Nat. Tech. Systems v. Comm'l Contractors

108 Cal. Rptr. 2d 67, 89 Cal. App. 4th 1000
CourtCalifornia Court of Appeal
DecidedJune 27, 2001
DocketB141537
StatusPublished

This text of 108 Cal. Rptr. 2d 67 (Nat. Tech. Systems v. Comm'l Contractors) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nat. Tech. Systems v. Comm'l Contractors, 108 Cal. Rptr. 2d 67, 89 Cal. App. 4th 1000 (Cal. Ct. App. 2001).

Opinion

108 Cal.Rptr.2d 67 (2001)
89 Cal.App.4th 1000

NATIONAL TECHNICAL SYSTEMS, Plaintiff and Appellant,
v.
COMMERCIAL CONTRACTORS, INC., Defendant;
United Pacific Insurance Company, Objector and Respondent.

No. B141537.

Court of Appeal, Second District, Division Three.

June 7, 2001.
As Modified on Denial of Rehearing June 27, 2001.

*70 Maher & Maher, Cynthia R. Maher, Orange; and Robert I. Snyder, La Canada, for Plaintiff and Appellant.

Ramseyer & Kuhlman, David B. Kuhlman, Craig A. Ramseyer, San Diego and Laura K. Gantney, for Objector and Respondent.

*69 KLEIN, P.J.

Plaintiff and appellant National Technical Systems (plaintiff or the subcontractor) appeals a postjudgment order denying its motion to summarily enforce a judgment against United Pacific Insurance Company (the surety), the surety on a stop notice release bond.

The essential question presented is whether plaintiff is entitled to enforce a money judgment against the surety pursuant to the summary proceedings provided by the Bond and Undertaking Law (Code Civ. Proc, §§ 995.010 et seq., 996.440)[1] for recovery on the bond.

Summary enforcement may be had only if a bond is "given in an action or proceeding." (§ 996.440, subd. (a).) Here, the stop notice release bond was not given in an action or proceeding because the bond was issued prior to the filing of the lawsuit. Because the issuance of the bond preceded the filing of the lawsuit, the surety should have been joined as a party to the action. (§ 996.430, subd. (a).)

Because the instant bond was not "given in an action or proceeding" in that it preceded the filing of the action, the trial court properly rejected the plaintiffs attempt to enforce the bond against the surety pursuant to the summary remedy under section 996.440. Therefore, the order is affirmed.

FACTUAL AND PROCEDURAL BACKGROUND

On April 9, 1996, Commercial Contractors, Inc. (the general contractor) entered into a written prime contract with the City of Long Beach (the city), a public entity, to perform remediation and excavation work in the Port of Long Beach.[2] On April 16, 1996, the general contractor hired plaintiff as a subcontractor on the project.

The subcontractor claimed it was only partially paid for services rendered to the general contractor, and on March 21, 1997, the subcontractor filed a stop notice with the city in the amount of $343,905.

*71 On April 8, 1997, the general contractor obtained a bond from the surety in the sum of $429,881 to release money withheld on the stop notice. On April 30, 1997, the surety notified the subcontractor by certified mail that the general contractor had filed a bond to release money withheld on the stop notice.

Although the subcontractor was aware of the surety's issuance of the bond, on May 17, 1997, the subcontractor filed the instant action against the general contractor (the NTS v. CCI action) (L.A.Super. Ct. No. NC021319), without naming the surety, seeking damages on the contract, enforcement of the stop notice, and recovery on the bond.

On or about January 31, 1999, on the eve of trial, the subcontractor moved for leave to file a second amended complaint to add the surety as a party and to add a new cause of action for recovery on the bond "so that it may avail itself of the summary proceeding provided by ... section 996.440 .... [¶] Otherwise, [plaintiff] will be required to file a separate civil action against [the general contractor] and the Surety to recover on the Bond."

The general contractor opposed the motion to amend, arguing the surety had not participated in any manner during the course of the litigation, and that it would be unduly prejudicial to the surety to force it to defend itself on the eve of trial. The trial court denied leave to amend because trial was imminent and the surety had not been involved in any of the discovery or other trial preparation in the action.[3] The matter came on for a jury trial, the amount due and owing from the general contractor to the subcontractor was litigated, and the trial court entered judgment in favor of the subcontractor. Neither party appealed.

On October 11, 1999, the subcontractor made demand upon the surety in a letter for payment of $466,552, representing the judgment, attorney fees, penalties and accrued interest.

The surety refused to pay. It advised the subcontractor by letter that it "was never served with the lawsuit or made a party to the lawsuit. The first notice of claim was [the subcontractor's] letter of October 11, 1999. The verdict does not mention either the stop notice, the [city] or [the surety]. [The subcontractor's] judgment is only against [the general contractor]. [¶] ... [¶] While we do not require that you file an action to enforce your rights, [the surety] is not bound by the judgment.... There is no basis at this time to make payment to your client. If your client seeks to enforce its rights on the stop notice release bond, [the surety] will have the opportunity to assert all the relevant defenses on the claim...."

On March 1, 2000, due to the surety's refusal, the subcontractor filed a separate action against the surety (National Technical System, v. United Pacific Insurance *72 Company (L.A.Super. Ct. No. NC027374), the NTS v. UPIC action) to recover on the stop notice release bond.

On March 14, 2000, notwithstanding the pendency of the second action, the subcontractor attempted to invoke the summary proceeding of section 996.440 by filing a motion in the instant action, the NTS v. CCI action, for summary enforcement of the judgment against the surety. The subcontractor asserted that having obtained a judgment against the general contractor, and the judgment having become final, the subcontractor was now entitled to enforce the judgment against the surety. The subcontractor further contended that a surety which fails to make payment after a claim is made for payment on a bond incurs its own liability for attorney fees and costs and postjudgment interest from the date of the claim.

On April 18, 2000, the trial court heard and denied the subcontractor's motion for summary enforcement of the judgment against the surety "without prejudice, and it's based on the fact that the court feels that [the surety] has not been made a party to the action. Further, ... there is another action pending where [the surety] is named as a party with the same recovery being requested."[4] The subcontractor filed a timely notice of appeal from the order denying its motion for summary enforcement of the judgment against the surety.[5]

CONTENTIONS

The subcontractor contends: the California Bond and Undertaking Law (§ 995.010 et seq.) allows for summary enforcement of the judgment against the surety; and because the surety has an absolute right to recover from the general contractor, the bond includes the award of attorney fees and penalties against the general contractor.

DISCUSSION

1. Overview of statutory scheme.

A "stop notice" is a remedy to reach unexpended construction funds in the hands of the owner or lender, is available on both public and private works, and may be served by a claimant other than an original contractor. (Civ.Code, § 3181; Department of Industrial Relations v. Fidelity Roof Co. (1997) 60 Cal.App.4th 411, 419, 70 Cal.Rptr.2d 465.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stockton Savings & Loan Bank v. Massanet
114 P.2d 592 (California Supreme Court, 1941)
Stanton v. Panish
615 P.2d 1381 (California Supreme Court, 1980)
Mark Briggs & Associates, Inc. v. Kinestar, Inc.
143 Cal. App. 3d 483 (California Court of Appeal, 1983)
Acoustics, Inc. v. Trepte Construction Co.
14 Cal. App. 3d 887 (California Court of Appeal, 1971)
Winick Corp. v. County Sanitation District No. 2
185 Cal. App. 3d 1170 (California Court of Appeal, 1986)
Walt Rankin & Associates, Inc. v. City of Murrieta
101 Cal. Rptr. 2d 48 (California Court of Appeal, 2000)
DEPARTMENT OF INDUS. REL. v. Fidelity Roof Co.
60 Cal. App. 4th 411 (California Court of Appeal, 1997)
Grade-Way Construction Co. v. Golden Eagle Insurance
13 Cal. App. 4th 826 (California Court of Appeal, 1993)
Quarterman v. Kefauver
55 Cal. App. 4th 1366 (California Court of Appeal, 1997)
California Federal Savings & Loan Ass'n v. City of Los Angeles
902 P.2d 297 (California Supreme Court, 1995)
National Technical System v. Commercial Contractors, Inc.
89 Cal. App. 4th 1000 (California Court of Appeal, 2001)