National Engineering & Contracting Company v. Occupational Safety And Health Review Commission

45 F.3d 476, 1995 CCH OSHD 30,671, 310 U.S. App. D.C. 175, 17 OSHC (BNA) 1041, 1995 U.S. App. LEXIS 2114
CourtCourt of Appeals for the D.C. Circuit
DecidedFebruary 3, 1995
Docket93-1468
StatusPublished
Cited by5 cases

This text of 45 F.3d 476 (National Engineering & Contracting Company v. Occupational Safety And Health Review Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Engineering & Contracting Company v. Occupational Safety And Health Review Commission, 45 F.3d 476, 1995 CCH OSHD 30,671, 310 U.S. App. D.C. 175, 17 OSHC (BNA) 1041, 1995 U.S. App. LEXIS 2114 (D.C. Cir. 1995).

Opinion

45 F.3d 476

310 U.S.App.D.C. 175, 17 O.S.H. Cas. (BNA) 1041,
1995 O.S.H.D. (CCH) P 30,671

NATIONAL ENGINEERING & CONTRACTING COMPANY, Petitioner,
v.
OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION, Robert B.
Reich, Secretary of Labor, United States
Department of Labor, Respondents.

No. 93-1468.

United States Court of Appeals,
District of Columbia Circuit.

Argued Oct. 18, 1994.
Decided Feb. 3, 1995.

Petition for Review of an Order of the Occupational Safety and Health Review Commission.

Kent W. Seifried, argued the cause, for the petitioner.

John Shortall, Atty., Dept. of Labor, argued the cause for the respondents. On brief were Joseph M. Woodward, Associate Sol., and Barbara Werthmann, Counsel, Dept. of Labor.

Before BUCKLEY, WILLIAMS and HENDERSON, Circuit Judges.

Opinion for the court filed by Circuit Judge HENDERSON.

KAREN LeCRAFT HENDERSON, Circuit Judge:

National Engineering & Contracting Company (National) petitions for review of a $400 fine levied against it by the Occupational Safety and Health Administration (OSHA) after an OSHA inspector found exposed metal bars at one of its construction sites. OSHA also cited National after its inspector discovered an extension cord stripped of insulation and an ungrounded electrical plug at the same location. National contends that the warrant used to obtain entry to its worksite was not based on probable cause and that the Secretary of Labor (Secretary) failed to meet his burden of proof in the ensuing administrative proceeding. We conclude that probable cause supported OSHA's warrant and that substantial evidence supported OSHA's determination of liability. We therefore deny the petition.

I. BACKGROUND

OSHA conducts a routine inspection program under a written policy to monitor compliance with workplace health and safety standards promulgated by the Secretary under the Occupational Safety and Health Act.1 OSHA Field Operations Manual, Instruction CPL 2.45B CH-1 at II-1 (1990), reprinted at Joint Appendix (JA) 13. It inspects construction worksites on a list randomly generated by a computer owned and operated by the University of Tennessee. Based on criteria whose neutrality National does not challenge the computer selects worksites from a commercially published list of current construction projects known as "Dodge reports." Id.2 On its application for an inspection warrant OSHA stated that the computer had chosen a bridge construction site along U.S. Route 50 at Cleves, Ohio (near Cincinnati) as one of the sites for inspection in April 1992. JA 7. At the worksite, National was the general contractor for the state of Ohio's Department of Transportation on the latter's bridge construction project.

OSHA assigned compliance officer John Collier to inspect National's worksite. Collier applied for a warrant from a magistrate judge of the United States District Court for the Southern District of Ohio. The warrant application indicated that OSHA planned to conduct its inspection as part of its inspection and investigation program and included a copy of OSHA's written policy as an exhibit. JA 6. Collier also attached a copy of the Dodge report for the Cleves construction site. JA 57. He attested that "[i]n accordance with OSHA regulation 29 C.F.R. [Sec.] 1903.4 an anticipatory inspection warrant is requested because the general contractor at the inspection worksite scheduled, National Engineering & Contracting Company, has a stated and written policy forbidding government inspection of their worksites without a valid inspection warrant." JA 8.

The magistrate judge issued a warrant on April 27, 1992 to inspect the Cleves site. Because of scheduling difficulties, another inspector, James Denton, actually carried out the inspection three days later, April 30. National's superintendent, William Delsignore, arrived at the site 90 minutes after Denton. Denton showed his credentials but did not mention the warrant. The National representative did not allow him to enter; instead he consulted with two other company officials. One hour later, National asked Denton to wait until it could bring its lawyers to the site. After consulting his supervisor, Denton refused. He then served the warrant on Delsignore and began his inspection. When Denton returned to conduct a second day of inspection, National presented him with a form notice of protest regarding the issuance and validity of the warrant. JA 122.

Denton found six violations of regulatory workplace standards, three of which are at issue here. First, he saw a carpenter working near a line of exposed vertical steel bars known as rebar. Although the bars were away from the main work area, Denton determined that they were likely to pose an impalement hazard to workers.3 Second, Denton found an extension cord located in the middle of the bridge from which the outer insulation cover had pulled loose from one end, leaving the inner wires (which were themselves insulated) exposed about one-half inch. Denton concluded that the cord posed an electrocution hazard because the inner wires could pull loose while being used.4 Third, Denton found that a fax machine in an office trailer had been improperly plugged into the power outlet. The three-pronged plug had been plugged into a two-prong adapter before being put into the socket, thus removing the grounding path.5 Denton cited National for all three violations.6

National contested the citations before an administrative law judge (ALJ) acting for the Occupational Safety and Health Review Commission (Commission or OSHRC). Although National contended that the warrant was invalid, the ALJ determined without extended discussion that it had been properly issued pursuant to OSHA's administrative plan. JA 190-91. On the merits, National declined to present evidence and moved for a directed verdict in its favor after OSHA presented its case. JA 192. The ALJ found that the extension cord and fax machine plug violations were not serious and assessed no penalty. JA at 192-98, 201. The ALJ found that the rebar violation was "serious" and fined National $400. JA 200. The Commission declined discretionary review of the ALJ's decision, which became final on June 7, 1993. JA 209.7

II. DISCUSSION

National's petition challenges the warrant and the sufficiency of the evidence supporting the ALJ's findings. As to the warrant, National argues that OSHA Inspector Collier did not include information demonstrating specifically how National was chosen for inspection under OSHA's administrative plan, he lacked personal knowledge of some statements in the warrant application and he misrepresented one fact included in the application. As a result, it contends, the warrant was not supported by probable cause.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
45 F.3d 476, 1995 CCH OSHD 30,671, 310 U.S. App. D.C. 175, 17 OSHC (BNA) 1041, 1995 U.S. App. LEXIS 2114, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-engineering-contracting-company-v-occupational-safety-and-cadc-1995.