Nassau Power Corp. v. Beard

601 So. 2d 1175, 17 Fla. L. Weekly Supp. 314, 1992 Fla. LEXIS 998, 1992 WL 110902
CourtSupreme Court of Florida
DecidedMay 28, 1992
Docket78275
StatusPublished
Cited by3 cases

This text of 601 So. 2d 1175 (Nassau Power Corp. v. Beard) is published on Counsel Stack Legal Research, covering Supreme Court of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nassau Power Corp. v. Beard, 601 So. 2d 1175, 17 Fla. L. Weekly Supp. 314, 1992 Fla. LEXIS 998, 1992 WL 110902 (Fla. 1992).

Opinion

601 So.2d 1175 (1992)

NASSAU POWER CORPORATION, Appellant,
v.
Thomas M. BEARD, etc., et al., Appellees.

No. 78275.

Supreme Court of Florida.

May 28, 1992.

*1176 Joseph A. McGlothlin, Vicki Gordon Kaufman, Stephen O. Decker and Matthew D. Soyster of McWhirter, Grandoff & Reeves, P.A., Tallahassee, and Edward Berlin and J. Phillip Jordan of Swidler & Berlin, Chartered, Washington, D.C., for appellant.

Robert D. Vandiver, General Counsel and Marsha E. Rule, Associate General Counsel, Florida Public Service Com'n, Matthew M. Childs, P.A., Charles A. Guyton and C. Alan Lawson of Steel, Hector and Davis, Tallahassee, Florida Power and Light Co., for appellees.

BARKETT, Justice.

This case is before the Court on direct appeal from two final orders of the Florida Public Service Commission (PSC or Commission)[1] relating to the manner in which the PSC determines the "need" for a power plant under the Florida Electrical Power Plant Siting Act (Siting Act).[2] At issue is the relationship, if any, between the requirements of the Siting Act and the requirements of the PSC's regulations[3] governing small power producers and cogenerators.[4]

The Siting Act was passed by the legislature in 1973 for the purpose of minimizing the adverse impact of power plants on the environment. See § 403.502, Fla. Stat. (1989). That Act establishes a site certification process that requires the PSC to determine the need for any proposed power plants, including cogenerators, based on the criteria set forth in section 403.519, Florida Statutes (1989).[5] Section 403.519 requires the PSC to make specific findings for each electric generating facility proposed in Florida, as to (1) electric system reliability and integrity; (2) the need to provide adequate electricity at a reasonable cost; (3) whether the proposed facility is *1177 the most cost-effective alternative available for supplying electricity; and (4) conservation measures reasonably available to mitigate the need for the plant.

Prior to 1990, the PSC did not determine the second and third criteria based on any separate, independent factual basis. Instead, the PSC merely presumed the need for and cost-effectiveness of cogenerators based on the prior approval of the amount of cogenerated power that would have to be purchased by Florida utilities calculated according to the criteria set forth in the cogeneration regulations.[6]See Order No. 22341 (Dec. 26, 1989); Fla. Admin. Code Rule 25-17.083 (repealed 1990).

These cogeneration regulations were promulgated by the PSC in accordance with the mandate of the Public Utilities Regulatory Policies Act (PURPA). 16 U.S.C. §§ 2601-2645 (1988). One of the purposes of PURPA was to foster the development of cogeneration by establishing a mandatory wholesale market for cogenerated electric power. See 16 U.S.C. § 2601(2) (1988); id. § 824a-3.

Under the cogeneration regulations, Florida utilities are required to purchase cogenerated power based on the utilities' "avoided costs" — that is, the costs that the utilities would incur to produce the same amount of electricity if they did not instead purchase the cogenerated power from a qualifying facility.[7]See 18 C.F.R. § 292.101(b)(1) (1991). At all times relevant to this appeal, the avoided costs were calculated on a statewide utility basis, not an individual utility basis. Fla. Admin. Code Rule 25-17.083(4) (repealed 1990). These costs in turn formed the basis for calculating the terms of so-called "standard offer contracts" — contracts to sell electricity that consist of preapproved terms and conditions that the PSC requires utilities, such as Florida Power and Light Company (FPL), to honor with all qualified cogeneration facilities.

Presuming need under the Siting Act by way of the cogeneration regulations, however, presented the awkward possibility that individual utilities would be required to purchase electricity that neither they nor their customers actually needed. See Fla. Admin. Code Rule 25-17.083(5) (repealed 1990). The PSC recognized this problem and in March 1989 held a public hearing to reexamine aspects of its cogeneration policy. The PSC gave notice to every investor-owned electric utility in the state, as well as numerous cogenerators operating as qualified facilities. In the resulting order, No. 22341, the Commission announced that it would no longer automatically presume, based on the cogeneration regulations, that a particular cogeneration facility power plant was needed when making determinations under the Siting Act, but would instead evaluate the need for a cogenerator's capacity based on the individual, localized need of the facility ultimately consuming the cogenerated power. In the Commission's own words, it would no longer use the findings under the cogeneration regulations "as a surrogate for the factual findings required by the Siting Act." Order No. 22341.

On January 1, 1990, one of the parties requested reconsideration of Order No. 22341. On June 15, 1990, before the order became final, appellant, Nassau Power Corporation (Nassau), filed a Petition to Intervene. Nassau, a cogenerator operating as a qualified facility under federal and state law, was seeking permission to build a 435-megawatt gas-fired electric power plant on Amelia Island situated off Florida's northeast coast. On the same date, June 15, 1990, after filing its Petition to Intervene, and thus with full knowledge of the PSC's policy determination in Order No. 22341, Nassau submitted its standard offer contract to sell its anticipated 435 megawatt generating capacity to FPL. The terms of *1178 the standard offer contract were calculated based on the projected statewide need for power in 1996 calculated according to the criteria set forth in the cogeneration regulations.

In Order No. 23792, issued November 27, 1990, the PSC tentatively approved Nassau's contract,[8] but held, consistent with Order No. 22341, that Nassau's standard offer would still have to be evaluated against individual utility need (i.e., the needs of FPL's customers) in separate need determination proceedings under the Siting Act. Nassau appeals this latter portion of Order No. 23792, as well as Order No. 24672 denying its Motion for Reconsideration on this issue.

Nassau argues that the PSC's cogeneration regulations, and its previous policy, prohibit the PSC from determining the need for Nassau's power under the Siting Act based on FPL's individual utility needs, and instead require the PSC to determine need based on the projected statewide electric utility need. The PSC, on the other hand, contends that, notwithstanding its prior practice of not specifically determining actual local needs when evaluating the need for cogenerated power, it is not bound by the cogeneration regulations and is in fact required to assess actual local needs when making need determinations under the Siting Act.

In our view, the PSC's prior practice of presuming need, as opposed to determining actual need, cannot be used now to force the PSC to abrogate its statutory responsibilities under the Siting Act.[9]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tampa Elec. Co. v. Garcia
767 So. 2d 428 (Supreme Court of Florida, 2000)
Nassau Power Corp. v. Deason
641 So. 2d 396 (Supreme Court of Florida, 1994)
Floridians for Responsible Utility Growth v. Beard
621 So. 2d 410 (Supreme Court of Florida, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
601 So. 2d 1175, 17 Fla. L. Weekly Supp. 314, 1992 Fla. LEXIS 998, 1992 WL 110902, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nassau-power-corp-v-beard-fla-1992.