Nannis Terpening & Associates, Inc. v. Mark Smith Construction Co.

318 S.E.2d 89, 171 Ga. App. 111, 1984 Ga. App. LEXIS 2115
CourtCourt of Appeals of Georgia
DecidedMay 14, 1984
Docket67721, 67722
StatusPublished
Cited by19 cases

This text of 318 S.E.2d 89 (Nannis Terpening & Associates, Inc. v. Mark Smith Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nannis Terpening & Associates, Inc. v. Mark Smith Construction Co., 318 S.E.2d 89, 171 Ga. App. 111, 1984 Ga. App. LEXIS 2115 (Ga. Ct. App. 1984).

Opinion

Carley, Judge.

The litigation underlying the instant appeals had its genesis in a decision by the DeKalb County Board of Education (Board) to have a baseball stadium constructed at DeKalb Community College. The Board engaged appellant-defendant Henry H. Jordan (Jordan) to prepare the architectural plans and specifications for the stadium. Mr. Jordan, in turn, engaged appellant-third party defendant Nannis Terpening & Associates, Inc. (NT&A) to prepare the structural portion of the plans and specifications. The Board subsequently hired appellee-plaintiff Mark Smith Construction Company (Mark Smith) to act as the general contractor for the project.

After work on the stadium began, Mark Smith encountered problems. According to Mark Smith, these problems were the direct and proximate result of discrepancies, errors and omissions in the plans and specifications pursuant to which it had contracted to build the stadium and were compounded by Mr. Jordan’s refusal to acknowledge his responsibility therefor when making his periodic reports on the project to the Board. It was on the basis of these allegations that Mark Smith filed suit against Mr. Jordan and commenced the litigation at issue. Count I of Mark Smith’s complaint sought $95,476.80 as compensatory damages for Mr. Jordan’s alleged “gross negligence in the preparation of Plans and Specifications for Construction of the DeKalb Community Baseball Stadium.” Count II realleged Mr. Jordan’s “gross negligence” regarding the plans and specifications, and sought the same amount of compensatory damages plus exemplary damages based upon the further allegations that Mr. Jordan’s subsequent actions with regard to the deficiencies in the *112 plans and specifications when they had been discovered in the construction phase constituted malicious interference “between [Mark Smith], its subcontractors and the [Board].” Count III realleged Mr. Jordan’s “gross negligence” and “malicious interference” and sought the same amount of compensatory damages plus exemplary damages for the alleged malicious breach of Mr. Jordan’s duty as architect for the project “to fairly and justly administer the contract between [Mark Smith] and the [Board].” Mr. Jordan answered, denying the allegations of Mark Smith’s complaint. In addition, Mr. Jordan filed a third party action against NT&A. The allegations of the third party complaint were premised upon NT&A’s preparation of the structural portion of the plans and specifications which had been the subject of Mark Smith’s complaint.

Prior to the commencement of the instant litigation, Mark Smith invoked the arbitration provisions of its contract with the Board, claiming that it was owed some $95,476.80 for the stadium project. The Board responded by filing a counterclaim for arbitration as to an amount that it claimed to be owed as the result of Mark Smith’s alleged defective and incomplete construction work on the stadium. Although the arbitration process was initiated by Mark Smith prior to its institution of the instant litigation, the arbitration hearing itself was not held until sometime after Mark Smith had filed its complaint against Mr. Jordan. A transcript of the arbitration hearing demonstrates that it was conducted with the express understanding that the Board, as principal, would be liable for whatever construction problems Mark Smith had encountered which had been caused by Mr. Jordan, whom the Board had engaged to act as its agent with regard to the project. The arbitration proceedings resulted in an award to Mark Smith and also an award to the Board on its counterclaim. Because the award to the Board was in a lesser amount, a net award in favor of Mark Smith and against the Board resulted. Pursuant to OCGA § 9-9-92, Mark Smith sought judicial confirmation of its arbitration award. Thereafter, judgment was entered on the award. See OCGA § 9-9-95. The Board subsequently satisfied the judgment which had been entered on the award.

Thereafter, Mr. Jordan and NT&A (hereinafter collectively referred to ns “appellants”) filed motions for summary judgment in the instant litigation, which had been pending while the arbitration proceedings were conducted. Their motions were predicated upon the Board’s satisfaction of the judgment which had been entered on Mark Smith’s arbitration award. Appellants’ contention was that the satisfied judgment was a bar to Mark Smith’s further pursuit of litigation against them regarding damages it had incurred as the result of the stadium project. In addition to a motion for summary judgment, NT&A filed a motion to sever the third party action from the main *113 action. Before a ruling on appellants’ respective motions could be obtained, Mark Smith amended its complaint to allege an alternate count for contribution from Mr. Jordan as to that amount awarded to the Board on its arbitration counterclaim. Thereafter, the trial court conducted a hearing on appellants’ motions and denied them all. However, the order denying the motions was certified for immediate review and this court granted appellants’ applications for interlocutory appeals.

1. Appellants’ main contention is that their motions for summary judgment should have been granted pursuant to OCGA § 9-2-4, which provides in relevant part: “A plaintiff may pursue any number of consistent or inconsistent remedies against the same person or different persons until he shall obtain a satisfaction from some of them.” (Emphasis supplied.)

“ ‘Damages are given as compensation for the injury done.’ ‘There can be but one satisfaction of the same damage or injury.’ ” Edmondson v. Hancock, 40 Ga. App. 587 (a, b) (151 SE 114) (1929). It is clear that the $95,476.80 in compensatory damages that Mark Smith (hereinafter referred to as “appellee”) seeks from Mr. Jordan in the instant case represents essentially the same claim that it pursued in the prior arbitration proceeding against the Board, to wit: those damages which it incurred as the result of undertaking construction of the stadium project pursuant to the plans and specifications supplied to it. The only apparent difference is that appellee now seeks those same damages from Mr. Jordan in tort, whereas before it sought them by pursuing its contractual arbitration remedy against the Board. See generally Bell v. Sigal, 129 Ga. App. 249 (199 SE2d 355) (1973). Appellee had no direct contractual privity with appellants regarding the project. Mr. Jordan was hired by the Board to provide architectural services to it regarding the construction of the stadium. NT&A was, in turn, engaged by Mr. Jordan. Accordingly, whatever actions were taken by appellants with regard to the project were taken in their capacities as agents for the Board. It is clear that, in the Board’s capacity as appellants’ principal, its vicarious liability for such damage to appellee as might have resulted from appellants’ performance of their duties regarding the stadium project was an issue which was raised in the context of the arbitration proceedings. The arbitration award, pursuant to which judgment was subsequently entered, was a final adjudication of those claims. See generally Denham v. Williams, 39 Ga. 312 (4) (1869).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Georgia Department of Revenue v. Richard Moore
Court of Appeals of Georgia, 2012
Georgia Department of Revenue v. Moore
730 S.E.2d 671 (Court of Appeals of Georgia, 2012)
McKissick v. AYDELOTT
705 S.E.2d 897 (Court of Appeals of Georgia, 2011)
Bennett v. Cotton
536 S.E.2d 802 (Court of Appeals of Georgia, 2000)
McCaughey v. Murphy
485 S.E.2d 511 (Court of Appeals of Georgia, 1997)
Saunders, Stuckey & Mullis, Inc. v. Citizens Bank & Trust Co.
458 S.E.2d 337 (Supreme Court of Georgia, 1995)
Smith v. Maytag Corp.
455 S.E.2d 379 (Court of Appeals of Georgia, 1995)
Citizens Bank & Trust Co. v. Saunders, Stuckey & Mullis, Inc.
447 S.E.2d 632 (Court of Appeals of Georgia, 1994)
Sorrells Construction Co. v. Chandler Armentrout & Roebuck, P.C.
447 S.E.2d 101 (Court of Appeals of Georgia, 1994)
Brinson v. First American Bank
409 S.E.2d 50 (Court of Appeals of Georgia, 1991)
Klausman v. Klausman
368 S.E.2d 185 (Court of Appeals of Georgia, 1988)
Overstreet v. Georgia Farm Bureau Mutual Insurance
355 S.E.2d 744 (Court of Appeals of Georgia, 1987)
Travillian v. Georgia Farm Bureau Mutual Insurance
355 S.E.2d 677 (Court of Appeals of Georgia, 1987)
OLDEN CAMERA & LENS COMPANY, INC. v. White
347 S.E.2d 696 (Court of Appeals of Georgia, 1986)
Norris v. Atlanta & West Point Railroad
330 S.E.2d 151 (Court of Appeals of Georgia, 1985)
James R. French v. Jinright & Ryan, P.C. Architects
735 F.2d 433 (Eleventh Circuit, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
318 S.E.2d 89, 171 Ga. App. 111, 1984 Ga. App. LEXIS 2115, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nannis-terpening-associates-inc-v-mark-smith-construction-co-gactapp-1984.