National Bank of Commerce of Tulsa v. ABC Construction Co.

1966 OK 14, 442 P.2d 269
CourtSupreme Court of Oklahoma
DecidedFebruary 1, 1966
Docket40737
StatusPublished
Cited by16 cases

This text of 1966 OK 14 (National Bank of Commerce of Tulsa v. ABC Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Bank of Commerce of Tulsa v. ABC Construction Co., 1966 OK 14, 442 P.2d 269 (Okla. 1966).

Opinion

LAVENDER, Justice.

This cause involves a dispute between the National Bank of Commerce of Tulsa, Oklahoma, hereinafter referred to as “Bank,” ABC Construction Company, hereinafter referred to as “ABC,” and Standard Accident Insurance Company, hereinafter called “surety.”

The dispute arose when one J. C. Johnson, an individual, doing business as Johnson Construction Company, hereinafter called “Johnson,” admitted in writing that he was in default and would be unable to complete his sub-contract to do certain phases of the work in connection with the relocation of U. S. Highway 169 near the Oologah Reservoir. ABC was the prime contractor on the project with the United States of America by and through the U. S. Army Corps of Engineers as the other contracting party. Surety was the surety upon Johnson’s performance bond and upon a labor and materialmen payment bond for Johnson. Bank was the holder of a $35,-000.00 promissory note of Johnson secured by a written assignment from Johnson of monetary benefits he was to receive under his sub-contract.

ABC, as the prime contractor, agreed with the United States of America to furnish all the labor and materials for the relocation of U. S. Highway 169 near the Oologah Reservoir, for which ABC was to receive specified unit prices for the actual quantities of the various items of work and materials listed as being required to perform the contract according to the plans and specifications therefor. This contract provided, among other things, for the government to retain ten percent of the amount of each progressive estimate of work done and materials furnished until the project had been completed and accepted by the government.

On March 17, 1959, ABC entered into the written sub-contract with Johnson under which Johnson agreed to furnish all materials, equipment, tools and labor required to perform certain portions of the prime contract. What was to be done by Johnson was covered by “items” specified in the sub-contract and in accordance with the plans and specifications therefor included in the prime contract. The work was to be done in such a manner as not to delay the progress or completion of the prime contract project within the time allowed therefor in the prime contract. Johnson also agreed to keep the sub-contract proj ect free and clear of all mechanic’s liens or other encumbrances arising by act of Johnson or contract.

By the terms of this sub-contract, ABC agreed to pay Johnson, for the faithful performance of the sub-contract, a sum equal to five percent less than the amount derived by multiplying the quantity of each prime contract item furnished by Johnson by the unit price set' forth in the prime contract for each such item furnished by Johnson, with the total estimated to be $368,-972.88. Such consideration was to be paid by ABC to Johnson in installments as the *271 work progressed, on estimates of Johnson’s proportionate part of all items furnished in the performance of the prime contract, as and when ABC received payment from the government on its progressive estimates of all items furnished in the performance of the prime contract, hut with a provision that ten percent of Johnson’s proportionate part of each ABC estimate should be retained by ABC until the final ABC estimate be made, completion of Johnson’s sub-contract portion of the project be certified as satisfactory by the Corps of Engineers and ABC be paid therefor by the government. This subcontract also provides:

“5. If Sub-contractor shall fail to prosecute said work or furnish said material as rapidly as the Contractor shall require, of if Sub-contractor shall fail to comply with the terms of the general contract or the Plans and Specifications as to quality of material or workmanship, or if Sub-contractor shall fail to furnish necessary material and complete said work in such manner as to permit completion of the entire contract upon the date specified in the general contract, the Contractor may on five (5) days’ written notice relet the said work or any part thereof, or may purchase materials as the general contractor may determine, or may proceed to perform any or all portions of the sub-contract, and all costs of said material and expense for such labor shall be charged to the Sub-contractor and may be treated as payments to the Sub-contractor. The Sub-contractor shall be liable to the Contractor for any excess of expenditure so made over and above the sub-contract price fixed hereinafter.
“6. Sub-contractor agrees that in case of any error or default on his part in the performance of this sub-contract, Contractor may correct the error or perform the work as economically as possible and charge the cost thereof to Sub-contractor or deduct such cost from any sum due Sub-contractor hereunder.”

Also under date of March 17, 1959, and pursuant to such sub-contract, Johnson, as principal, and the intervenor, Standard Accident Insurance Company, as surety for Johnson, executed and delivered to ABC, as obligee, two separate bonds, each with penalty of $184,486.44, one conditioned that Johnson would promptly make payment, to all claimants having a direct contract with Johnson, for all labor and material used or reasonably required for use in the performance of said sub-contract, including that part of water, gas, power, light, heat, oil, gasoline, telephone service or rental of equipment, directly applicable to the subcontract, and the other bond conditioned that Johnson would promptly and faithfully perform said sub-contract, which, by reference, was made a part of such bond.

As a condition precedent to and a part of the consideration for the execution of said bonds by the Surety, Johnson executed and delivered to the Surety a written application dated March 31, 1959 for said bonds, which application provided, inter alia, that Johnson would. perform all the conditions of said bonds and any and all renewals and extensions thereof, which application included an assignment of money due Johnson under the sub-contract.

After the prime contract had been awarded to ABC, Johnson arranged with an officer of the National Bank of Commerce of Tulsa for the financing of Johnson’s proposed sub-contract, upon proper assignment of the sub-contract to the Bank, approved or accepted by ABC. That information was conveyed by Johnson to ABC, and under date of April 6, 1959, the president of ABC, upon behalf of ABC, wrote the Bank a letter which reads as follows:

“This letter is to inform you that it will be permissible with the A.B.C. Construction Company for Mr. J. C. Johnson to give your bank an assignment on Contract Number DA-34-066-CIVENG-59-1114, covering the relocation of Highway #169, Oologah Reservoir Area, for the United States Corp of Engineers. Thank you in advance for your cooperation.”

On November 4, 1959 the Bank loaned Johnson $35,000.00 and took from him his *272 promissory note in that amount secured by an assignment in writing, the material portions of which are as follows:

“Now, therefore, in consideration of the sum of One Dollar and other valuable considerations, the receipt of which is hereby acknowledged, and for the purpose of securing the payment of the above described indebtedness as evidenced by said promissory note(s) and all renewals, ex-tentions and changes in form thereof, * * *.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
1966 OK 14, 442 P.2d 269, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-bank-of-commerce-of-tulsa-v-abc-construction-co-okla-1966.