National Electrical Contractors Ass'n v. City of Mentor

108 Ohio App. 3d 373
CourtOhio Court of Appeals
DecidedDecember 26, 1995
DocketNos. 95-L-060 and 95-L-062
StatusPublished
Cited by1 cases

This text of 108 Ohio App. 3d 373 (National Electrical Contractors Ass'n v. City of Mentor) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Electrical Contractors Ass'n v. City of Mentor, 108 Ohio App. 3d 373 (Ohio Ct. App. 1995).

Opinion

Nader, Judge.

This is an appeal and cross-appeal from two judgments of the Lake County Court of Common Pleas. Appellant and cross-appellee, the city of Mentor (“appellant” or “city”), appeals the decisions declaring its bid solicitation for a public works project to be improper and finding the action to be a taxpayer suit and subject to an award of attorney fees. Appellees and cross-appellants, the National Electrical Contractors Association, Inc. (“NECA”), the Ohio Mechanical Contracting Industry, Inc. (“OMCI”), Ralph Day, and Day Electric Company, Inc. (collectively, “appellees”), appeal from the decision of the court finding that appellant’s charter conferred authority to deviate from the requirements of R.C. 153.50.

Appellee Ralph Day is a resident and taxpayer in the city of Mentor. He is the President and CEO of appellee Day Electric Company, Inc., an electrical contractor, which pays corporate taxes to the city. Appellee NECA is an association of electrical contractors. OMCI is an association of skilled trades contractors which provide plumbing, heating, ventilating and air conditioning services.

In 1993, appellant solicited bids for two projects: the fire station and the senior center. For each project, appellant advertised that consideration would be given only to “prime aggregate bids,” which required general contractors to submit a single bid for the entire project. This excluded contractors in specific trades from being considered separately for the projects.

Believing that the bidding procedure for the two projects violated state law, appellee Day sent letters to the city and the city law director, prior to the bid [376]*376opening dates, requesting that the city accept separate bids from the individual trades. The letter addressed to the law director requested that a suit be filed pursuant to R.C. 733.56. Day’s requests were denied.

On September 9,1993, appellees filed a complaint for declaratory judgment and injunctive relief. The action was brought as a taxpayer’s suit. The trial court denied temporary injunctive relief. However, appellant did not award a contract on either project. Early in 1994, appellant resolicited bids for the fire station project, once again requiring prime aggregate bids. On February 3, 1994, appellees filed an amended complaint. The trial court denied temporary and preliminary relief.

On February 8, 1994, appellant passed Ordinance No. 94-0-11, authorizing the advertising for and awarding of prime aggregate bids only. On this same date, appellant awarded the fire station project to a general contractor, who had submitted an aggregate bid, through the passage of Ordinance No. 94-0-12. Subsequently, bidding was reopened on the senior center project and a contract was awarded to an aggregate bidder.

Both parties filed motions for summary judgment. Following extensive briefing, judgment was filed on December 30, 1994. The court held that the city possessed the home rule authority under its charter to enact the ordinance restricting bids for public works to aggregate bids, thereby superseding the dictates of R.C. 153.50. However, the trial court held that because bidding for the fire station was opened prior to the enactment of Ordinance No. 94-0-11, the bidding for this project was subject to and in violation of R.C. 153.50. The bidding process for the senior center was declared to be proper. Appellees’ request for injunction was denied as to both projects, presumably for the reason that there had occurred substantial construction on the fire station project at the time the judgment was rendered.

On March 8, 1995, the trial court entered judgment finding the requirements for a statutory taxpayer action had been met, and awarding attorney fees in the amount of $34,439.17.

Appellant has filed a notice of appeal from these judgments, assigning the following as error:

“1. The trial court erred in finding the city of Mentor violated R.C. 153.50.
“2. The trial court erred in sustaining the taxpayers action and awarding attorney fees in the amount of $34,439,197 [sic ].”

Appellees have filed a cross-appeal from the judgments, and present two cross-assignments of error:

[377]*377“1. The trial court erred in failing to grant summary judgment or default judgment to Appellees/Cross-Appellants as a matter of law, and given the City of Mentor’s failure to file an amended answer or a response.
“2. The trial court violated Appellees/Cross-Appellants’ Constitutional right to due process by granting summary judgment to the City of Mentor thus denying a trial on the factual dispute raised by Appellees/Cross-Appellants.”

For appellant’s first assignment of error, it is argued that the trial court erred in concluding that the bidding procedure for the fire station project was in violation of R.C. 153.50. Appellant asserts that the city charter authorized the aggregate bid requirement for public works projects and that the passage of an ordinance was not necessary.

R.C. 153.50 provides:

“[A] municipal corporation * * * authorized to contract for the erection, repair, alteration, or rebuilding of a public building * * * or improvement and required by law to advertise and receive proposals for furnishing of materials and doing the work necessary for the erection thereof, shall require separate and distinct proposals to be made for furnishing such materials or doing such work, or both, in their discretion, for each separate and distinct trade or kind of mechanical labor, employment, or business entering into the improvement.”

The trial court held that the Home Rule Amendment to the Ohio Constitution, found in Section 3, Article XVIII, permitted the city to provide in its charter for the solicitation of aggregate bids in public works projects in contravention of the mandates of R.C. 153.50.

Section 7, Article XVIII of the Ohio Constitution provides:

“Any municipality may frame and adopt or amend a charter for its government and may, subject to the provisions of section 3 of this article, exercise thereunder all powers of local self-government.”

Section 3, Article XVIII reads:

“Municipalities shall have authority to exercise all powers of local self-government and to adopt and enforce within their limits such local police, sanitary and other similar regulations, as are not in conflict with general laws.”

It is well established that the words “as are not in conflict with general laws” modify the words “local police, sanitary and other similar regulations,” but not the words “powers of local self-government.” State ex rel. Canada v. Phillips (1958), 168 Ohio St. 191, 5 O.O.2d 481, 151 N.E.2d 722, paragraph four of the syllabus. Thus, in matters of local self-government, a charter provision which conflicts with a parallel state law prevails over the state law and supersedes it. State ex rel. Bardo v. Lyndhurst (1988), 37 Ohio St.3d 106, 524 N.E.2d 447.

[378]*378In Natl. Elec. Contrs. Assn., Inc. v. Painesville (Jan. 29, 1973), Lake App. No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
108 Ohio App. 3d 373, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-electrical-contractors-assn-v-city-of-mentor-ohioctapp-1995.