing pursuant to Rule 52(a) of the Federal Rules of Civil Procedure. For the reasons discussed herein, this Court finds that the findings of fact and conclusions of law reached indicate that under the law of Saudi Arabia, Plaintiff is prohibited from collecting damages for the loss of its Projects Department beyond the loss in actual value of the Department’s existing assets. Consistent with its previous Order, this Court reserves judgment on the precise valuation of NGC’s Projects Department.

Findings of Fact

A. Underlying Events

As agreed by the parties, this Court has “assumed” for the purposes of the resolution of the issue now before it that Defendant breached the subcontract in dispute and that this breach caused the loss of Plaintiffs Projects Department. Therefore, the following findings of fact shall not be dispositive on the contractual issues of breach and causation, matters which will be decided at trial, but speak only to the proper award of damages under Saudi Arabian law.

On August 13, 1994, Defendant’s corporate predecessor, AT & T International, Inc., entered into a $4.6 billion contract with the Saudi Arabian Ministry of Post Telephone and Telegraph (which later became the Saudi Telecom Company), a contract involving the Saudi government’s sixth telecommunications project (“TEP-6”). On April 5, 1995, Plaintiff NGC, a Saudi Arabian corporation, entered into contract No. 220806 (the “Subcontract”) with Defendant as part of the larger expansion project. According to the terms of the Subcontract, Plaintiff was to implement the Roadside Emergency Telephone and Wayside Facilities Projects (“RET/WSF Projects”) in Saudi Arabia by performing design and engineering services and installing emergency and pay telephones along Saudi Arabia’s highways and nearby facilities. The Subcontract provided for a four year contractual relationship at a fixed price of $75,460,902.

For reasons that remain disputed in the underlying litigation, and need not be resolved in the present analysis, the RET/ WSF Projects were never completed and the Subcontract was ultimately terminated in the summer of 1999. As the alleged direct result of this contractual termination, Plaintiff liquidated its Projects Department during the fourth quarter of 1999. The Projects Department had been created to implement Plaintiffs telecommunications contracts, including the Subcontract. It included staff and labor under contract, offices, equipment, vehicles, and *293 warehouses. Soon after these events took place, the present lawsuit was filed.

B. Background, on Valuation of Projects Department

Beginning in August 1998, Plaintiff attempted to attract outside capital by preparing for a private placement of a portion of its equity. Plaintiff engaged Riyad Bank to act as the lead bank in this private placement and to carry out a professional valuation of NGC. Riyad Bank completed two valuations in late 1998, appraising the Projects Department at $153.0 million and $173.8 million, respectively. (“Riyad Bank Valuation Analysis,” Pl.Ex. 5-7)

In the fall of 1998, Kingdom Holding Company Ltd. (“Kingdom Holding”) became interested in purchasing equity in Plaintiff NGC. As part of its investigation, Kingdom Holding requested that its accountant, Arthur Andersen, review the Ri-yad Bank valuations and to prepare its own. Arthur Andersen completed its assessment on January 9, 1999, and valued the Projects Department at $112.3 million. On May 9, 1999, Kingdom Holding agreed to purchase 25.4% of Plaintiff company for a fixed price per share and acquired options to acquire another 15.6% at the same price. These options were never exercised. Extrapolating from this purchase price basis, the value of the entire Projects Department would be fixed at $111.7 million.

As part of this lawsuit, Plaintiffs valuation expert has determined that the value of NGC’s Projects Department as of June 30, 1999 was $101,170,591. (“Deck of R. Christopher Rosenthal”, PL’s Exh. 1). Once discounting this amount for duplica-tive items of damage subsumed under other claims, the expert calculated the adjusted value of NGC’s claim for loss of the Projects Department to be $92,319,579. Plaintiffs expert employed five methodologies to arrive at his ultimate valuation. Three of these methodologies were based respectively on the two Riyad Bank valuations and the Arthur Anderson valuation. The fourth methodology, the so-called “Guideline Company Method,” used data on five publicly traded companies with businesses comparable to NGC’s Projects Department, and generated a valuation of $105,064,296. The fifth methodology, the “Kingdom Holding Method,” was based on the price per share of NGC equity actually paid by Kingdom Holding on May 9, 1999. The valuation by Plaintiffs expert was created by applying different weights to each of these methodologies — 40% to the Kingdom Holding Method, 30% to the Guideline Company Method, and 10% to each of the Riyad Bank and Arthur Andersen valuations. (R. Christopher Rosenthal, Transcript of Oral Arguments on December 15th and December 17th (hereinafter “Tr.”), 30:18-23).

Conclusions of Law

A. Legal Framework

Both parties agree that the law of Saudi Arabia covers this contractual dispute. This conclusion stems from the terms of the Subcontract which include the following choice of law provision:

This Subcontract is subject to the regulations in force in the Kingdom of Saudi Arabia. Interpretation and execution of the Subcontract and settlement of claims arising therefrom shall be subject to and in accordance with the said regulations.

(Def. Ex. 14A, Tab 3, Art. 8). Therefore, it is incumbent upon this Court to determine how Saudi Arabian law would apply to the present case, more particularly, how Saudi Arabian law would construe Plaintiffs claim for the loss of its Projects Department.

Federal Rule of Civil Procedure 44.1 governs the judicial determination of foreign law. Rule 44.1 states that when *294

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
331 F. Supp. 2d 290, 2004 U.S. Dist. LEXIS 16165, 2004 WL 1825228, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-group-for-communications-computers-ltd-v-lucent-technologies-njd-2004.