N. E. Redlon Co. v. Franklin Square Corp.

195 A. 348, 89 N.H. 137, 1937 N.H. LEXIS 29
CourtSupreme Court of New Hampshire
DecidedNovember 2, 1937
StatusPublished
Cited by4 cases

This text of 195 A. 348 (N. E. Redlon Co. v. Franklin Square Corp.) is published on Counsel Stack Legal Research, covering Supreme Court of New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
N. E. Redlon Co. v. Franklin Square Corp., 195 A. 348, 89 N.H. 137, 1937 N.H. LEXIS 29 (N.H. 1937).

Opinions

Page, J.

I. The defendant urges that under the contract arbitration of disputed questions was a condition precedent to legal action. Article 40 of the Standard Documents provides that “All questions subject to arbitration under this Contract shall be submitted to arbitration at the choice of either party to the dispute .... The demand for arbitration shall be filed in writing with the Architect.” The referee ruled that the contract did not require arbitration unless called for by one of the parties. This was a correct interpretation of the contract.

The plaintiff first suggested arbitration and on January 20, 1931, it was agreed that the plaintiff should name its arbitrator immediately and that the defendant should name one on January 23. The plaintiff formally demanded arbitration and named an arbitrator on *139 January 21. The defendant never named one, either on January 23 or any later day. With the apparent purpose of securing its mechanic’s lien, the plaintiff brought this action on January 23.

Three days later, the defendant’s treasurer learned of the beginning of suit and announced that no choice of an arbitrator would be made. For nearly a year thereafter the plaintiff made various attempts to get the disputes referred to arbitrators, but the defendant did not yield. At the February, 1932, term, the plaintiff filed a bill praying for an order of arbitration and the stay of trial in the present action. The defendant filed an answer to this bill, alleging that the plaintiff had an adequate remedy at law, that it had elected to proceed at law rather than by arbitration and was not entitled to equitable relief, and that the rights of the parties should be determined in the action at law. It does not appear that the bill in equity was ever heard.

The parties went to trial upon the merits in the action at law. Each submitted its case fully upon the facts. During the trial, the defendant raised the question of jurisdiction, but not as a preliminary one. The referee correctly ruled that both parties were estopped to deny the jurisdiction of the court in this action. The plaintiff desired the court to determine its claim in the pending action. That was a complete waiver of its attempts to get arbitration. The defendant, by resisting the plaintiff’s attempts and its insistence that the plaintiff had no right to arbitration and must pursue its remedy in this action, has also waived any claim to arbitration. Even if the defendant had had a good case for arbitration prior to trial, its claim should have been presented and determined as a preliminary question. The submission to a trial upon the merits without it effectively barred the defendant from a later raising of the question. Sauriolle v. O’Gorman, 86 N. H. 39, 49; American Motorists &c. Company v. Garage, 86 N. H. 362, 364; Gibbs v. Casualty Co., 87 N. H. 19, 21; Howe v. Howe, 87 N. H. 338, 339.

II. A specification in the contract provided as follows: “Floor timbers. Supply and erect long leaf hard pine floor timbers of sizes shown and spaced on centers as indicated in the framing plans.”

The referee found that on August 21, 1929, ten days before the contract was signed, the plaintiff obtained a quotation upon such timber at an average price of $66.50 per thousand delivered at the building. After the work began in September, it was discovered that the hard pine market was sold out, that the price then quoted was $96, and that it would take five or six weeks to get deliveries.

*140 The plaintiff asked the architect for permission to substitute Douglas fir in order to avoid delay. The architect explained the situation to Mr. Rosen who acted for the defendant, Mr. Rosen consented to the use of fir and it was substituted. For practical purposes the fir was found by the referee to be as efficient as hard pine for the purpose for which it was used. The matter of an allowance was not discussed, and none was claimed. The fir cost about $38 a thousand. While the testimony upon most points was contradictory, the record discloses evidence to support all these findings.

To sustain its claim that it is entitled to be allowed what the plaintiff may have saved by the substitution, the defendant urges that valid consent to the change was not obtained because the plaintiff failed to disclose the fact that the Douglas fir cost much less than hard pine. The applicable provision of the Standard Documents is that the owner, “without invalidating the Contract, may order extra work or make changes by altering, adding to or deducting from the work, the Contract Sum being adjusted accordingly.” The specifications went further and gave the architect the right to make such alterations, additions or omissions in the work or materials as he or the owner thought advisable. “The amount to be added or deducted for such change is to be fixed by a schedule of prices previously submitted and agreed upon and to be added or deducted from the final payment as the case may demand.”

The intention was that if the parties by mutual consent amended the contract so that the work was enlarged or diminished, the basis of any price-change was at the same time to be agreed upon. The validity of amendments, even by parol, is pretty generally conceded, but here the parties agreed that such amendments, if made, should be understood as complete and that nothing further was to be implied.

If no price-change was agreed upon, there could be no implication of one. If a possible price-change were involved, the party to be benefited by an adjustment was required to make his claim when he gave consent to the change. This the defendant did not do. The amendment was an agreement for change in the work but not for change in price.

Consistently with this view it has been said of a similar, though less explicit, provision that “it was a condition precedent to either party being entitled to add the value [of the changes] to or deduct it from the contract price that the value of the changes be agreed upon in writing.” Budd &c. Company v. Company, 272 Fed. 775, 777. That case really turned, however, on the fact that the engineer *141 gave consent to the change and the owner did not. The change was an extra and the owner knew nothing about it until the work was finished and payment demanded. But the court seems correctly to have interpreted the contract when it declared that the stipulations “are both equitable and reasonable, and are intended to protect the owner against doubtful claims, and to protect the contractor from doubtful deductions.” The party claiming the protection of the condition, in this case the plaintiff, may of course waive the performance of the condition expressly or by conduct (see a very full note, 66 A. L. R. 649, 662-684), but there is no possibility of concluding from the findings (or from the evidence in the record) that the plaintiff has waived.

A dictum in the Budd case to the effect that the plaintiff’s knowledge concerning relative costs must be communicated to the defendant is inapplicable to the circumstances we are considering. In the present case consent was actually given; in the Budd

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Logic Associates, Inc. v. Time Share Corp.
474 A.2d 1006 (Supreme Court of New Hampshire, 1984)
Tothill v. Richey Insurance Agency, Inc.
374 A.2d 656 (Supreme Court of New Hampshire, 1977)
Gulezian v. Manchester
290 A.2d 631 (Supreme Court of New Hampshire, 1972)
Terminal Const. Corp. v. Bergen, Etc., Authority
112 A.2d 762 (New Jersey Superior Court App Division, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
195 A. 348, 89 N.H. 137, 1937 N.H. LEXIS 29, Counsel Stack Legal Research, https://law.counselstack.com/opinion/n-e-redlon-co-v-franklin-square-corp-nh-1937.