Naek Construction Co. v. Wilcox Excavating Construction Co.

726 A.2d 653, 52 Conn. App. 367, 1999 Conn. App. LEXIS 101
CourtConnecticut Appellate Court
DecidedMarch 23, 1999
DocketAC 17548
StatusPublished
Cited by7 cases

This text of 726 A.2d 653 (Naek Construction Co. v. Wilcox Excavating Construction Co.) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Naek Construction Co. v. Wilcox Excavating Construction Co., 726 A.2d 653, 52 Conn. App. 367, 1999 Conn. App. LEXIS 101 (Colo. Ct. App. 1999).

Opinion

Opinion

LANDAU, J.

The plaintiff, Naek Construction Company, Inc., appeals from the judgment of the trial court denying the plaintiffs motion to vacate an arbitration award rendered in favor of the defendant, Wilcox Excavating Construction Company, Inc., and granting the cross application to confirm the award. We affirm the judgment of the trial court.

The following facts are relevant to this appeal. The plaintiff, as general contractor, entered into a contract (prime contract) with the state of Connecticut to construct barracks for Troop C of the state police in Tolland (project). The plaintiff subsequently entered into a subcontract with the defendant, who was to perform the site excavation for the project. Thereafter, disputes arose between the parties and the subcontract was terminated.1 Consequently, the defendant commenced an arbitration proceeding pursuant to the arbitration clause of the subcontract. The plaintiff filed a counterclaim. On June 5, 1996, the arbitrator awarded $96,837.80 to the defendant and $67,152 to the plaintiff on its counterclaim.2 The plaintiff filed an application to vacate the award, pursuant to General Statutes § 52-420, and the defendant filed a cross application to confirm the award. The trial court denied the application [369]*369to vacate the award and granted the defendant’s cross application to confirm the award. This appeal followed.

On appeal, the plaintiff claims3 that the trial court improperly confirmed the award because the form of the award does not conform with the arbitration clause in the subcontract,4 which by reference incorporates the arbitration provision of the prime contract.5 The trial court, however, in ruling that the award conformed with the submission, determined that the original or a copy of the executed prime contract was not in evidence before the arbitrator and that the plaintiff failed to prove that the award did not comply with General Statutes § 4-61 (d) and (e).6 We agree.

[370]*370“The [appellate] court may reverse or modify the decision of the trial court if it determines that the factual findings are clearly erroneous in view of the evidence and pleadings in the whole record, or that the decision is otherwise erroneous in law. . . .” Practice Book § 60-5. “The scope of review by the court of an arbitrator’s power to make an award is limited. Arbitration is a creature of contract between the parties and its autonomy requires a minimum of judicial intrusion. . . . The parties themselves, by the agreement of the submission, define the powers of the arbitrator. . . . The submission constitutes the charter of the entire arbitration proceedings and defines and limits the issues to be decided. . . . When the parties have agreed to a procedure and have delineated the authority of the arbitrator, they must be bound by those limits. . . . An application to vacate or correct an award should be granted when an arbitrator has exceeded his power. In deciding whether an arbitrator has exceeded his power, we need only examine the submission and the award to determine whether the award conforms to the submission. (Citations omitted.) Bic Pen Corp. v. Local No. 134, 183 Conn. 579, 583-84, 440 A.2d 774 (1981).” (Internal quotation marks omitted.) Hartford v. International Assn. of Firefighters, Local 760, 49 Conn. App. 805, 811-12, 717 A.2d 258, cert. denied, 247 Conn. 920, 722 A.2d 809 (1998).

“In determining whether a submission is unrestricted, we look at the authority of the arbitrator. The authority of the arbitrator to adjudicate the controversy is limited only if the agreement contains express language restricting the breadth of issues, reserving explicit [371]*371rights, or conditioning the award on court review. In the absence of such qualifications, an agreement is unrestricted. . . . Perkins & Mario, P. C. v. Annunziata, 45 Conn. App. 237, 239-40, 694 A.2d 1388 (1997).” (Internal quotation marks omitted.) Hartford v. International Assn. of Firefighters, Local 760, supra, 49 Conn. App. 812.

The following additional facts and procedural histoiy are necessary for our resolution of this appeal. During the arbitration proceedings, the parties submitted joint exhibits to the arbitrator. Although one of the exhibits purported to be a copy of the prime contract, it was incomplete and not signed. After the arbitrator issued his award, the plaintiff asked that the arbitrator conform his award to § 4-61 (e). The arbitrator denied the request. The plaintiff then moved to vacate the award claiming that (1) the award did not conform to the contract requirement to follow § 4-61 (e), (2) the arbitrator was guilty of misconduct in accepting evidence after the close of the proceedings and (3) the arbitrator imperfectly executed his powers in not providing a mutual, final and definite award.7 At oral argument, the plaintiff claimed that because the arbitrator failed to issue an award that conforms with § 4-61 (e), it cannot pursue its claims against the state.

The trial court heard oral argument on the parties’ motions on several days. On December 30, 1996, with the consent of the parties and with their agreement as to the language of the request, the trial court asked the arbitrator for an articulation of his award. The arbitrator responded to the trial court on March 14, 1997. The articulation consisted of several attachments or tabs; tab B sets forth how the defendant’s award was computed and tab C sets forth how the plaintiffs award was computed. The plaintiff renewed its application to [372]*372vacate the award, claiming that the articulation articulated only the damages without any conclusions of law or findings of fact as required by § 4-61 (e). The defendant renewed its objection to the application to vacate.

The trial court determined that the submission to the arbitrator was the subcontract between the parties and that article I of the subcontract provides that “the subcontract documents consist of . . . (2) the Prime Contract, consisting of the Agreement between the [state and the plaintiff] . . . .” Article 6.1 of the subcontract provides that arbitration “shall be conducted in the same manner and under the same procedure as provided in the Prime Contract with respect to claims between the [state and the plaintiff] .... If the Prime Contract does not provide for arbitration or fails to specify the manner and procedure for arbitration, it shall be conducted in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association. . . .’’The trial court found that the prime contract between the state and the plaintiff was never in evidence before the arbitrator. In response to the plaintiffs claim that the prime contract was incorporated by reference, the trial court reasoned that, assuming the plaintiffs argument is correct, the original or a copy of the executed prime contract should have been submitted to the arbitrator to ensure its accuracy and to advise the arbitrator of its provisions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kirwan v. Kirwan
197 A.3d 1000 (Connecticut Appellate Court, 2018)
Cote v. Colonial Penn Franklin Insurance
869 A.2d 266 (Connecticut Appellate Court, 2005)
Lurrae v. Lupone, No. Cv0446200s (Nov. 8, 2002)
2002 Conn. Super. Ct. 14397 (Connecticut Superior Court, 2002)
Exley v. Connecticut Yankee Greyhound Racing, Inc.
755 A.2d 990 (Connecticut Appellate Court, 2000)
Afscme v. City of New London, No. 54 16 78 (Sep. 27, 1999)
1999 Conn. Super. Ct. 13034 (Connecticut Superior Court, 1999)
Giardino v. the Belle Haven Land Co., No. Cv 97 0156992 S (Jun. 17, 1999)
1999 Conn. Super. Ct. 7248 (Connecticut Superior Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
726 A.2d 653, 52 Conn. App. 367, 1999 Conn. App. LEXIS 101, Counsel Stack Legal Research, https://law.counselstack.com/opinion/naek-construction-co-v-wilcox-excavating-construction-co-connappct-1999.