Nassif v. United States, for Use of Bayer & Mingolla Const. Co., Inc

187 F.2d 794, 1951 U.S. App. LEXIS 2314
CourtCourt of Appeals for the First Circuit
DecidedMarch 23, 1951
Docket4538_1
StatusPublished
Cited by1 cases

This text of 187 F.2d 794 (Nassif v. United States, for Use of Bayer & Mingolla Const. Co., Inc) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nassif v. United States, for Use of Bayer & Mingolla Const. Co., Inc, 187 F.2d 794, 1951 U.S. App. LEXIS 2314 (1st Cir. 1951).

Opinion

WOODBURY, Circuit Judge.

David Nassif, doing business as David Nassif Company, entered into a written contract with the United States to furnish labor and materials, and to perform certain work, in connection with the development and enlargement of an existing military airfield in Bedford, Massachusetts. Under the terms of the contract he as principal, and the defendant, Century Indemnity Company, as surety, executed and delivered to the United States a bond under which each was bound to make prompt payment to all persons supplying labor or materials in the prosecution of the work called for in the contract. Subsequently Nassif entered into a contract with the plaintiff-appellee, Bayer & Mingolla Construction Company, Inc., hereinafter referred to as the Company, under which the latter agreed to complete the work on the airfield which Nassif had already begun in accordance with Nassif’s prime contract with the United States.

In addition to the work called for in the original contract between the United States *796 and Nassif, certain other work and materials were ordered from time to time by the United States through the Army Engineers as the work progressed. These additional items of labor and materials were performed and furnished by the Company under “change orders” negotiated between representatives of the United States and Nassif and agreed to by representatives of the Company. The instant litigation has to do with some of these latter items; it being the Company’s contention that although it supplied all the items called for in “change orders”, it has not been paid for all of them by Nassif.

The present suit was duly instituted under § 2 of the Act of Congress of August 24, 1935, 49 Stat. 794, 40 U.S.C.A. § 270b. We are therefore not concerned with any question of the diversity of the citizenship of the parties or with the amount in controversy. Our appellate jurisdiction under Title 28 U.S.C.A. § 1291 is clear.

After issue had been joined in the court below the plaintiff company moved for reference to a master. The motion was granted and a master appointed, who heard the parties at length and filed a detailed report which concluded with a finding that the defendants were severally liable to the plaintiff in the amount of $24,997.19 with interest thereon. The parties then filed a stipulation in the court below waiving trial by jury and, although reserving the right to introduce further relevant testimony, agreeing that the master’s report should be given the same “force, effect and evidential value as if it had been offered in a trial before a jury”. Furthermore the parties agreed that the decision of the court below should not be accompanied by a written opinion unless the court in its discretion should think otherwise. No opinion was filed.

The court below held hearings at which evidence was introduced and arguments were made and took the case under advisement. It found the plaintiff entitled to recover $35,675.30 from the defendant, nearly $11,000 more than the master had found due, and entered judgment for the plaintiff in accordance with its finding, with interest and costs. The defendants thereupon took this appeal.

On this appeal it is contended that the court below erred in increasing the amount which the master found to be due the plaintiff. Thus the dispute is narrowed down to only two items. One is for regrading and reseeding 14.5 acres of land, and the other is for digging 16,143 linear feet of taxiway gutters and ditches.

Little needs to be said with respect to the item for regrading and reseeding. There is no doubt that this work was done as an “extra”, i. e. that it was work not called for in the original contract between the United States and Nassif, that it was ordered as such by the Army Engineers as provided in the above contract, that it was covered in a duly executed “change order”, and that the plaintiff company actually did the work. The only dispute with respect to this item is as to price.

On conflicting evidence the master found the fair value of this work to be $342.50 per acre, or $4,966.25. The court, however, rejecting evidence the master had found persuasive and believing the testimony of the Army Engineer in charge of the work, which the master had rejected, found $500 per acre to be a fair price for the work. It therefore awarded the plaintiff a total of $7,250 for this item; $2.283.-75 more than the master had found due. The fair value, and hence the price to be paid for the work, is a pure question of fact and the evidence bearing thereon is conflicting. There being ample testimonial basis in the record for the conclusion reached by the court below its finding is not to be disturbed on appeal under principles too familiar to require any citation other than Rule 52(a), Fed.Rules Civ.Proc., 28 U.S.C.A. Moreover, $500 per acre was the original price agreed upon between the United States and Nassif in the “change order” covering the work; it was the price subsequently agreed upon between Nassif himself and the plaintiff’s general superintendent when the latter agreed on behalf of the plaintiff to do the work, and it would appear that it was also the price which the United States paid Nassif for it.

*797 The item for digging taxiway gutters and ditches calls for slightly more extended consideration. Here again it is not disputed that the work was an extra not called for in the specifications of the original contract, that dt was ordered by the Army Engineers and covered by a duly agreed upon and executed “change order”, and that the plaintiff company actually did the work. The question is whether the work belongs in the category of “common excavation” which was to be paid for under the terms of the original contract at an agreed unit price per cubic yard and as such had been included in a larger general item of “common excavation” for which the plaintiff had been paid by Nassif, or whether, on the other hand, it wa's a special sort of excavation requiring a substantial amount of hand labor the fair and reasonable value of which amounted to $8,394.36, for which the plaintiff has not been paid. The master found that the work had been charged to the defendant by the plaintiff as “common excavation”, and that the defendant had paid the plaintiff for it on that basis at the agreed unit price per cubic yard. He therefore awarded the plaintiff nothing on this item.

The court, however, took a different view. Apparently, although without a memorandum opinion we do not know, it regarded the work as a special sort of excavation, which had not been included in the general item of “common excavation” for which the plaintiff had been paid, for it awarded the plaintiff $8,394.36 for the item, that being the lump sum agreed upon for the work in the “change order” covering it.

The evidence introduced before the master is not before us. We therefore do not know the evidentiary basis for his conclusion that the plaintiff company’s .engineer included the work done in digging extra taxiway gutters and ditches in his computation of extra “common excavation” and billed it as such to the defendant, Nassif, at the unit price per cubic yard agreed upon for such work in the latter’s contract with the United States.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States Ex Rel. Viglione v. Klefstad Engineering Co.
324 F. Supp. 972 (W.D. Pennsylvania, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
187 F.2d 794, 1951 U.S. App. LEXIS 2314, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nassif-v-united-states-for-use-of-bayer-mingolla-const-co-inc-ca1-1951.