Nat Harrison Associates, Inc. v. Louisville Gas and Electric Co., and Ohio Valley Transmission Corp.

512 F.2d 511
CourtCourt of Appeals for the Sixth Circuit
DecidedMay 27, 1975
Docket73-1468, 73-1469
StatusPublished
Cited by6 cases

This text of 512 F.2d 511 (Nat Harrison Associates, Inc. v. Louisville Gas and Electric Co., and Ohio Valley Transmission Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nat Harrison Associates, Inc. v. Louisville Gas and Electric Co., and Ohio Valley Transmission Corp., 512 F.2d 511 (6th Cir. 1975).

Opinion

ENGEL, Circuit Judge.

These appeals are the result of a contractual dispute between plaintiff Nat Harrison, Inc. (hereinafter Harrison) and defendants Louisville Gas and Electric Company and Ohio Valley Transmission Corporation, 1 (hereinafter jointly referred to as Louisville).

In early 1968, Louisville solicited private bids for performing all work and furnishing certain materials needed to install conductors, shield wire, and line hardware on a new 345,000 volt double circuit steel tower transmission line. The line was to run from Cane Run Generating Station in Louisville, Kentucky to Middletown Substation near Middle-town, Kentucky, a distance of approximately forty-two miles (hereinafter referred to as the Cane Run project). Harrison was the successful bidder. Upon completion of the transmission line, Harrison instituted a diversity action against Louisville. The complaint contained two counts. Count I sought reformation of the contract price, alleging that Harrison made a mistake in computing and submitting its bid. It further alleged that Louisville knew or should have known that a material mistake had been made because of its experience in this field, the estimate of its own engineers, and the amount of other competitive bids. Count II sought money damages for breach of contract arising from an alleged failure by Louisville to supervise and direct the work.

This lawsuit was tried twice, both times before a jury. In the first trial, the district court granted a defense motion to dismiss count II, but submitted count I to the jury. 2 The jury, however, was unable to reach a verdict and was discharged. Louisville’s motion for judgment notwithstanding the jury’s failure *513 to agree was denied by the district court. Count I was retried and following the second trial, 3 the jury reformed the contract and awarded damages in the amount of $293,230.00.

APPEAL NUMBER 73-1469

In appeal number 73 — 1469, appellant Louisville contends that it was entitled to judgment in its favor on count I notwithstanding the jury’s failure to agree at the first trial. In reviewing the denial of Louisville’s Rule 50(b) motion, we view the evidence, and reasonable inferences to be drawn therefrom, in the light most favorable to Harrison. Fortner Enterprises, Inc. v. United States Steel Corp., 452 F.2d 1095 (6th Cir. 1971), cert. denied 406 U.S. 919, 92 S.Ct. 1773, 32 L.Ed.2d 119. This being a diversity of citizenship case, the substantive law of Kentucky applies.

Harrison sought reformation of the contract on the theory that it made a unilateral mistake in submitting its bid, accompanied by fraud or inequitable conduct on the part of Louisville in accepting the bid, when it knew or should have known that a material mistake had been made in the bid. Kentucky recognizes this theory as a basis for reformation of a contract. City of Campbellsville v. Taylor County Telephone Co., 229 Ky. 843, 18 S.W.2d 305 (1929) and Beatty v. Donahue, 249 S.W.2d 33 (Ky.1952). The parties concede that under Kentucky law a party sustains the burden of proving a right of reformation on the ground of mistake if evidence favorable to it is sufficient in quantity and quality to be clear and convincing. Deskins v. Leslie, 387 S.W.2d 596 (Ky.1965). Each case must be viewed against its own peculiar facts and circumstances. The rule in essence means nothing more than that the entire proof, together with the surrounding circumstances, shall be sufficient to convince a reasonable mind of the truth of the grounds alleged, and to dispel any well founded doubts on the subject. Glass v. Bryant, 302 Ky. 236, 194 S.W.2d 390, 393 (1946). While this case is unusual in its submission of normally equitable issues to a jury, we conclude that the threshold issue of sufficiency of the evidence, measured by the clear and convincing rule, was for the trial judge to determine.

The facts involved in this case are quite involved, but it is necessary to repeat them here in some detail, since it is from the facts presented, construed in the light most favorable to appellee, that we must determine whether Harrison was entitled to have its case put to the jury. The Cane Run project was part of a larger expansion program which had been in the planning stage at Louisville for some five years prior to 1968. Although Louisville had its own special construction department capable of doing all the work on this project, the press of work persuaded it to solicit bids for the wire stringing aspect of the project. Louisville did, however, plan to construct the foundations and erect the steel towers which would support the transmission line.

In 1967 Robert Somers, an employee of Louisville’s special construction department, estimated that the wire stringing costs of the Cane Run project, if done by an independent contractor, would total $721,075, including indirects and a 10% profit.

Louisville sent proposals for wire stringing to nine contractors and invited them to a pre-bid conference at its offices in late February or early March of 1968. Harrison was represented at this conference by its vice president, Mr. Allan C. Baker, a man of considerable experience in the construction of high voltage transmission lines. Louisville disseminated to each contractor the various contract documents and job specifica *514 tions relating to the work, and took the representatives, including Baker, on a tour of part of the line. The bidders were also directed to submit with their proposed bids a description of the methods and equipment to be used for the wire stringing. Finally, Louisville expressly reserved the right to open the bids privately and unannounced and to reject any or all bids.

Harrison, an electrical and general contractor, had previously installed high voltage lines such as the one called for on the Cane Run project. Mr. Baker prepared Harrison’s bid.

According to Baker, the wire stringing job for which bids were solicited by Louisville, consisted of six basic operations: hanging insulators and travelers on the towers, installing guard structures, pulling lead lines, pulling conductors, making up dead-ends and jumpers, and clean-up. In preparing Harrison’s bid, Baker assigned a work crew and equipment to each operation. On an “estimating form” Baker estimated separately for each of the six operations involved, the labor costs of each crew assigned to that operation. On an “equipment sheet”, Baker estimated the equipment costs that would be incurred at each operation. He then attached the estimating form of each project to the corresponding equipment sheet. In arriving at Harrison’s bid, Baker apparently computed the total of these estimates, from that data that he had compiled.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Langley v. Credit Suisse First Boston Corp.
89 F. App'x 938 (Sixth Circuit, 2004)
Hanover Insurance v. American Engineering Co.
33 F.3d 727 (Sixth Circuit, 1994)
Guarantee Electric Co. v. Big Rivers Electric Corp.
669 F. Supp. 1371 (W.D. Kentucky, 1987)
Lulling v. Barnaby's Family Inns, Inc.
87 F.R.D. 720 (E.D. Wisconsin, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
512 F.2d 511, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nat-harrison-associates-inc-v-louisville-gas-and-electric-co-and-ohio-ca6-1975.