Nash v. City of Saint Paul

8 Minn. 172
CourtSupreme Court of Minnesota
DecidedJanuary 15, 1863
StatusPublished
Cited by17 cases

This text of 8 Minn. 172 (Nash v. City of Saint Paul) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nash v. City of Saint Paul, 8 Minn. 172 (Mich. 1863).

Opinion

By the Court.

Emmett, C. J.

This is an action brought to recover a balance alleged to be due for work done under a contract for grading a street, entered into between the Plaintiff and the City of Saint Paul, the Defendant. The contract appears to be dated the 5th day of August, a. d. 1857, and countersigned by the Comptroller of the city on the 6th of October following.

The Plaintiff alleges the-making of the contract and the doing of a certain amount of work thereunder, upon which he admits payments to a specified amount; that he was ready [176]*176and able to complete tbe job according to tbe terms of tbe contract, but was prevented from so doing bj tbe interference of tbe Defendant, wbo stopped the work, and refused to ]et tbe Plaintiff proceed therewith. That by reason of tbe non-completion of said work tbe Defendant is not authorized to issue to him, tbe Plaintiff, certificates upon the adjoining lots, in payment, as provided by the charter of said city. And that bad be been permitted to finish said work, and said certificates been issued to him, they would have been worth their face in money. Upon these allegations be demands a judgment against tbe Defendant for the balance due for the work done, at the contract price, after deducting the payments admitted to have been received. ■

The Defendant demurred to the complaint, and the District Court sustained the demurrer. The Plaintiff then appealed to this Court.

The objection made by the demurrer is, that the complaint does not state facts sufficient to constitute a, cause of action ; and the principal ground relied upon in the argument is, that the complaint does not allege that an estimate of the whole expense of the work to be done, and of the proportion thereof to be assessed to each lot, was ever made and filed, as required by the charter; nor that the contract was let to the lowest, bidder.

The decision of this appeal properly depends upon this simple question of pleading, but the parties on the argument in this Court were willing to waive any advantage which either might gain thereby, and desirous of getting at once to' the question upon which their rights must ultimately be determined. The case was therefore presented and argued as ■ though the complaint alleged that the contract had been let to the lowest bidder, but admitted that the estimate- spoken of had never been made or filed.

The Defendant’s counsel insists that the making and filing of these‘estimates were conditions precedent to the power of the Street Commissioners to enter into the contract, and bases his position upon section 6, chapter 7, of the City Charter, which is in the language following:

“ Sso. 6. Whenever the Commissioners shall determine to [177]*177make any public improvement, as authorized by sections three, four and five of this chapter, they shall cause to be made an estimate of the whole expense thereof, and of the proportion to be assessed to each 'lot, which estimate shall be filed with the City Comptroller, for the inspection of parties interested. The said Commissioners shall thereupon enter wito fioniraetfor the doing thereof.”

Sections three, four and five, referred to in said section six, read as follows:

Seo. 3. The Street Commissioners shall have power to order and contract for the making, grading, repairing and cleansing of streets, alleys, public grounds,reservoirs, gutters and sewers, within their respective wards, and to1 direct 'and control the persons employed therein.
“ Sec. 4. Whenever the Street Commissioners shall deem it necessary to construct or repair any sidewalk within their ward, they shall direct the owner or occupant of any lot adjoining said sidewalk, to make or repair the same, at his own proper cost and charge. If such work is not done in the manner and within the time prescribed, the Commissioners shall cause the same to be done at the expense of the lots adjoining such sidewalk.
“ Sec. 5. The cost and expense of surveying streets, alleys, sidewalks, sewers, and of estimating work thereon, and of repairing and cleansing streets and alleys, and of constructing and repairing reservoirs and sewers, shall be chargeable to and payable out of the fund of the proper ward; opening, grading, gravelling, planking or paving streets and alleys, to the centre thereof, shall be chargeable to and payable by the lots fronting on such street or alley. Sewers may be ordered. *****”

We will be greatly aided in giving the proper interpretation to the last clause of section six, as above recited, and may account for its appearance in that connection, by examining somewhat into the amendment which the section has undergone. Prior and up to February 27, 1856, the section read as follows:

. Sec. 6. Whenever the Commissioners shall determine to make any public improvement, as authorized by sections 3,4 [178]*178and 5 of this chapter, they shall cause to be made an estimate of the whole expense thereof, and of the proportion to be assessed and charged to each lot; and vn case of grading streets, alleys or sidewalks, of the number of cubic yards to be filled in, or to be excavated in front of each lot j .and such estimate .¿hall be filed with the City Comptroller, for the inspection of parties interested. The Street Commissioners shall give notice, by advertisement, for ten days, in one or more papers published in St. Paul, to the owner or occupants of the lots or parcels of land fronting on any street, alley or sidewalk ordered to be graded, gravelledplanked or paved, requirvnq them to do the work mentioned in such notice, within a reasonable time, therein to be specified ; and if the said toork shall not be done withm such time, the said Commissioners shall enter into contract for the doing thereof.”

While this section remained in the terms just recited, it appears that all improvements chargeable to the adjoining lots were first required to be made by the lot owners themselves. They were therefore to be duly notified by advertisement to do the work specified, within a reasonable time therein named, and it was only in case of a failure on the part of the lot owners, that the Street Commissioners had a right to make any contract concerning such improvements. But to enable the owners of lots to determine whether it were better for them to make the improvement themselves, or suffer the city to do it for them, and it may be also to enable them to ascertain whether the cost thereof assessed to them would exceed the benefit which their lots .would derive from said improvement, the Street Commissioners were, required to cause certain estimates to be made and filed for the benefit of parties interested.

The sole object of restraining the Commissioners from contracting for such work, in the first instance, seems to have been to enable the lot owners to. do the work themselves, if they saw proper. Their power to contract, however, does not appear to have depended in the least degree upon the m aking or filing of the estimate, but wholly on the fact of the owners having failed to do, fhe work, after due notice — (and there is no pretence, in this case, that .such notice was not [179]*179given.) It is true that the failure to

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ARMCO DRAINAGE & METAL PROD. v. County of Pinellas
137 So. 2d 234 (District Court of Appeal of Florida, 1962)
Inland Products Corp. v. Donovan Inc.
62 N.W.2d 211 (Supreme Court of Minnesota, 1953)
Propper v. Chicago, Rock Island & Pacific Railroad
54 N.W.2d 840 (Supreme Court of Minnesota, 1952)
Hildebrandt v. Hagen
38 N.W.2d 815 (Supreme Court of Minnesota, 1949)
State v. Strong
256 N.W. 900 (Supreme Court of Minnesota, 1934)
Cohen v. Mirviss Manufacturing Co.
216 N.W. 606 (Supreme Court of Minnesota, 1927)
Oahu Railway & Land Co. v. Armstrong
18 Haw. 507 (Hawaii Supreme Court, 1907)
Anderson v. Fuller
51 Fla. 380 (Supreme Court of Florida, 1906)
City of Mankato v. Barber Asphalt Paving Co.
142 F. 329 (Eighth Circuit, 1905)
Winters v. City of Duluth
84 N.W. 788 (Supreme Court of Minnesota, 1901)
Strickland v. Minnesota Type-Foundry Co.
79 N.W. 674 (Supreme Court of Minnesota, 1899)
Portland v. Bituminous Paving Co.
44 L.R.A. 527 (Oregon Supreme Court, 1898)
Merchants Insurance v. Herber
71 N.W. 624 (Supreme Court of Minnesota, 1897)
Hurd v. Hurd
65 N.W. 728 (Supreme Court of Minnesota, 1896)
Board of Supervisors v. Arrighi
54 Miss. 668 (Mississippi Supreme Court, 1877)
Nash v. City of St. Paul
11 Minn. 174 (Supreme Court of Minnesota, 1866)
Griggs v. City of St. Paul
9 Minn. 246 (Supreme Court of Minnesota, 1864)

Cite This Page — Counsel Stack

Bluebook (online)
8 Minn. 172, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nash-v-city-of-saint-paul-minn-1863.