Nadeau v. Bagley, No. Cv 93 54613 S (Sep. 12, 1994)

1994 Conn. Super. Ct. 9106
CourtConnecticut Superior Court
DecidedSeptember 12, 1994
DocketNo. CV 93 54613 S
StatusUnpublished

This text of 1994 Conn. Super. Ct. 9106 (Nadeau v. Bagley, No. Cv 93 54613 S (Sep. 12, 1994)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nadeau v. Bagley, No. Cv 93 54613 S (Sep. 12, 1994), 1994 Conn. Super. Ct. 9106 (Colo. Ct. App. 1994).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]MEMORANDUM OF DECISION The plaintiff, on or about February 23, 1993 filed a mechanic's lien on the land record for the town of Staffordville in the amount of $9000.00 on certain real estate owned by the defendants Brian Bagley and Amanda Bagley.

The defendants have filed a Motion for Discharge or Reduction of the Mechanic's Lien.

Factual Background

Sometime prior to February 1993, the Bagleys contracted with Theodore Beuchert, d/b/a The Hartford Construction Group, Inc. as the general contractor (G.C.) to erect a residential dwelling on the property in question.

Thereafter on or about February 2, 1993, the G.C. entered into a sub-contract with Norman Nadeau d/b/a Nadeau Drywall Inc. (Nadeau), wherein Nadeau was to install the drywall for the house for $7800. The contract provided for the work to be completed on or about February 18, 1993.

Bagley paid the G.C. $3400 towards the dry wall work and the G.C. in turn gave Nadeau its check for $3400 on February 3, 1993.

On February 3, 1993 the sheetrock was delivered to the site and Nadeau started the work along with three others Nadeau had hired to help with the job. February 3, 1993 was a Wednesday. Nadeau worked on Wednesday, February 3rd, and on Thursday, February 4th, Nadeau was notified that the G.C. check for $3400 bounced. Nadeau reported the dishonored check to both Theodore Beuchert, the G.C. and to Brian Bagley on February 4th. Bagley responded that he had paid the G.C. and that the G.C. would therefore be paying him in turn. (Bagley's check to the G.C. was in fact deposited and honored). Beuchert told Nadeau to re-deposit the check and it would clear as he Beuchert was wiring money to the account. Satisfied with that representation Nadeau continued to work on Thursday and on Friday, February 5th. Sometime on Friday, Nadeau learned that the second check or the redeposited check would not clear and at that point (the end of the day) left the job.

The G.C. thereafter subcontracted with Windsor Texture Co., Inc. to complete the unfinished dry wall work and Bagley paid the G.C. $5500 in accordance with the invoice from Windsor Texture Co., Inc. (defendant's exhibit 3). The total amount paid by the Bagleys CT Page 9108 for drywall work was $8900 or $1100 over the original contract price.

Windsor Texture was on the job for eight to ten days: Nadeau was on the job for three days (plus approximately one half of a day on Tuesday, February 2, 1993 when he was measuring the job. Nadeau did not complete 50% of the job before leaving the project.

There are several issues to be resolved in this dispute, as follows:

Notice of Lien

The defendants claim the lien is defective because Nadeau failed to serve a Notice of Intent to File a Lien pursuant to § 49-35(a) of the general statutes, which provides in pertinent part, that no subcontractor except one "whose contract with the original contractor is in writing and has been assented to in writing by the other party to the original contract, is entitled to claim any . . . mechanic's lien, unless, after commencing, and not later than sixty days after ceasing to furnish materials or render services for such construction . . . he gives written notice to the owner of the building, lot or plot of land that he has furnished or commenced to furnish materials, or rendered or commenced to render services, and intends to claim a lien therefor on the building, lot or plot of land."

Our Supreme Court has addressed this issue and ruled that "there is no occasion for reading into § 49-35 an implied provision that as [a] matter of law the notice must be served on the owner prior to the filing for record of the certificate of lien under § 49-34" H S Torrington Associates v. Lutz Engingeering [Engineering]Co., 185 Conn. 549, 555 (1981). That case held that two separate notices are not necessary, and service of the lien certificate meets the notice requirements of the mechanic's lien statutes. The lien is not defective because the plaintiff did not serve a separate notice of intent.

Standing

The defendants claim that this suit was brought by Norman Nadeau d/b/a Nadeau Drywall, but that the contracting entity (and the entity which partially performed the work) was Nadeau Drywall, Inc. Therefore the claim is made that the plaintiff Norman Nadeau has no standing to file the lien. CT Page 9109

Norman Nadeau testified that his business was incorporated at one time and called Norman Nadeau, Inc. However, at the time of the contract in February 1993, the corporation had been dissolved and he was at that time a sole proprietorship. His contract with the G.C. was prepared on a form pre-printed with the name Nadeau Drywall, Inc. and Nadeau testified that he was merely using up his old forms. Nadeau's signature is a personal one, not signed in any corporate capacity.

From these facts the Court finds that Norman Nadeau d/b/a was the entity that entered into the contract with the G.C. performed the work, and brought the action. Accordingly, the plaintiff has standing.

Defective Service

The mechanic's lien statutes (§§ 49-34 and 49-35) set out the requirements for serving the certificate of lien. § 49-34 in relevant part states: "A mechanic's lien is not valid, unless the person performing the services or furnishing the materials, . . . serves a true and attested copy of the certificate upon the owner of the building, lot or plot of land in the same manner as is provided for the service of the notice in § 49-35.

§ 49-35 provides in relevant part that: "the notice shall (emphasis added) be served upon the owner . . . if such owner . . . resides in the same town in which the building is being erected . . . by any indifferent person, sheriff, or other proper officer, by leaving with such owner . . . or at his usual place of abode a true and attested copy thereof."

In this case the building being erected was located on Virginia Lane in the town of Stafford. The Bagleys, prior to August 1992 had lived in Enfield, Connecticut. They sold their home in Enfield in June or July 1992 and as of August 1992 were living at 156 Orcuttville Road in Stafford Springs. The town of Stafford is comprised of three postal districts, Stafford, Stafford Springs and Staffordville. The districts of Stafford Springs and Staffordville are within the town of Stafford (Connecticut State Register and Manual).

The plaintiff made service on the Bagleys by mailing true and attested copies of the mechanic's lien to Amanda Bagley at 50 Kimberly Drive, Enfield, Connecticut 06082 and to Brian Bagley at CT Page 9110 the same address in Enfield. They were sent by certified mail return receipt requested and the sheriff's return states he received the return receipts on March 12, 1993. The Enfield Post Office forwarded the notices to the Stafford Springs post office where they were picked up by Amanda Bagley.

It is inescapable that service was not made in accordance with the statutory requirements.

The issue is whether this non-compliance with the statutory requirements of service will render the mechanic's lien void and thus dischargeable.

There are conflicting principles concerning mechanic's liens which come into play in deciding this issue.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

H & S TORRINGTON ASSOCIATES v. Lutz Engineering Co.
441 A.2d 171 (Supreme Court of Connecticut, 1981)
Henry F. Raab Connecticut, Inc. v. J. W. Fisher Co.
438 A.2d 834 (Supreme Court of Connecticut, 1981)
Burque v. Naugatuck Lumber Co.
155 A. 414 (Supreme Court of Connecticut, 1931)
City Lumber Co. of Bridgeport, Inc. v. Borsuk
41 A.2d 775 (Supreme Court of Connecticut, 1945)
American Home Builder's v. Blonder, No. Cv88-0040857 (Jun. 14, 1991)
1991 Conn. Super. Ct. 5624 (Connecticut Superior Court, 1991)
Milone MacBroom, Inc. v. Bysiewicz Corp., No. 68807 (Jul. 15, 1993)
1993 Conn. Super. Ct. 6711-D (Connecticut Superior Court, 1993)
Camputaro v. Stuart Hardwood Corp.
429 A.2d 796 (Supreme Court of Connecticut, 1980)
Seaman v. Climate Control Corp.
436 A.2d 271 (Supreme Court of Connecticut, 1980)
J. C. Penney Properties, Inc. v. Peter M. Santella Co.
555 A.2d 990 (Supreme Court of Connecticut, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
1994 Conn. Super. Ct. 9106, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nadeau-v-bagley-no-cv-93-54613-s-sep-12-1994-connsuperct-1994.