Nathan Bikowski v. Pro Seamless of Wisconsin Inc.

CourtCourt of Appeals of Wisconsin
DecidedSeptember 16, 2021
Docket2020AP001234
StatusUnpublished

This text of Nathan Bikowski v. Pro Seamless of Wisconsin Inc. (Nathan Bikowski v. Pro Seamless of Wisconsin Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nathan Bikowski v. Pro Seamless of Wisconsin Inc., (Wis. Ct. App. 2021).

Opinion

COURT OF APPEALS DECISION NOTICE DATED AND FILED This opinion is subject to further editing. If published, the official version will appear in the bound volume of the Official Reports. September 16, 2021 A party may file with the Supreme Court a Sheila T. Reiff petition to review an adverse decision by the Clerk of Court of Appeals Court of Appeals. See WIS. STAT. § 808.10 and RULE 809.62.

Appeal No. 2020AP1234 Cir. Ct. No. 2018CV209

STATE OF WISCONSIN IN COURT OF APPEALS DISTRICT IV

NATHAN BIKOWSKI,

PLAINTIFF-APPELLANT,

V.

PRO SEAMLESS OF WISCONSIN INC., F/K/A PRO SEAMLESS,

DEFENDANT-RESPONDENT.

APPEAL from a judgment of the circuit court for Wood County: TODD P. WOLF, Judge. Affirmed.

Before Blanchard, P.J., Fitzpatrick, and Graham, JJ.

Per curiam opinions may not be cited in any court of this state as precedent

or authority, except for the limited purposes specified in WIS. STAT. RULE 809.23(3). No. 2020AP1234

¶1 PER CURIAM. Nathan Bikowski contracted with Pro Seamless of Wisconsin, Inc. to replace the roof and siding on his residence, and he was unsatisfied with Pro Seamless’s performance. Following completion of these projects, Bikowski sued Pro Seamless for breach of contract and trade violation claims and Pro Seamless counterclaimed for unpaid contract amounts. Bikowski appeals the judgment entered by the circuit court following a bench trial. According to Bikowski, the court erred when it determined that he failed to meet his burden of proof on portions of his breach of contract claims, and when it denied relief for Pro Seamless’s alleged violations of various trade practices. We reject Bikowski’s arguments and affirm.

BACKGROUND

¶2 This is an appeal of a judgment following a three-day bench trial. The parties disputed many facts during the trial, but the following are undisputed except as noted below.

¶3 Bikowski owns a home in Wisconsin Rapids. In September 2014, following a hailstorm, he entered into two written contracts with Pro Seamless. Both contracts contained a clause that required the work “to be completed in a workmanlike manner according to standard practices.”

¶4 One of the contracts was for the installation of a new roof over Bikowski’s house and garage. This contract, which we refer to as the “Roofing Agreement,” called for the installation of an ice and water shield, a drip edge, and

2 No. 2020AP1234

a continuous ridge vent, and also the replacement of the shingles, roof vents, and flashing. The final price of the Roofing Agreement was $9,150.00.1

¶5 The other contract, which we refer to as the “Siding Agreement,” called for the installation of vinyl siding, aluminum wrap around all windows and doors, and new soffits and fascia.2 The contract price of the Siding Agreement was $11,955.00.

¶6 Pro Seamless completed the work on the Roofing Agreement in December 2014 and the work on the Siding Agreement the following spring. Bikowski’s fiancée raised issues with Pro Seamless about the quality of its work in March 2015. Pro Seamless submitted a final invoice for both projects on April 8, 2015, and Bikowski’s fiancée advised Pro Seamless of additional issues. The parties engaged in the right to cure process found in WIS. STAT. § 895.07 (2019-20),3 but that process did not result in a resolution of their disputes. Bikowski did not pay the final invoice.

1 The Roofing Agreement originally included repair work on the chimney. Pro Seamless contends that, after determining that the chimney required more than just “repair work” and that Pro Seamless would be unable to do the work, it provided Bikowski with a $1,150 credit so he could have someone else replace the chimney. After this adjustment and another smaller credit, the final price for the Roofing Agreement was reduced from $10,500 to $9,150.00.

On appeal, Bikowski alleges that the so-called chimney repair was a “throw in” designed to induce him to enter into the agreement. We address this allegation in a footnote below. For now, it suffices to say that it is undisputed that Pro Seamless did not perform any work on Bikowski’s chimney and did not bill him for any chimney work. 2 The Siding Agreement also provided for the installation of river rock or vinyl stone in select areas, 36 feet of gutter, and one 15-foot downspout. It is undisputed that the rock or stone was not installed and that Bikowski was not charged for that item. Bikowski did not allege that this resulted in a breach of contract. He did challenge the adequacy of the gutter and downspout at trial, but he makes no argument about it on appeal, and we discuss it no further. 3 All references to the Wisconsin Statutes are to the 2019-20 version unless otherwise noted.

3 No. 2020AP1234

¶7 Bikowski filed a complaint alleging that Pro Seamless breached both contracts and violated various trade practices.4 Pro Seamless responded with a counterclaim for $9,274.31, which it claimed represented the unpaid balance due under the two contracts.

¶8 Following a bench trial and the submission of post-trial briefing, the circuit court determined that Pro Seamless breached some but not all of its contractual promises. It awarded damages based on its determination of whether the work in question could be repaired or had to be replaced. Specifically, the court found that some of the installation work contemplated by the Roofing Agreement was not done in a workmanlike manner, but that there was no “significant violation[]” of the Roofing Agreement and the minor issues could be easily repaired. As for the Siding Agreement, the court determined that Pro Seamless did not breach the portions of the Siding Agreement pertaining to the soffits, but that it had breached the portions of the Siding Agreement pertaining to the aluminum wrap and the vinyl siding and that this work had to be replaced.

¶9 As for a remedy, the court determined that Bikowski was entitled to damages for breach of the Siding Agreement in the amount of $7,050.00, which represented the cost to replace the siding and the aluminum wrap. The court subtracted that amount from the $9,274.31 that Bikowski still owed on the contracts. It ordered that the difference, $2,224.31, would be held in an attorney trust account and used to pay for the minor repairs that were required under the

4 The complaint also included claims for slander of title and breach of WIS. STAT. § 895.07. The slander of title claim was dismissed during the trial. As for the § 895.07 claim, Bikowski does not challenge any aspect of the circuit court’s determinations regarding that claim on appeal.

4 No. 2020AP1234

Roofing Agreement, and that any portion of these funds that remained after the repairs were completed would belong to Pro Seamless.

¶10 As for the alleged trade practices violations, the circuit court determined that Pro Seamless had violated some provisions in the Wisconsin Statutes and the Wisconsin Administrative Code that regulate trade practices, but that Bikowski failed to prove that he was entitled to relief for any violation.

¶11 Bikowski appeals. We present additional background and address the parties’ disputes of fact as needed in our discussion below.

DISCUSSION

¶12 Our standard for reviewing a decision following a bench trial is well established. We apply a highly deferential standard to the circuit court’s findings of fact. Royster-Clark, Inc. v. Olsen’s Mill, Inc., 2006 WI 46, ¶11, 290 Wis. 2d 264, 714 N.W.2d 530. The circuit court is the ultimate arbiter of witness credibility, and when more than one reasonable inference can be drawn from the credible evidence, the reviewing court must accept the inference drawn by the circuit court. Cogswell v. Robertshaw Controls Co., 87 Wis.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cords v. Anderson
259 N.W.2d 672 (Wisconsin Supreme Court, 1977)
State v. Pettit
492 N.W.2d 633 (Court of Appeals of Wisconsin, 1992)
Volvo Trucks v. State, Dept. of Transp.
2010 WI 15 (Wisconsin Supreme Court, 2010)
Fiumefreddo v. McLean
496 N.W.2d 226 (Court of Appeals of Wisconsin, 1993)
Schill v. Wisconsin Rapids School District
2010 WI 86 (Wisconsin Supreme Court, 2010)
Moonlight v. Boyce
372 N.W.2d 479 (Court of Appeals of Wisconsin, 1985)
Noll v. Dimiceli's, Inc.
340 N.W.2d 575 (Court of Appeals of Wisconsin, 1983)
Cogswell v. Robertshaw Controls Co.
274 N.W.2d 647 (Wisconsin Supreme Court, 1979)
Adams Outdoor Advertising, Ltd. v. City of Madison
2006 WI 104 (Wisconsin Supreme Court, 2006)
Stuart v. Weisflog's Showroom Gallery, Inc.
2008 WI 22 (Wisconsin Supreme Court, 2008)
Shy v. Industrial Salvage Material Co.
58 N.W.2d 452 (Wisconsin Supreme Court, 1953)
Thorp Sales Corp. v. Gyuro Grading Co.
319 N.W.2d 879 (Court of Appeals of Wisconsin, 1982)
Brew City Redevelopment Group, LLC v. Ferchill Group
2006 WI App 39 (Court of Appeals of Wisconsin, 2006)
Royster-Clark, Inc. v. Olsen's Mill, Inc.
2006 WI 46 (Wisconsin Supreme Court, 2006)
Milton v. Washburn County
2011 WI App 48 (Court of Appeals of Wisconsin, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Nathan Bikowski v. Pro Seamless of Wisconsin Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/nathan-bikowski-v-pro-seamless-of-wisconsin-inc-wisctapp-2021.