Nasif v. Booth

72 So. 2d 440, 221 Miss. 126, 64 Adv. S. 20, 1954 Miss. LEXIS 521
CourtMississippi Supreme Court
DecidedMay 10, 1954
Docket39220
StatusPublished
Cited by8 cases

This text of 72 So. 2d 440 (Nasif v. Booth) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nasif v. Booth, 72 So. 2d 440, 221 Miss. 126, 64 Adv. S. 20, 1954 Miss. LEXIS 521 (Mich. 1954).

Opinion

Halo, J.

This case is a setpiel to Nasif v. Hawkins, 212 Miss. 834, 55 So. 2d 497. We there affirmed a judgment in favor of Hawkins and against the Nasifs for damages to his party wall between a building owned by Hawkins and a building known as the Seay building leased by Nasif in the City of Vicksburg. After paying off that judgment, the Nasifs brought this suit against (George T. Booth, Sr., et al., operating a plumbing business as partners, to recover the amount which they had paid Hawkins under the judgment. Prom an adverse judgment in the second suit the Nasifs appeal.

The declaration was in four counts. The first count was upon an alleged express contract of indemnity; the second count was upon an alleged implied contract of indemnity; the third count was based upon negligence in violation of Section 1006, Code of 1942; and *132 the fourth count adopted all charges of negligence laid in the third count and in addition alleged an implied obligation to indemnify plaintiffs for such negligence. The lower court overruled a demurrer to the declaration which raised the question that two counts were based upon contract and two on tort. It then overruled a motion to strike counts one and two. Upon conclusion of the evidence for plaintiffs it sustained a motion to dismiss counts one and two, and submitted the cause to the jury on the question of negligence. The jury found for the defendants and judgment was entered accordingly.

After renting the Seay building the Nasifs employed an architect who prepared detailed plans and specifications for remodeling the interior thereof so as to turn it into a restaurant which they expected to open. The plumbing work was to be done under a separate contract. Appellees filed with appellants a written proposal to do this work for a specified amount, but appellants, while retaining this proposal, did not accept the same. On the contrary, they made arrangements with a competitor of appellees to do the work. This competitor entered upon the premises and started the work, first breaking up the concrete floor and opening a ditch about thirty inches from and parallel with the party wall, for the purpose of laying a sewer line. This ditch began near the rear of the Seay building and extended to a point about half the distance to the front of the building. It was along a line which the architect had specified on his plans and “lay-out” drawing for the plumbing installation. For some reason not disclosed by the record the appellants dispensed with the services of this plumber and then made an oral contract with appellees to complete the job at a slight increase in price over their original proposal. Appellees then entered upon the premises and completed the ditch along- the line specified by the architect to the sewer main in the street in front of the building. They installed the connection *133 to the sewer main and laid and connected the sewer line from the main to a point just inside the Seay building. This was two or three days after appellees began working. Work hours for the day having ended, appellees and their employees left the job until the next morning. During that night there came the heaviest rainfall ever recorded by the weather bureau in Vicksburg for a thirty-minute period. It was described as a cloudburst. The ditch became wet and on the following morning it was discovered that the party wall had settled slightly and had cracked at a point about midway its length. The city building inspector was called and pronounced it dangerous and ordered it torn down.

There was a sharp conflict in the evidence as to where the water came from which got into the ditch. The appellants claimed and were supported by testimony which would have warranted the jury in believing that the water backed up from the street into the open ditch which was on a gradual slope all the way from the rear to the front of the building. On the other hand, there was evidence for the appellees which would have justified the jury in finding that the water did not back up into the inside of the building, but that some of it fell directly into the building from an uncovered space overhead near the front and that some of it seeped into the soil in the Hawkins building from the poor connections in a drainage line underneath the floor thereof which extended from and drained an open courtyard in the rear of the Hawkins building for the entire length of the building and into the street. likewise there was a conflict in the evidence as to whether the banks of the ditch in the Seay building gave way and sloughed off, and as to whether the walls of the ditch should have been braced to prevent caving. We mention these conflicts as stepping stones to a consideration of the points raised by appellants.

It is contended that notwithstanding the fact that appellees only submitted a signed proposal to appellants, *134 which was never signed by appellants, that nevertheless it was accepted with oral modifications and thereby became an express contract of indemnity wherennder appellees agreed to indemnify and save harmless the appellants against anything that might happen to the party wall. Reliance is placed on the following provision of the proposal: “The contractor is amply protected by Workmen’s Compensation, Public Liability and property damage insurance in connection with all work executed by it on the purchaser’s premises and assumes all risks, incident to the work done by it, provided for such insurance.” It will be at once noted that the property damage insurance mentioned is only in connection with the work executed by appellees and the risks assumed by them are only incident to the work done by them. They did not agree to indemnify appellants for negligence of appellants’ architect if he specified the sewer line to be laid too close to the party wall nor did they agree to indemnify appellants for the negligence, if any, of the plumber who had started the job before appellees took over, nor did they agree to indemnify appellants for the defects, if any, in the sewer drain which was already laid underneath the floor of the Hawkins building. As stated at the outset, the second count was upon an implied contract of indemnity, and it was alleged therein that this was an “implied obligation on the part of the defendants to the plaintiffs to indemnify them from any liability or loss occasioned and proximately resulting to them by reason of and incident to the work done by the defendants under and by virtue of said contract”. The implied contract as alleged imposed no greater obligation on appellees than did the alleged express contract of indemnity.

Appellants contend that the trial court erred in dismissing counts one and two of the declaration and that they were entitled to a peremptory instruction thereon. It is our opinion that the demurrer should have been sustained for the reason that the declaration clearly con *135 tains two counts on contract and two on tort sounding in negligence, and consequently there was no error in dismissing the first two counts. Especially is this true since all the proof was directed to the issue of negligence. As we said in Potomac Insurance Co. v. Wilkinson, 213 Miss. 520, 526, 57 So. 2d 158

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Progressive Casualty Insurance Company v. Keys
317 So. 2d 396 (Mississippi Supreme Court, 1975)
Bush v. City of Laurel
215 So. 2d 256 (Mississippi Supreme Court, 1968)
Delta Construction Co. of Jackson v. City of Jackson
198 So. 2d 592 (Mississippi Supreme Court, 1967)
Stringer v. Consumers Credit Corp.
105 So. 2d 756 (Mississippi Supreme Court, 1958)
Bowyer & Johnson Construction Co. v. White
255 F.2d 482 (Fifth Circuit, 1958)
Bowyer & Johnson Construction Company v. Joe White
255 F.2d 482 (Fifth Circuit, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
72 So. 2d 440, 221 Miss. 126, 64 Adv. S. 20, 1954 Miss. LEXIS 521, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nasif-v-booth-miss-1954.