National Environmental Service Co. v. Homeplace Homes, Inc.

961 S.W.2d 632, 1998 Tex. App. LEXIS 146, 1998 WL 10800
CourtCourt of Appeals of Texas
DecidedJanuary 14, 1998
Docket04-96-00940-CV
StatusPublished
Cited by1 cases

This text of 961 S.W.2d 632 (National Environmental Service Co. v. Homeplace Homes, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Environmental Service Co. v. Homeplace Homes, Inc., 961 S.W.2d 632, 1998 Tex. App. LEXIS 146, 1998 WL 10800 (Tex. Ct. App. 1998).

Opinion

OPINION

GREEN, Justice.

This dispute arises from a contract to build a parking lot. The trial court rendered judgment in favor of the general contractor, Homeplace Homes, Inc. (Homeplace), and the subcontractor, Johnny Escalante, against the property owner, National Environmental Service Company, Inc. (NESCO). In four points of error, NESCO challenges the damages awarded to Homeplace plus the statutory interest and attorney’s fees awarded to Escalante. In one cross point, Homeplace claims it should receive attorney’s fees. In three cross points, Escalante contends he should receive additional interest and attorney’s fees and further requests foreclosure of his mechanic’s lien. We affirm the judgment in favor of Homeplace. We also reverse the interest and attorney’s fees awarded to Esca-lante and render judgment that Escalante take nothing by those claims.

Background

NESCO contracted with Homeplace, which agreed to design and build a commercial building at a fixed price. In turn, Home-place hired Fisher Engineering Company (Fisher) to review its foundation plans. At Homeplace’s suggestion, NESCO also re *634 tained Fisher to design a parking lot for the building.

When the building was finished, NESCO solicited bids for construction of the parking lot. It received bids from several companies; including Homeplace. Although Homeplace was not the low bidder, it promised to complete the project within a short period of time. NESCO accepted Homeplace’s bid and signed a change order to its original contract, agreeing to pay Homeplace the fixed sum of $48,000 to build a parking lot according to an attached addendum.

When construction began on the parking lot, NESCO’s distribution manager, Marshall Ryan, noticed the concrete forms were not running parallel to the street. Ryan spoke with the subcontractor, Escalante, and discovered he was using the landscaping plan, rather than Fisher’s parking lot plan. After Escalante completed the parking lot with Fisher’s plan, Homeplace gave NESCO a second change order for $20,000.

NESCO refused to sign the order or pay the additional amount, and Homeplace and Escalante filed mechanic’s liens 1 against NESCO’s property. Thereafter, NESCO filed suit, seeking a release of lien and declaratory judgment as to the amounts owed each party. Homeplace counterclaimed on the basis of its contract and, alternatively, quantum meruit. Escalante also counterclaimed, seeking foreclosure of its lien. Es-calante later moved for partial summary judgment, arguing that Homeplace admitted owing him $12,050.

The trial court granted Escalante partial summary judgment for $12,050, which NES-CO paid prior to trial. After a bench trial, the court rendered judgment against NES-CO in favor of Homeplace for $10,000 in damages. The court did not award Home-place statutory interest or attorney’s fees. The trial court also rendered judgment against NESCO in favor of' Escalante for $4,007.38 in damages, which included a $1,942.50 balance on his lien plus $2,064.88 in interest. The court awarded Escalante $1,500 in attorney’s fees from both NESCO and Homeplace. In this appeal, each party challenges the trial court’s judgment.

Standards of Review

The points of error and corresponding cross points, which we discuss together as they relate to each party, are essentially attacks on the legal and factual sufficiency of the evidence and the trial court’s conclusions drawn from that evidence. In reviewing the legal sufficiency of the evidence supporting the trial court’s findings, we consider only the evidence and inferences that tend to support the findings and disregard all evidence and inferences to the contrary. Catalina v. Blasdel, 881 S.W.2d 295, 297 (Tex.1994). “If there is more than a scintilla of evidence to support the findings, the ‘no evidence’ challenge cannot be sustained.” Id.

In reviewing the factual sufficiency of the evidence supporting the trial court’s findings, we weigh all of the evidence in the record to determine whether the findings are so against the great weight and preponderance of the evidence as to be clearly wrong and unjust. Ortiz v. Jones, 917 S.W.2d 770, 772 (Tex.1996). Under this analysis, we are not fact finders, we do not pass upon the credibility of witnesses, and we do not substitute our judgment for that of the trier of fact, even if there is conflicting evidence upon which a different conclusion could be supported. Martin v. Texas Dental Plans, Inc., 948 S.W.2d 799, 802 (Tex.App.—San Antonio 1997, writ denied).

Although we may not review the factual sufficiency of the trial court’s conclusions of law, we may review the correctness of the conclusions as drawn from the facts. Mercer v. Bludworth, 715 S.W.2d 693, 697 (Tex.App.—Houston [1st Dist.] 1986, writ ref'd n.r.e.); see also Spiller v. Spiller, 901 S.W.2d 553, 556 (Tex.App.—San Antonio 1995, writ denied). In other words, we review conclusions of law de novo as questions of law, and we uphold them if the judgment can be sustained on any legal theory supported by the evidence. Nelkin v. Panzer, *635 833 S.W.2d 267, 268 (Tex.App.—Houston [1st Dist.] 1992, writ dism’d w.o.j.); see also Valencia v. Garza, 765 S.W.2d 893, 898 (Tex.App.—San Antonio 1989, no writ).

Homeplace

1. Liability

We first address that portion of NES-CO’s third point of error regarding its liability to Homeplace. 2 Specifically, NESCO contends the evidence is legally and factually insufficient to support the trial court’s findings that NESCO (1) provided the original site plan; (2) hired Fisher to design a larger plan; and (3) substituted the Fisher plan on the day the concrete was poured. NESCO also argues the trial court erred as a matter of law by concluding “NESCO’s substitution of site plans constituted a cardinal change in the original contract between Homeplace Homes, Inc. and NESCO.” We disagree with NESCO’s arguments. 3

The original contract was modified by a change order that did not specify any quantities or square footage. Although the change order referenced an addendum, the document was not introduced into evidence at trial. Ryan, NESCO’s representative, could not remember receiving an exhibit. In contrast, Gary Ballard, Homeplace’s representative, said the smaller landscape plan was attached to the charge order.

Given Ballard’s testimony, we hold the evidence is legally and factually sufficient to support the trial court’s finding that NESCO contracted for the smaller parking lot.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
961 S.W.2d 632, 1998 Tex. App. LEXIS 146, 1998 WL 10800, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-environmental-service-co-v-homeplace-homes-inc-texapp-1998.