N. Coast Rivers Alliance v. U.S. Dep't of the Interior
Opinion
Lawrence J. O'Neill, UNITED STATES CHIEF DISTRICT JUDGE
I. INTRODUCTION
This case concerns approval by the United States Department of the Interior and its member agency, the United States Bureau of Reclamation (collectively, "Federal Defendants," "Reclamation," or the "Bureau"), of six interim renewal contracts that authorize delivery of water from March 1, 2016, through February 28, 2018, from federal reclamation facilities to certain water districts served by the federal Central Valley Project ("CVP") ("2016-18 Interim Contracts").1 Doc. 64 (First Amended and Supplemental Complaint ("FASC") ). The 2016-18 Interim Contracts at issue in this case provide water service to Westlands Water District, Santa Clara Valley Water District, and Pajaro *1201Valley Water Management Agency (collectively, "Interim Contractors"). See FASC at ¶ 2. A coalition of environmental organizations led by the North Coast Rivers Alliance (collectively, "Plaintiffs") allege in the FASC's first claim for relief that Federal Defendants issued a deficient Revised Environmental Assessment ("EA") and associated Finding of No Significant Impact ("FONSI")2 prior to approval of the Interim Contracts, in violation of the National Environmental Policy Act ("NEPA"),
Before the Court for decision is Westlands Water District's and Panoche Water District's ("Defendant Intervenors") motion to dismiss the second claim for relief in the FASC for failure to state a claim pursuant to Fed. R. Civ. P. 12(b)(6) on the ground that the proposed action does not alter the status quo and therefore cannot trigger NEPA's requirement for preparation of an EIS. ECF No. 69. Federal Defendants join the motion, provided it is decided under the Rule 12(b)(6) standard and note cases declining to limit summary judgment briefing by federal agency defendants based upon denial of an intervenor's motion to dismiss. ECF No. 72. Plaintiffs oppose the motion. ECF No. 71. Defendant Intervenors replied. ECF No. 73. The matter was taken under submission on the papers pursuant to Local Rule 230(g). ECF No. 74.
II. BACKGROUND
This case is related to an earlier case, Pacific Coast Federation of Fishermen's Ass'ns v. U.S. Dep't of the Interior ("PCFFA "), 1:12-cv-01303-LJO-MJS, which concerned a similar challenge to the NEPA review performed in connection with eight interim contracts that covered the period of time from March 1, 2012 through the end of February 2014 ("2012-2014 Interim Contracts"). See PCFFA , ECF No. 47. The first amended complaint in that case ("PCFFA FAC"), filed December 4, 2012, contained two causes of action similar to those alleged here: (1) that the EA prepared by Federal Defendants in connection with the eight Interim Contracts is inadequate; and (2) that Federal Defendants should have prepared an EIS.
Federal Defendants and Defendant Intervenors moved to dismiss both claims in the PCFFA FAC. PCFFA ECF No. 45-46. A March 8, 2013 Order granted the motions in part. PCFFA ECF No. 52; Pac. Coast. Fed'n of Fishermen's Ass'ns v. U.S. Dep't of the Interior ,
While the PCFFA appeal was pending, Reclamation issued its EA and FONSI for the 2016-18 Interim Contracts. Plaintiffs sued, raising claims substantially similar to those in PCFFA : (1) that the EA/FONSI was inadequate under NEPA; and (2) that Reclamation should have prepared an EIS for the 2016-18 Interim Contracts. ECF No. 2.
Free access — add to your briefcase to read the full text and ask questions with AI
Lawrence J. O'Neill, UNITED STATES CHIEF DISTRICT JUDGE
I. INTRODUCTION
This case concerns approval by the United States Department of the Interior and its member agency, the United States Bureau of Reclamation (collectively, "Federal Defendants," "Reclamation," or the "Bureau"), of six interim renewal contracts that authorize delivery of water from March 1, 2016, through February 28, 2018, from federal reclamation facilities to certain water districts served by the federal Central Valley Project ("CVP") ("2016-18 Interim Contracts").1 Doc. 64 (First Amended and Supplemental Complaint ("FASC") ). The 2016-18 Interim Contracts at issue in this case provide water service to Westlands Water District, Santa Clara Valley Water District, and Pajaro *1201Valley Water Management Agency (collectively, "Interim Contractors"). See FASC at ¶ 2. A coalition of environmental organizations led by the North Coast Rivers Alliance (collectively, "Plaintiffs") allege in the FASC's first claim for relief that Federal Defendants issued a deficient Revised Environmental Assessment ("EA") and associated Finding of No Significant Impact ("FONSI")2 prior to approval of the Interim Contracts, in violation of the National Environmental Policy Act ("NEPA"),
Before the Court for decision is Westlands Water District's and Panoche Water District's ("Defendant Intervenors") motion to dismiss the second claim for relief in the FASC for failure to state a claim pursuant to Fed. R. Civ. P. 12(b)(6) on the ground that the proposed action does not alter the status quo and therefore cannot trigger NEPA's requirement for preparation of an EIS. ECF No. 69. Federal Defendants join the motion, provided it is decided under the Rule 12(b)(6) standard and note cases declining to limit summary judgment briefing by federal agency defendants based upon denial of an intervenor's motion to dismiss. ECF No. 72. Plaintiffs oppose the motion. ECF No. 71. Defendant Intervenors replied. ECF No. 73. The matter was taken under submission on the papers pursuant to Local Rule 230(g). ECF No. 74.
II. BACKGROUND
This case is related to an earlier case, Pacific Coast Federation of Fishermen's Ass'ns v. U.S. Dep't of the Interior ("PCFFA "), 1:12-cv-01303-LJO-MJS, which concerned a similar challenge to the NEPA review performed in connection with eight interim contracts that covered the period of time from March 1, 2012 through the end of February 2014 ("2012-2014 Interim Contracts"). See PCFFA , ECF No. 47. The first amended complaint in that case ("PCFFA FAC"), filed December 4, 2012, contained two causes of action similar to those alleged here: (1) that the EA prepared by Federal Defendants in connection with the eight Interim Contracts is inadequate; and (2) that Federal Defendants should have prepared an EIS.
Federal Defendants and Defendant Intervenors moved to dismiss both claims in the PCFFA FAC. PCFFA ECF No. 45-46. A March 8, 2013 Order granted the motions in part. PCFFA ECF No. 52; Pac. Coast. Fed'n of Fishermen's Ass'ns v. U.S. Dep't of the Interior ,
While the PCFFA appeal was pending, Reclamation issued its EA and FONSI for the 2016-18 Interim Contracts. Plaintiffs sued, raising claims substantially similar to those in PCFFA : (1) that the EA/FONSI was inadequate under NEPA; and (2) that Reclamation should have prepared an EIS for the 2016-18 Interim Contracts. ECF No. 2.
On July 25, 2016, the Ninth Circuit reversed in part this Court's summary judgment ruling in PCFFA , remanding for further proceedings in connection with the EA/FONSI claim. Specifically, the Ninth Circuit found that, despite the fact that the Central Valley Project Improvement Act ("CVPIA"), Pub. L. No. 102-575,
In light of the PCFFA Appellate Ruling , Federal Defendants moved for voluntary remand without vacatur of the EA/FONSI prepared in connection with the 2016-18 Interim Contracts. ECF No. 42 at 4-5. Plaintiffs did not oppose remand but requested that the Court vacate, set aside, or otherwise rescind the 2016-18 Interim Contracts. ECF No. 44. The Court granted Federal Defendants' motion and denied Plaintiffs' request for vacatur. ECF No. 52. The Case was stayed until further notice, *1203the Court retained jurisdiction, and Federal Defendants were required to submit periodic status reports on the progress of remand.
On May 31, 2017, Reclamation issued a revised final EA and FONSI for the 2016-18 Interim Contracts. See ECF No. 56. Plaintiffs amended their complaint to address these new documents. See FASC. Defendant Intervenors' motion to dismiss the second claim for relief followed. ECF No. 69.
III. STANDARD OF DECISION
A motion to dismiss pursuant to Federal Rule of Civil Procedure 12(b)(6) is a challenge to the sufficiency of the allegations set forth in the complaint. Navarro v. Block ,
Under Rule 8, a complaint must contain "a short and plain statement of the claim showing that the pleader is entitled to relief," Fed. R. Civ. P. 8(a)(2), in order to "give the defendant fair notice of what the ... claim is and the grounds upon which it rests." Bell Atl. Corp. v. Twombly ,
While Rule 8 does not require detailed factual allegations, "it demands more than an unadorned, the defendant-unlawfully-harmed-me accusation." Iqbal ,
IV. ANALYSIS
Defendant Intervenors argue that Plaintiffs' second claim for relief, which alleges that Federal Defendants violated NEPA by failing to prepare an EIS prior to approving the 2016-18 Interim Contracts, should be dismissed because the challenged contracts do not alter the status quo. ECF No. 69-1. NEPA requires all federal agencies to prepare an EIS for "major Federal actions significantly affecting the quality of the human environment."
A federal action that may have significant environmental impacts need not "also be 'major' in an economic or some other nonenvironmental sense to trigger the EIS requirement." City of Davis v. Coleman ,521 F.2d 661 , 673 n.15 (9th Cir. 1975) ; see40 C.F.R. § 1508.18 ("Major reinforces but does not have a meaning independent of significantly."). But when an agency, responding to changing conditions, makes a decision to operate a completed facility "within the range originally available" to it, the action is not major. Upper Snake River ,921 F.2d at 235 (quoting Cty. of Trinity v. Andrus ,438 F.Supp. 1368 , 1388 (E.D. Cal. 1977) ). In other words, "where a proposed federal action would not change the status quo, an EIS is not necessary."Id. ; accord San Luis & Delta-Mendota Water Auth. v. Jewell ,747 F.3d 581 , 646 (9th Cir. 2014).
The "status quo" jurisprudence was born out of the fact that ongoing projects "such as the CVP and SWP, constructed prior to the date on which NEPA became effective, January 1, 1970, are not retroactively subject to NEPA." See San Luis & Delta-Mendota Water Auth. v. Salazar ,
Upper Snake River concerned Palisades Dam and Reservoir, constructed in 1956 and continuously managed and controlled by the Bureau since that time.
The Federal defendants in this case had been operating the dam for upwards of ten years before the effective date of the Act. During that period, they have from time to time and depending on the river's flow level, adjusted up or down the volume of water released from the Dam. What they did in prior years and what they were doing during the period under consideration were no more than the routine managerial actions regularly carried on from the outset without change. They are simply operating the facility in the manner intended. In short, they are doing nothing new, nor more extensive, nor other than that contemplated when the project was first operational. Its operation is and has been carried on and the consequences have been no different than those in years past.
Upper Snake River specifically cited County of Trinity v. Andrus ,
The Bureau has neither enlarged its capacity to divert water from the Trinity River nor revised its procedures or standards for releases into the Trinity River and the drawdown of reservoirs. It is simply operating the Division within the range originally available pursuant to the authorizing statute, in response to changing environmental conditions.
This line of authority was developed further in Idaho Conservation League , where the Ninth Circuit examined plans to modify operation of the Albeni Falls Dam on the Columbia River during the winter months.
Westlands Water District v. U.S. Department of Interior ,
To some extent, the finding is based on whether the proposed agency action and its environmental effects were within the contemplation of the original project when adopted or approved. [Citations]. The inquiry requires a determination of whether plaintiffs have complained of actions which may cause significant degradation of the human environment. [Citations].
Westlands ,
Likewise, implementation of components of the massive biological opinions that govern the operation of the CVP and SWP have been found to be "major federal actions" because they significantly impacted operations at CVP and SWP pumping plants and other facilities and substantially affected flows in the Delta. See San Luis & Delta-Mendota Water Auth. v. Salazar ,
Plaintiffs maintain that under the analytical framework set forth in Idaho Conservation League , an EIS should be required here because "the cumulative consequences of the interim contracts" are far worse than in past years. See ECF No. 71 at 5. They assert in their brief that "the cumulative amount of water diverted from the Delta has increased" and that this "indisputable cumulative increase has taken its toll on the Delta's fish and wildlife."
In those cases discussed above in which changes were deemed sufficient to rise above "routine managerial actions," to amount to "significant or long-term change in operating policy" the allegations were indicative of real, substantive changes to operational parameters. In Westlands , for example, CVP operations were alleged to have re-directed 1.2 million acre feet of water away from agricultural use.
*1208Plaintiffs attempt to sidestep entirely the "status quo" aspect of the analysis by focusing on the significance of the potential environmental impact. They cite
A federal action that may have significant environmental impacts need not "also be 'major' in an economic or some other nonenvironmental sense to trigger the EIS requirement." City of Davis v. Coleman ,521 F.2d 661 , 673 n.15 (9th Cir. 1975) ; see40 C.F.R. § 1508.18 ("Major reinforces but does not have a meaning independent of significantly."). But when an agency, responding to changing conditions, makes a decision to operate a completed facility "within the range originally available" to it, the action is not major. Upper Snake River ,921 F.2d at 235 (quoting Cty. of Trinity v. Andrus ,438 F.Supp. 1368 , 1388 (E.D. Cal. 1977) ). In other words, "where a proposed federal action would not change the status quo, an EIS is not necessary."Id. ; accord San Luis & Delta-Mendota Water Auth. v. Jewell ,747 F.3d 581 , 646 (9th Cir. 2014).
Plaintiffs are also incorrect that the PCFFA Appellate Decision undermines Defendant Intervenors' argument that the 2016 Interim Contracts do not alter the status quo for purposes of NEPA's EIS requirement. The PCFFA Appellate Decision did not address NEPA's EIS requirement or the cases discussed herein.
More persuasively, Plaintiffs cite Pit River Tribe v. U.S. Forest Service ,
The BLM argued that the 1998 lease extensions did not require separate environmental review because the extensions "preserved the status quo."
Without the affirmative re-extension of the 1988 leases, Calpine would have retained no rights at all to the leased property and would not have been able *1210to go forward with the [planned geothermal plant]. The status quo before the 1998 extensions was that Calpine owned rights to produce geothermal steam valid through May 31, 1998, after which Calpine owned nothing. Instead of preserving the status quo, the lease extensions gave Calpine an extra five years to develop the land and the possibility of obtaining a future lease extension of up to forty years.
Like the original 1988 leases, the 1998 extensions of Calpine's leases did not reserve to the agencies the absolute right to deny development and did not merely preserve the status quo. Under NEPA and our case law, the agencies were required to complete an environmental impact statement before extending the leases. This obligation was not satisfied by the earlier environmental reviews.
Id. at 784.
Plaintiffs argue that Pit River controls here because the 2016-18 Interim Contracts, like the geothermal leases in Pit River , are a "new grant of rights to the intervenors that would otherwise have expired, and constitute an irretrievable commitment of resources mandating an EIS." ECF No. 71 at 6. At first glance, the parallels are compelling. Pit River concerned a lease arrangement. The Interim Contracts are, unsurprisingly, contracts, arguably distinguishing their execution from the managerial decision-making at issue in Idaho Conservation League (dam management), Upper Snake River (same), and Westlands (delivery of water from the CVP to contractors). It is also true that the Ninth Circuit concluded that renewal of the Interim Contracts is not mandatory:
[W]e do not agree with the district court that the Central Valley Project Improvement Act ("CVPIA"), a part of the Reclamation Projects Authorization and Adjustment Act of 1992, required Reclamation to enter into the interim contracts. The CVPIA requires "appropriate environmental review," including the preparation of a programmatic EIS ("PEIS"), before Reclamation is authorized to renew an existing long-term water service contract. CVPIA § 3404(c)(1). After the completion of the PEIS, Reclamation "shall, upon request, renew any existing long-term repayment or water service contract for the delivery of water from the Central Valley Project for a period of twenty-five years." Id. Prior to the completion of the PEIS, Reclamation "may" renew water service contracts for interim three-or two-year periods. Id. As the district court acknowledged, normally, when "may" and "shall" are used in the same statute, the " 'inference is that each is being used in its ordinary sense-the one being permissive, the other mandatory.' " Ctr. for Biological Diversity v. U.S. Fish & Wildlife Serv. ,450 F.3d 930 , 935 (9th Cir. 2006) (quoting Haynes v. United States ,891 F.2d 235 , 239-40 (9th Cir. 1989) ) (interpreting Endangered Species Act). We also reject Reclamation's argument that the contracts themselves mandated renewal. NEPA imposes obligations on agencies considering major federal actions that may affect the environment. An agency may not evade these obligations by contracting around them.
PCFFA ,
However, Plaintiffs are incorrect that the Interim Contracts constitute "an irreversible and irretrievable commitment of resources," akin to the geothermal leases in Pit River . Pit River focused on a line of *1211cases requiring the preparation of an EIS "before any irreversible and irretrievable commitment of resources."
On this issue the 2016-18 Interim Contracts are facially distinguishable from the geothermal leases in Pit River for reasons this Court has discussed at length in related cases. Specifically, the Interim Contracts at issue here contain a shortage provision that allows Reclamation to completely withhold water deliveries. See Nat. Res. Def. Council v. Norton ,
The second claim for relief in the FASC must be dismissed because the 2016-18 Interim Contracts do not alter the status quo as that concept is outlined in Upper Snake River and IdahoConservation League . NEPA does not require an EIS under such circumstances.
V. CONCLUSION AND ORDER
For the reasons set forth above, Defendant Intervenors' motion to dismiss the *1212second claim for relief is GRANTED. The case shall remain OPEN.
IT IS SO ORDERED.
Footnotes
313 F. Supp. 3d 1199 (N. Coast Rivers Alliance v. U.S. Dep't of the Interior) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.