National Fuel Gas Distribution Corp. v. Pennsylvania Public Utility Commission

587 A.2d 54, 137 Pa. Commw. 621, 1991 Pa. Commw. LEXIS 88
CourtCommonwealth Court of Pennsylvania
DecidedFebruary 14, 1991
Docket1645 C.D. 1989
StatusPublished
Cited by11 cases

This text of 587 A.2d 54 (National Fuel Gas Distribution Corp. v. Pennsylvania Public Utility Commission) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Fuel Gas Distribution Corp. v. Pennsylvania Public Utility Commission, 587 A.2d 54, 137 Pa. Commw. 621, 1991 Pa. Commw. LEXIS 88 (Pa. Ct. App. 1991).

Opinion

CRAIG, President Judge.

National Fuel Gas Distribution Corporation (NFG) appeals a decision of the Pennsylvania Public Utility Commission (PUC or commission) that refused to place in effect NFG’s proposed tariff supplement, through which NFG sought to recover contract reformation costs, commonly referred to as take-or-pay costs (TOP costs), under the gas cost rate adjustment mechanism of § 1307(f) of the Public Utility Code, 66 Pa.C.S. § 1307(f), providing for prompt recovery by the utility of increases in the cost of gas purchased by it. We affirm.

Generally speaking, TOP costs are charges that interstate pipeline suppliers impose upon local gas distributors (LDCs), such as NFG, under cost recovery procedures established by the Federal Energy Regulatory Commission (FERC) in accordance with FERC regulations.

*625 An Administrative Law Judge (ALJ) conducted hearings on the proposed tariff supplement and NFG’s TOP costs. The ALJ issued an opinion on June 8, 1989, in which he noted that the PUC had issued a proposed policy statement which indicated that the commission did not regard TOP costs as purchased or natural gas expenses that an LDC may recover under § 1307(f). The ALJ distinguished TOP costs, quoting the commission’s policy statement which described TOP costs as arising

out of a failure, for whatever reasons, to purchase gas. As such, there is no basis in fact or in law that would mandate their recovery through a purchase gas expense recovery mechanism. These costs represent a cost whose recovery should be addressed in a base rate proceeding.

Recommended decision of the Administrative Law Judge, p. 39.

After NFG filed its § 1307(f) tariff, and after the commission filed its proposed policy statement, but before the commission adopted its Final Statement of Policy, in which it reaffirmed its proposed policy, NFG filed a tariff supplement under § 1308 of the Public Utility Code, 66 Pa.C.S. § 1308, in which it also sought to recover its TOP costs in a base rate proceeding. 1 In that proceeding, the PUC approved the tariff NFG submitted, allowing NFG to recover all of its TOP costs known at the time it filed the tariff. However, the commission refused to allow recovery of TOP costs that, NFG anticipates, one of its pipeline suppliers will ultimately pass through to NFG. NFG appealed the commission’s refusal to permit recovery of those anticipated costs; however, the company withdrew its appeal.

1. The issues

Initially, the PUC and the Office of the Consumer Advocate (OCA) raise jurisdictional and other preliminary chal *626 lenges to NFG’s appeal, contending that: (1) the commission adjudicated the issues NFG now raises on appeal in the base rate proceeding, which is no longer subject to appeal; (2) collateral estoppel precludes NFG from challenging the commission’s decision to disallow recovery of TOP costs in the base rate case in this § 1307(f) proceeding; (3) the commission’s order in the base rate proceeding renders this appeal moot; (4) the commission’s order is not a final, appealable order with respect to NFG’s TOP costs; and (5) NFG has failed to demonstrate that it has been harmed by the PUC’s decision denying recovery of its TOP costs under § 1307(f).

With respect to the merits of this appeal, the pivotal question here involves the classification of TOP costs. NFG argues that TOPs are natural gas costs that are billed to NFG as a natural gas distributor by its gas supplier, and which may be recovered through a § 1307(f) filing. The PUC asserts that TOPs are attributable to acquisition costs and therefore should be classified as production-related costs that properly should be allocated to a pipeline’s commodity rate, the adjustment of which the PUC must address in a base rate proceeding under § 1308.

Before addressing the issues raised in this appeal, a discussion of TOP costs is warranted. The court of appeals for the fifth circuit summarized take-or-pay costs in Diamond Shamrock Exploration Corp. v. Hodel, 853 F.2d 1159, 1164 (5th Cir.1988):

Natural gas sales contracts usually contain a standard “take-or-pay” clause. This clause requires the pipeline-purchaser either to take (and pay for at the maximum lawful price) a specified quantity of natural gas during each contract year or to make a single annual payment to the producer to the extent that the volumes of gas taken during any contract year fall short of the minimum annual contract quantity. During a contract year, the producer receives monthly payments only for the gas actually taken.
*627 At the end of the contract year, volumes of natural gas production actually taken are compared with the minimum contract volume. In the event the pipeline has actually taken less than the contract volume, the pipeline must then make an annual lump-sum payment, the take- or-pay payment, representing the difference between the minimum contract volume for that year and the actual volume taken. Because natural gas is almost always transported by pipeline and cannot be “stored” at the lease site, if a pipeline cannot accept delivery of gas, the producer must shut in his wells or restrict production. There can be no gas produced at the time a take-or-pay payment is made because the producer has to leave in the ground reserves sufficient to meet make-up demands over the make-up period, generally five-to-seven years. The committed volume under the gas sales contract must remain in the reservoir for the remainder of the make-up period.
Over the next seven years, the pipeline has the right to credit excess gas taken against a previous take-or-pay payment. Whenever the pipeline purchases gas in excess of the contract volume for a subsequent year, that excess gas purchase is credited against the earlier deficiency. This excess gas is referred to as make-up gas. At the end of a year in which make-up gas is taken, the pipeline will receive a single lump-sum refund, or credit, of prior take-or-pay payments made for the earlier deficiency to the extent to which the deficiency has now been made up. The refund is calculated on the basis of the price of gas during the month in which the make-up gas was actually taken.
Although the price paid for these make-up gas deliveries is the price in effect at the time the make-up gas is produced and taken, the payment is made by applying the purchaser’s prior take-or-pay payments as a credit towards the purchase price of the make-up gas. While some contracts allow the producer to retain take-or-pay *628 payments that have not been recouped by the expiration of the make-up period, others require the producer to refund any unrecouped payments to the purchaser.

The interstate pipeline suppliers in turn pass on their TOP costs to their local gas distributor customers, under rates approved by FERC.

2. The effect of the base rate case on this appeal

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Peoples Natural Gas Co., LLC v. PUC
Commonwealth Court of Pennsylvania, 2022
Dominion Retail, Inc. v. Pennsylvania Public Utility Commission
831 A.2d 810 (Commonwealth Court of Pennsylvania, 2003)
UGI Utilities, Inc.—Gas Division v. Pennsylvania Public Utility Commission
677 A.2d 882 (Commonwealth Court of Pennsylvania, 1996)
National Fuel Gas Distribution Corp. v. Pennsylvania Public Utility Commission
677 A.2d 861 (Commonwealth Court of Pennsylvania, 1996)
Popowsky v. Pennsylvania Public Utility Commission
647 A.2d 302 (Commonwealth Court of Pennsylvania, 1994)
Three Rivers Aluminum Co. v. Zoning Hearing Board
618 A.2d 1165 (Commonwealth Court of Pennsylvania, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
587 A.2d 54, 137 Pa. Commw. 621, 1991 Pa. Commw. LEXIS 88, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-fuel-gas-distribution-corp-v-pennsylvania-public-utility-pacommwct-1991.