Naragon v. Dayton Power Light, Unpublished Decision (3-30-1998)

CourtOhio Court of Appeals
DecidedMarch 30, 1998
DocketCASE NO. 17-97-21.
StatusUnpublished

This text of Naragon v. Dayton Power Light, Unpublished Decision (3-30-1998) (Naragon v. Dayton Power Light, Unpublished Decision (3-30-1998)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Naragon v. Dayton Power Light, Unpublished Decision (3-30-1998), (Ohio Ct. App. 1998).

Opinion

Nancy Naragon, (Naragon) administratrix for the estate of her deceased husband, Timothy Naragon (Tim), appeals from judgment of dismissal entered in the Shelby County Court of Common Pleas. Summary judgment was granted in favor of all three defendants: Dayton Power Light Co. (DPL), Henkels McCoy, Inc. (HM) and American Line Builders Joint Apprenticeship Training Committee (ALBAT). Naragon's motion for summary judgment against all three defendants was denied.

This action stems from Timothy Naragon's death on November 9, 1993 while working on above ground power lines in Shelby County, Ohio. Tim, employed by HM as a sixth step apprentice linesman, was electrocuted while performing distribution line maintenance on power lines owned by DPL.

On the day of the incident, Karl Matilla (Karl), Tim's foreman, Tim and Mark Cameron, the groundsman, were assigned by HM to replace lightning arresters1 and cutouts2 affixed to the first utility pole south of State Route 274 in Jackson Center. Karl and Tim went aloft in the three by four foot insulated bucket. Tim was positioned near the partially energized phase cutouts and Karl was positioned closest to the bucket controls, to the side and rear of Tim. Starting with the first of the three phases, the A phase, the two men worked west and affixed insulated rubber blankets and hoses to exposed parts of phases, A, B and C respectively. Karl and Tim first installed replacement parts on the C phase. The bucket was then moved between the C and B phase as the men replaced equipment on the B phase.

Upon finishing the B phase installation, Karl states that the B phase was recovered with a rubber blanket. Karl then asked Tim if he was "in the clear,"as Karl intended to remove the protective blanket and hose from the C phase. Karl states further that his back was to Tim, but he heard Tim say "Okay" in response to his question. Karl then began to remove the blanket from the C phase when he heard a roar behind him. Karl turned and saw Tim on fire, slumped over in the bottom of the bucket.

Tim's chest and chin came in contact with the B phase cutout allowing 7,200 volts of electricity to enter his body. Tim's injuries were fatal. Karl could offer no explanation as to how Tim came in contact with the cutout. After the incident, the protective blanket originally clamped around the B phase cutout was observed only partially covering the cutout, exposed to where Tim was standing. There is no evidence in the record, however, indicating that Karl or any other HM employee observed the B phase cutout exposed to Tim immediately prior to the incident.

A few months prior to his electrocution Tim was credited with 5,000 hours of experience from the ALBAT training program which certified Tim as a sixth step apprentice, competent to perform energized line work while under supervision. Though Tim had worked in the utilities construction business for well over 20 years, he had primarily been a groundsman, truck driver and a transmission linesman, working on only de-energized lines. Distribution line work requires work on energized lines. An ALBAT representative, Wally Sickles, testified at his deposition that Tim's prior above ground de-energized line work was the primary reason he was credited with 5,000 hours experience. Sickles explained that Tim had to know his way around energized lines to work on de- energized lines.

Another ALBAT representative was deposed by the Appellant, regional Director, Alfred Pelletier. Pelletier stated that Tim's 5,000 hours were credited based on two factors 1) Tim's experience and 2) ALBAT's concern that Tim would be hurt economically if placed in a lower apprenticeship slot. Tim worked energized lines for only about three months prior to his death and had not yet begun his ALBAT energized line training classes, which were scheduled to start the week after his death.

Naragon asserts three assignments of error.

I. THE TRIAL COURT ERRED BY REFUSING TO ALLOW ADEQUATE ANDUNENCUMBERED DISCOVERY.

II. THE TRIAL COURT ERRED WHEN IT GRANTED APPELLEES' MOTIONS FOR SUMMARY JUDGMENT BECAUSE THERE EXISTS, AT THE VERY LEAST, GENUINE ISSUES OF MATERIAL FACT.

III. THE TRIAL COURT ERRED BY MISAPPLYING THE LAW OF INTENTIONAL EMPLOYMENT TORTS AND EMPLOYER DUTIES.

I.
Naragon's first assignment claims the "trial court erred by refusing to allow adequate and unencumbered discovery." Naragon claims her discovery was encumbered because counsel for DPL improperly demanded payment for their discovery costs citing an order from a previously dismissed federal case. Naragon contends that absent such demands from DPL, she could have conducted necessary depositions. Naragon's argument is not well taken.

The civil rules do not require permission be obtained from the opposing party or counsel before a deposition may be conducted. To the contrary, "[a]fter commencement of the action, any party may take the testimony of any person, including a party, by deposition." Civ. R. 30(A). Further, the appearance of the opposing party or witness may be compelled either through a subpoena or proper notice. Civ. R. 30(A). While agreed discovery and the courtesy of counsel are encouraged, the Civil Rules provide relief for delay caused by recalcitrant witnesses and counsel. The record discloses no attempts by Naragon to use the rules to get needed discovery.

Naragon claims the trial court erred when it denied her request for a second 90 day continuance to complete discovery. The trial court ruled that Naragon had been afforded sufficient time for discovery and noted that "extensive discovery was conducted in the federal action." Citing Civ. R. 56(F), Naragon claims that a party opposing a motion for summary judgment shall be liberally afforded time to complete discovery. While Civ. R. 56(F) does permit a continuance for additional discovery, a request therefore must be proper. Civil Rule 56(F) provides:

Should it appear from the affidavits of a party opposing the motion for summary judgment that the party cannot for sufficient reasons stated present by affidavit facts essential to justify the party's opposition, the court may refuse the application for judgment or may order a continuance to permit affidavits to be obtained or discovery to be had or may make such other order as is just. (emphasis added).

Civ. R. 56(F).

To avail oneself to a Civ. R. 56(F) continuance, the adverse party must file an affidavit stating sufficient reasons why they are unable to present facts essential to establish opposition to a motion for summary judgment. Grange Mut. Cas. Co. v. State Auto.Mut. Ins. Co. (1983), 13 Ohio App.3d 217, 468 N.E.2d 909; andClose v. Ebersole (May 29, 1990), Logan App. No. 8-89-1, unreported. Here, Naragon filed no such affidavit. Without an explanation as to why Naragon was unable to present facts in opposition to the defendants' motions for summary judgment, the motions were properly before the trial court for decision. Civ. R. 56(F); and Gates Mills Investment Co. v. Pepper Pike (1978),59 Ohio App.2d 155, 392 N.E.2d 1316.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Midwest Specialties, Inc. v. Firestone Tire & Rubber Co.
536 N.E.2d 411 (Ohio Court of Appeals, 1988)
Stamper v. Middletown Hospital Ass'n
582 N.E.2d 1040 (Ohio Court of Appeals, 1989)
Gates Mills Investment Co. v. Village of Pepper Pike
392 N.E.2d 1316 (Ohio Court of Appeals, 1978)
Whiteleather v. Yosowitz
461 N.E.2d 1331 (Ohio Court of Appeals, 1983)
Feichtner v. City of Cleveland
642 N.E.2d 657 (Ohio Court of Appeals, 1994)
Stephens v. A-Able Rents Co.
654 N.E.2d 1315 (Ohio Court of Appeals, 1995)
Grange Mutual Casualty Co. v. State Automobile Mutual Insurance
468 N.E.2d 909 (Ohio Court of Appeals, 1983)
Nice v. City of Marysville
611 N.E.2d 468 (Ohio Court of Appeals, 1992)
Strother v. Hutchinson
423 N.E.2d 467 (Ohio Supreme Court, 1981)
Hirschbach v. Cincinnati Gas & Electric Co.
452 N.E.2d 326 (Ohio Supreme Court, 1983)
Cafferkey v. Turner Construction Co.
488 N.E.2d 189 (Ohio Supreme Court, 1986)
Bostic v. Connor
524 N.E.2d 881 (Ohio Supreme Court, 1988)
Fyffe v. Jeno's, Inc.
570 N.E.2d 1108 (Ohio Supreme Court, 1991)
Brady v. Safety-Kleen Corp.
576 N.E.2d 722 (Ohio Supreme Court, 1991)
Bond v. Howard Corp.
650 N.E.2d 416 (Ohio Supreme Court, 1995)
Dresher v. Burt
662 N.E.2d 264 (Ohio Supreme Court, 1996)
Kulch v. Structural Fibers, Inc.
677 N.E.2d 308 (Ohio Supreme Court, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
Naragon v. Dayton Power Light, Unpublished Decision (3-30-1998), Counsel Stack Legal Research, https://law.counselstack.com/opinion/naragon-v-dayton-power-light-unpublished-decision-3-30-1998-ohioctapp-1998.