National Development Corp. v. Planning Commission
This text of 439 A.2d 1308 (National Development Corp. v. Planning Commission) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
Opinion by
This is an appeal by appellant National Development Corporation (NADCO) from an order of the Court of Common Pleas of Allegheny County. The court’s order dismissed NADCO’s appeal, filed pursuant to the Pennsylvania Municipalities Planning Code (MPC),1 from a decision of the Harrison Township Planning Commission (appellee).
On November 13, 1979 NADCO submitted to the Planning Commission an application for preliminary approval of a proposed subdivision and land development plan. The Planning Commission rendered a decision rejecting the application on March 17,1980, and NADCO was notified of this decision by letter of the same date.
[248]*248. On March. 27, 1980 NAD 00 instituted an action in mandamus in the Court of Common Pleas of . Allegheny County. In its complaint, appellant alleged that the. Planning Commission had failed to act upon its application within the time period prescribed by Section 508 of the MPC,2 and that therefore, its application was deemed approved thereunder. Appel[249]*249lant accordingly requested the court below to declare its application preliminarily approved as a matter of law, or, in the alternative, to direct the Planning Commission to grant such preliminary approval.3
In addition to the action in mandamus, NADCO filed, in the court below, on May 1, 1980, a statutory zoning appeal from the Planning Commission’s decision under Section 1006 of the MPC.4 As in tbe mandamus action, appellant sought recognition and enforcement of the deemed approval of its application.
Subsequent to the initiation of the mandamus action and the filing of its statutory appeal, NADCO filed a motion for peremptory judgment in mandamus. Following oral argument and upon consideration of the briefs of counsel, the lower court granted NADCO’s petition and directed appellee to approve [250]*250NADCO’s application by order dated July 22, 1980. Thereafter, appellee filed a petition to open the peremptory judgment entered in NADCO’s favor.5 As of this date, appellee’s petition has not been acted upon by the court below. On January 16, 1981, without notice or hearing, the court sua sponte entered an order dismissing appellant’s zoning appeal. In its order, the' court stated, as grounds for the dismissal, that its disposition of the mandamus action rendered moot NADCO’s statutory appeal. NADCO has appealed to this court from the aforesaid order.
- Preliminarily, we observe that the lower court incorrectly dismissed NADCO’s statutory appeal as moot. While it is well established that a legal question can, after suit has been commenced, become moot as a result of changes in the facts of the case or in the law, such changes must finally and conclusively dispose of the controversy. See, In re Gross, 476 Pa. 203, 382 A.2d 116 (1978). Here, the issue involved in both the mandamus action and the statutory appeal is whether NADCO is entitled to preliminary approval of its application as a matter of law. The lower court’s disposition of this question in appellant’s mandamus action, however, is not final and conclusive: appellee’s petition to open the peremptory judgment entered in that matter has not yet been acted upon by that court. Accordingly, NADCO’s statutory appeal did not become moot as a result of the lower court’s decision in the mandamus action.
The record before us, however, presents the question of whether NADCO’s zoning appeal was timely [251]*251filed, and consequently, whether the court below had subject matter, jurisdiction over that appeal.6 Under Section 5571 of the Judicial Code,7 an appeal from an order of a government unit to a court must be commenced within thirty (30) days after the entry of the order from which the appeal is taken. Section 5572 of the Judicial Code8 provides that the date of mailing of an order of a government unit shall be deemed the date of entry of the order.9
As aforesaid, the instant record indicates that the Planning Commission rendered its decision rejecting appellant’s application on March 17, 1980, and notified NADCO of this decision in a letter bearing the same date. Appellant’s statutory appeal from that decision was filed on May 1, 1980. The record is devoid, however, of any indication of the date on which the létter to NADCO was mailed. We are thus unable to determine whether NADCO’s appeal under the MPC was timely filed. Accordingly, we are compelled to remand the case to the lower court for such a determination. In the event the court below determines that the statutory appeal was timely, the court should then decide the merits of that appeal.
[252]*252Order
And Now, the 26th day of January, 1982, the above-captioned case is hereby remanded to the Court of Common Pleas of Allegheny County.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
439 A.2d 1308, 64 Pa. Commw. 246, 1982 Pa. Commw. LEXIS 1010, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-development-corp-v-planning-commission-pacommwct-1982.