Myung Sung Presbyterian Church, Inc. v. North American Ass'n of Slavic Churches & Ministries, Inc.

662 S.E.2d 745, 291 Ga. App. 808, 2008 Fulton County D. Rep. 1761, 2008 Ga. App. LEXIS 587
CourtCourt of Appeals of Georgia
DecidedMay 22, 2008
DocketA08A0675
StatusPublished
Cited by33 cases

This text of 662 S.E.2d 745 (Myung Sung Presbyterian Church, Inc. v. North American Ass'n of Slavic Churches & Ministries, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Myung Sung Presbyterian Church, Inc. v. North American Ass'n of Slavic Churches & Ministries, Inc., 662 S.E.2d 745, 291 Ga. App. 808, 2008 Fulton County D. Rep. 1761, 2008 Ga. App. LEXIS 587 (Ga. Ct. App. 2008).

Opinion

Andrews, Judge.

After Myung Sung Presbyterian Church, Inc. (MSPC) leased a portion of its real property to North American Association of Slavic Churches & Ministries, Inc. (NAASCM), litigation ensued over the terms of the lease. MSPC appeals from the judgment entered on a jury verdict in favor of NAASCM, and for the following reasons, we reverse.

On March 9, 2000, MSPC leased a portion of its three-acre lot in the City of Norcross to NAASCM for the purpose of allowing NAASCM to place a temporary modular building on the lot. The lease term was for ten years with an option granted to NAASCM for an additional five years. As agreed rent under the lease, NAASCM granted MSPC certain rights to use of the modular building purchased by NAASCM and placed on the MSPC property pursuant to the lease. It is undisputed that when executing the lease both parties were aware that the modular building placed on the lot pursuant to the lease was in compliance with the City of Norcross zoning code only because the City’s Zoning Board of Appeals had granted a zoning variance to MSPC on October 1, 1998, which authorized the placement of a modular building on the lot for a period of five years. It is also undisputed that, under the terms of the lease, NAASCM was granted a usufruct, not an estate for years, and therefore only MSPC, as the sole owner of the real property, had the right to apply for another zoning variance. See OCGA § 44-7-1. Accordingly, when the lease for the ten-year term (with five-year option) was executed on March 9, 2000, both parties were aware that only three and a half years remained before the zoning variance authorizing the modular building was scheduled to expire, and that only MSPC could apply [809]*809for another variance to allow the modular building to remain on the lot during the agreed lease term. Nevertheless, the lease was silent as to whether the parties intended as part of the lease agreement that MSPC was required to apply for another zoning variance. The lease did provide that: “In the event that the City of Norcross requires at any time in the future the removal of the modular unit building, it shall be the responsibility of [NAASCM] to have the building removed and [NAASCM] shall pay all costs of removing said building.” After the five-year zoning variance expired without any attempt by MSPC to apply to the City of Norcross for another variance, the City informed MSPC in January 2004, that the modular building on its property was in violation of the City zoning code and demanded that the building be immediately removed from the property. Citations were issued to MSPC for violation of the City zoning code, and the Municipal Court of Norcross subsequently ordered that the modular building be removed because it violated the zoning code.

In February 2004, MSPC sued NAASCM for breach of the lease agreement, and NAASCM answered and counterclaimed asserting that MSPC breached the lease. The case was tried before a jury on claims asserted by the parties in a February 2007 pre-trial order. In the order, MSPC contended that, under the express terms of the lease, the lease terminated when the variance expired and the City demanded that the modular building be removed. According to MSPC, NAASCM breached the lease by failing to remove the building from the MSPC property immediately after receiving notice that the zoning variance had expired and the City required removal, instead waiting until May 2006 to remove the building. MSPC also asserted that, during the period the modular building remained on the property under the lease, NAASCM breached the lease by denying MSPC its full right to use of the building. NAASCM asserted that, during the period the building remained on the property pursuant to the lease, MSPC breached an implied covenant of quiet enjoyment contained in the lease by denying it the full use and enjoyment of the modular building to which it was entitled. NAASCM also asserted that MSPC breached an implied covenant of good faith and fair dealing contained in the lease by failing or refusing to timely apply to the City of Norcross for another zoning variance sufficient to allow the modular building to remain on the lot during the agreed lease term. In conjunction with the latter assertion, NAASCM claimed that the lease contained an implied provision requiring MSPC to apply for another zoning variance.

The case was submitted to the jury on a verdict form which required the jury to find for or against MSPC on its claim for breach of contract and for or against NAASCM on its claim for breach of [810]*810contract, without separately considering the various grounds for breach of contract asserted by MSPC and NAASCM. The jury returned a verdict: (1) finding in favor of MSPC on its breach of contract claim and awarding MSPC breach of contract damages in the amount of $1.00, plus $83,483.92 in attorney fees and expenses of litigation, and (2) finding in favor of NAASCM on its breach of contract claim and awarding NAASCM breach of contract damages in the amount of $196,115.12, plus $88,000 in attorney fees and expenses of litigation. With the agreement of NAASCM, the trial court refused to accept this verdict and instructed the jurors that they could not find for both MSPC and NAASCM, but were required to find for one or the other, or for neither. MSPC objected to this instruction.1 After receiving this instruction, the jury returned a verdict: (1) finding in favor of NAASCM on MSPC’s breach of contract claim, and (2) finding in favor of NAASCM on its breach of contract claim and awarding NAASCM breach of contract damages in the amount of $160,000. The trial court entered its judgment on this verdict.

1. We agree with MSPC that the trial court erred by instructing the jurors that they could not find for both MSPC and NAASCM on their respective breach of contract claims. There was nothing inconsistent with the jury’s first verdict finding that both NAASCM and MSPC breached different obligations under the lease. Accordingly, the judgment entered on the verdict rendered pursuant to this instruction must be reversed.

2. MSPC claims that the trial court erred by denying its motion for directed verdict on NAASCM’s claim that MSPC breached an implied covenant of good faith and fair dealing contained in the lease.

Every contract implies a covenant of good faith and fair dealing in the contract’s performance and enforcement. WirelessMD v. Healthcare.com Corp., 271 Ga. App. 461, 468 (610 SE2d 352) (2005); Hunting Aircraft v. Peachtree City Airport Auth., 281 Ga. App. 450, 451 (636 SE2d 139) (2006). The implied covenant modifies and becomes a part of the provisions of the contract, but the covenant cannot be breached apart from the contract provisions it modifies and therefore cannot provide an independent basis for liability. Stuart Enterprises Intl. v. Peykan, Inc., 252 Ga. App. 231, 233-234 (555 SE2d 881) (2001); WirelessMD, 271 Ga. App. at 468. NAASCM contended that MSPC breached an implied covenant of good faith and fair dealing in the lease agreement because MSPC failed to [811]*811timely apply to the City of Norcross for another zoning variance sufficient to allow the modular building to remain on the lot for the agreed lease term. Because the lease contained no express provision requiring MSPC to apply for another zoning variance, NAASCM contended that the good faith and fair dealing covenant modified an implied lease provision requiring MSPC to apply for another zoning variance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carol Tims v. LGE Community Credit Union
935 F.3d 1228 (Eleventh Circuit, 2019)
Lawmen Supply Co. of N.J., Inc. v. Glock, Inc.
330 F. Supp. 3d 1020 (D. New Jersey, 2018)
Stuttering Foundation, Inc. v. Glynn County
801 S.E.2d 793 (Supreme Court of Georgia, 2017)
George v. Hercules Real Estate Services, Inc.
795 S.E.2d 81 (Court of Appeals of Georgia, 2016)
Ahmed v. Air France-KLM
165 F. Supp. 3d 1302 (N.D. Georgia, 2016)
New York Life Insurance v. Grant
57 F. Supp. 3d 1401 (M.D. Georgia, 2014)
Ralls Corp. v. Huerfano River Wind, LLC
27 F. Supp. 3d 1303 (N.D. Georgia, 2014)
Walker v. JPMorgan Chase Bank, N.A.
987 F. Supp. 2d 1348 (N.D. Georgia, 2013)
Kin Chun Chung v. JP Morgan Chase Bank, N.A.
975 F. Supp. 2d 1333 (N.D. Georgia, 2013)
McGee v. Patterson
746 S.E.2d 719 (Court of Appeals of Georgia, 2013)
Arvil J. Ceasar v. Wells Fargo Bank, N. A.
Court of Appeals of Georgia, 2013
Ceasar v. Wells Fargo Bank, N.A.
744 S.E.2d 369 (Court of Appeals of Georgia, 2013)
McCabe v. Daimler AG
948 F. Supp. 2d 1347 (N.D. Georgia, 2013)
Ameris Bank v. Alliance Investment & Management Co.
739 S.E.2d 481 (Court of Appeals of Georgia, 2013)
Mike Layer v. Clipper Petroleum, Inc.
Court of Appeals of Georgia, 2012
Layer v. Clipper Petroleum, Inc.
735 S.E.2d 65 (Court of Appeals of Georgia, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
662 S.E.2d 745, 291 Ga. App. 808, 2008 Fulton County D. Rep. 1761, 2008 Ga. App. LEXIS 587, Counsel Stack Legal Research, https://law.counselstack.com/opinion/myung-sung-presbyterian-church-inc-v-north-american-assn-of-slavic-gactapp-2008.