Natchitoches Sweet Potato Co. v. Perfection Curing Co.

96 So. 808, 153 La. 916, 1923 La. LEXIS 1849
CourtSupreme Court of Louisiana
DecidedApril 30, 1923
DocketNo. 24638
StatusPublished
Cited by6 cases

This text of 96 So. 808 (Natchitoches Sweet Potato Co. v. Perfection Curing Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Natchitoches Sweet Potato Co. v. Perfection Curing Co., 96 So. 808, 153 La. 916, 1923 La. LEXIS 1849 (La. 1923).

Opinion

ROGERS J.

Plaihtiff instituted suit against the Perfection Curing Company, Inc., and the Southern Surety Company, its surety, for breach of a building contract. The prayer of the petition was for judgment against the contractor for $13,200 and against the surety company for $8,000-, amount of the bond. After the suit had been brought, certain furnishers of material liened the lot and building, and plaintiff then, by amended and supplemental petition, cited said lienors, the curing company, and its surety in concurso proceedings, praying that judgment be rendered for and against the several parties as their interests might appear, and rejecting any demand against itself.

Defendants curing company and shrety company filed exceptions, which were overruled, and then answered denying liability, and the curing company, further, by way of reconvention, prayed for damages in its behalf in the sum of $17,500 against plaintiff for the alleged circulation of false reports of and concerning said defendant, and for the breach of its obligations under said building contract.

The materialmen answered, alleging the sale, delivery, and use of the material as set forth in their respective claims and their lien and privilege therefor, and asked for judgment against all three of the parties, curing company, surety company, and sweet potato company, and for the enforcement of their privilege on the bond and of their lien against the lot and building.

When the case was called for trial, several other materialmen had filed interventions, ánd on the morning of the trial other claimants appeared, participated in the proceedings, and proved up their claims. The curing company. and the surety company objected to all of the evidence in the case, and to the allowance of the filing and trial of the interventions of the other claimants, which objections were overruled. After hearing, the district court rendered judgment in favor of all of the materialmen for the amounts of their respective claims, with interest thereon, against the defendants curing company and surety company, in solido, with preferential claim on the bond, but rejected their claims against the plaintiff and denied their liens on the lot and building; in- favor of plaintiff and against the contractor and surety company in solido for $2,270, with interest, less the sum of $350, “the estimated value -of additional concreting work required and done and which was done at the 'expense of the plaintiff owner,’’ and dismissing the re-conventional demand of the curing company.

From this judgment the curing company, the surety company, and the materialmen have appealed. Appellee has answered the appeal praying for an amendment of the judgment' by increasing the amount of damages in its favor to $5,000.

In this court, counsel for the curing company and. for -the surety company insist upon the meritoriousness of their /exceptions. These exceptions are: (1) Prematurity; (2) misjoinder; and (3) no right or cause of action.

It is contended that the proceeding of plaintiff is premature because, attempting to" invoke concursus proceedings under Act No. 262 of 1916, it has not brought itself within the provisions of the act, having failed to allege that it caused the contract and bond to be recorded “before the day fixed on which said work is to commence and not later than thirty days after the date of said contract.”

[921]*921The bond was exacted and given in conformity with Act No. 221 of 1914, and the laws amendatory thereof (Act No. 262 of 1916), and the contract is written into the bond. However, as the bond was not executed and delivered until more than 30 days after the contract was signed, it was impossible to have had it recorded within the delay set forth in the statute. Inasmuch as the surety company must be presumed to know the law, and since it executed and delivered the bond more than 30 days after the date of the contract, as appears on .the face of the bond itself, it cannot be heard to complain of the noneompliance in this respect with the terms of the statute, which by its action it had undeniably waived.

The exception of misjoinder is leveled at the alleged failure of plaintiff to bring all claimants into court. Plaintiff joined in the action three parties who had filed claims in the mortgage office of .the parish against its property. It is true plaintiff did not allege that these parties were the only ones who had filed such claims, although presumably they were, since it was to plaintiff’s interest to bring into court all claimants against its property so as to cause them to litigate their respective claims with the contractor and its surety, thereby freeing itself and its properly of their demands; nevertheless, even if plaihtiff did neglect to cite other lienors, if there were any others, we are unable to appreciate how the contractor and his surety can be prejudiced by plaintiff’s failure to provide them with additional opponents seeking to obtain substantial money judgments against them. . '

The exception of no right or cause of action is based upon the contention that since the obligation sought to be enforced is purely statutory (under section 3 of Act No. 262 of 1916), it is incumbent upon plaintiff to show by proper averments, which it has not done, that it has strictly complied with the provisions of the statute by alleging its own freedom from fault; by averring that it had caused the contract and bond to be recorded within the time and in the manner prescribed by the act; and by showing a deposit in the registry of the court of the admitted balance due on the contract.

Exceptors cite Wells v. Fidelity & Deposit Co., 146 La. 169, 83 South. 448, as reiterating the settled doctrine of our jurisprudence that the “obligation of the surety must be strictly construed,” and that therefore his obligation must be strictly and precisely alleged, which the plaintiff has failed to do. Inasmuch as plaintiff has attached to and made part of his petition the contract and bond containing all of the obligations of the contractor and of the surety, it has fully complied with the rule invoked by exceptors.

Savings & Homestead Association v. Frank, 146 La. 198, 83 South. 491, is referred to in support of the legal principle that' “the obligation of the surety is predicated upon the obligation of the owner that he will execute his part of the contract,” necessarily requiring plaintiff to allege his freedom from fault. The pleadings in the ease show that plaintiff has brought itself within the rule by alleging the performance on its part of the obligations of the contract.

Musey v. Prater, 147 La. 71, 84 South. 498, relied upon to uphold 'the contention that plaintiff must allege compliance with the requirements of the statute in order to enjoy the benefit of its provisions, has no application to the issues involved in the instant case. In the Musey Case the contest was between the owner and the material men, and not between the latter and the contractor and his bondsman. The bond was taken in the name of the owner for the faithful performance of the contract, and not for the benefit of the materialmen and laborers. The bond was not recorded within 30 days from the signing of the "contract, and none of the other things [923]*923required by law were done.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lambert v. Maryland Cas. Co.
403 So. 2d 739 (Louisiana Court of Appeal, 1981)
Prestigiacomo v. Phoenix Insurance Co. of Hartford
231 So. 2d 431 (Louisiana Court of Appeal, 1970)
EE Rabalais & Son, Inc. v. United Bonding Ins. Co.
226 So. 2d 528 (Louisiana Court of Appeal, 1969)
State v. Preferred Accident Insurance Co. of NY
149 So. 2d 632 (Louisiana Court of Appeal, 1963)
A. J. Bankhead v. Maryland Casualty Co.
197 F. Supp. 879 (E.D. Louisiana, 1961)
Fidelity Homestead Ass'n v. Kennedy & Anderson
105 So. 64 (Supreme Court of Louisiana, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
96 So. 808, 153 La. 916, 1923 La. LEXIS 1849, Counsel Stack Legal Research, https://law.counselstack.com/opinion/natchitoches-sweet-potato-co-v-perfection-curing-co-la-1923.