THOMAS, J.

(1) The complaint as amended contained two counts, one ex contractu and the other ex delicto, as is now authorized by statute. — Code, § 5329. The first counted upon a breach by the defendant, as a common carrier, of an express provision of the contract of carriage, and alleged, so far as is material to the consideration of the questions raised on this appeal, as follows: “That on, to-wit, the 11th day of March, 1913, the defendant was operating a railroad and engaged in the business of a common carrier, and on said date entered into a contract with plaintiff to carry 25 mules and one horse, the property of plaintiffs, from Martin, Tenn., to Huntsville, Ala., for hire, and by the terms of said contract, and as a part of the consideration thereof, said defendant agreed that said mules and horses were not to be unloaded in Nashville, Tenn., and plaintiffs aver that, in violation of said stipulation in said contract above set out, defendant unloaded said mules and horses at Nashville, Tenn.; that while unloaded there said mules and horse were exposed to pleural pneumonia, a contagious or infectious disease, and four head of said mules contracted said disease and afterwards died from the same.”

The second count declared upon the negligence of defendant as a common carrier in violation of an implied duty imposed by law and arising from the relationship of plaintiff and defendant as shipper and carrier, respectively, as shown in the count, which averred, so far as pertinent to the points reserved, as follows: “That on, to-wit, the 11th day of March, 1913, the defendant was operating a railroad and engaged in the business of a common carrier, and on said date accepted from plaintiffs for transportation for hire, from Martin, Tenn., to Huntsville, Ala., 25 mules and 1 horse, the property of plaintiffs. Plaintiffs aver that while said mules were in the possession of said defendant, for transportation as aforesaid, said defendant negligently exposed said animals, or negligently allowed said animals, or some of them, [383]*383to become exposed to pleural pneumonia, a contagious or infectious disease, and as the result of said exposure 4 of said mules contracted said disease and died of same,” etc.—Southern Railway Co. v. Proctor, 3 Ala. App. 413, 57 South. 513.

The defendant, which is apellant here, pleaded, in short, by consent, the general issue, with leave to give in evidence as a bar to the action any matter that might be specially pleaded, and at the conclusion of the evidence requested the general affirmative charge, separately and severally as to each count of the complaint, the refusal of the court to give which in each instance constitutes the chief ground of defendant’s insistence upon error.

(2-4) It cannot be doubted that, in order for the plaintiffs to recover under the first count of the complaint, it was incumbent upon them to prove that the contract of carriage contained the stipulation as alleged in said count, since such stipulation is the very basis and gist of the right of action declared on. The plaintiffs insist that the contract of carriage with defendant was a parol one, and that it contained the stipulation mentioned; and, while the evidence offered by plaintiffs tended to show that, on the day before the shipment was made, one of the plaintiffs, Braley, who had purchased the stock for the plaintiffs, at Fulton, Ky., a town 12 miles from Martin, Tenn,. went from said town down to Martin, Tenn., where defendant’s line of railway commenced, and told defendant’s agent that he (Braley) wanted to ship his stock home to Huntsville, Ala., over defendant’s line, provided defendant could get them through without stopping them at Nashville, Tenn., and putting them off of the cars at the stockyards there for feeding, watering, and resting, which was defendant’s custom as to intérstate shipments, followed by it in order to avoid a violation of the United States statutes (Fed. Stat. Anno. Supp. 1909), prohibiting under penalty common carriers from confining stock constituting an interstate shipment in cars for a longer period than 36 hours, without putting them off and watering, feeding, and resting them; and, while the plaintiff’s evidence also tends to show that defendant’s said agent then told said Braley that if he (Braley) would wait until the next day, at an hour named, to make the shipment, it could be gotten through to Huntsville over defendant’s “Green Line,” agreeable to the statutes mentioned, without stopping and putting the stock off at Nashville, yet, the evidence fails to show an acceptance by plaintiff of this proposition made by the defend[384]*384ant’s said agent, but shows without dispute that Braley proceeded home to Huntsville, and that the stock were afterwards shipped, not from Martin, Tenn., but from Fulton, Ky., and not by plaintiffs, but by one E. C. Reed, on a through bill of lading issued to him as consignor, not by the defendant, but by the Illinois Central Railroad Company, as-initial carrier, and that at Martin, Tenn., the shipment was delivered by said initial carrier to the defendant as connecting carrier, who accepted it on said through bill of lading, which did not contain any stipulation with reference to not putting the stock off at Nashville, and which contained nothing to indicate or apprise defendant or its agents that this was the shipment to which said Braley had reference in his alleged conversation with defendant’s said agent, as before mentioned. Under this through bill of lading, the defendant, as connecting carrier, accepted the shipment and transported and delivered the stock to plaintiffs Farrell & Braley, as consignees, at Huntsville, in apparent good order, though it appears the shipment was stopped at Nashville, and the stock there put off, watered, fed, and rested for the purpose of complying with the federal statutes cited. While it does appear from the evidence that E. C. Reed, the consignor as named in said through bill of lading, was plaintiffs’ agent in making the shipment, yet the bill of lading did not so disclose, and there was nothing in it, and nothing in the evidence, to show that defendant knew this fact, or any other fact which would reasonably be calculated to lead it or its agents to identify the shipment as being the shipment which said Braley had in the conversation mentioned previously talked with defendant’s agent about making. It may be said in passing,, however, that said agent denied having any such conversation as that claimed by said Braley; but, even assuming that he did, he had a right to expect what the offer, as we interpret it, clearly contemplated, that the stock were to be delivered to defendant at Martin, Tenn., as a new shipment there to be commenced, so that they would not be on a continuous journey without watering, feeding, and resting for a period.longer than that forbidden by the federal statutes mentioned. Certainly it was no acceptance of the offer to ship the stock from Fulton, Ky., on a through bill of lading containing no such stipulation, issued to another party as consignor and by another carrier as initial carrier, and without notifying defendant and without agreement with it that this was to be done. The plaintiff, in order to have [385]*385gotten the benefit of the offer as made, should have brought the stock through the country from Fulton, Ky., to Martin, Tenn., a distance of 12

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ARMY AVIATION CTR. FED. CREDIT U. v. Poston
460 So. 2d 139 (Supreme Court of Alabama, 1984)
Ex Parte Nix
401 So. 2d 64 (Supreme Court of Alabama, 1981)
Chandler v. Hunter
340 So. 2d 818 (Court of Civil Appeals of Alabama, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
70 So. 986, 14 Ala. App. 380, 1915 Ala. App. LEXIS 276, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nashville-c-st-l-ry-v-farell-alactapp-1915.