Myers v. Charles Simms Dev. Corp., Unpublished Decision (12-27-2002)

CourtOhio Court of Appeals
DecidedDecember 27, 2002
DocketC.A. Case No. 19281.
StatusUnpublished

This text of Myers v. Charles Simms Dev. Corp., Unpublished Decision (12-27-2002) (Myers v. Charles Simms Dev. Corp., Unpublished Decision (12-27-2002)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Myers v. Charles Simms Dev. Corp., Unpublished Decision (12-27-2002), (Ohio Ct. App. 2002).

Opinion

OPINION
{¶ 1} Plaintiff, Terry Myers, appeals from summary judgments granted on the motions of Defendants, Twin Valley Plumbing, Inc. and Charles Simms Development Corporation (Simms), on claims arising from injuries Myers suffered while working for Twin Valley during construction of Simms' condominiums.

{¶ 2} Terry Myers was employed by Twin Valley as a plumbing apprentice. Simms, a general contractor, had engaged Twin Valley as a subcontractor to install plumbing at the Bay Shores Condominium development in Centerville, which was under construction by Simms.

{¶ 3} On November 2, 1998, while on his lunch break at the Bay Shores condominium construction site, Myers arose from the stack of drywall where he had been sitting while eating his lunch with his co-workers in order to look out a window at an approaching truck. In an attempt to get a better view of the truck, Myers took several steps backward. As he did, he was in the process of either lighting or smoking a cigarette. With his last step backwards, Myers fell through an opening between the exposed studs of an uncompleted wall and landed at the bottom of an open stairwell, eight to ten feet below. Myers suffered injuries from the fall that caused him to miss work for several months.

{¶ 4} Myers commenced an action against both Twin Valley and Simms, presenting seven claims of relief against each Defendant. The claims were: general negligence; breach of duty as prescribed by O.A.C. 4121:1-3-4; breach of duty constituting gross, reckless, intentional and/or malicious conduct; intentional infliction of serious emotional distress; intentional infliction of emotional distress; negligent infliction of emotional distress; frequenter statute negligence; and derivative loss of consortium.

{¶ 5} Simms and Twin Valley each moved for summary judgment on all of the claims for relief. Simms argued that it owed no duty to Myers. Twin Valley argued that (1) it is immune from liability to Myers on his claims under the Ohio Workers' Compensation Act, (2) that it did not owe a duty of care to Myers, and (3) that Myers failed to state a claim for an intentional tort.

{¶ 6} The trial court granted summary judgements in favor of both Simms and Twin Valley on every claim alleged by Myers. Myers appeals, offering two assignments of error.

FIRST ASSIGNMENT OF ERROR
{¶ 7} "Where a general contractor actively participates in the job operation by retaining control of the safety of the workplace premises by installing and maintaining temporary safety railings where a hazard exists, the general contractor has a common law and statutory duty to protect a subcontractor's employees and may be liable for injuries sustained by the subcontractor's employee."

{¶ 8} This assignment of error pertains to the summary judgment in favor of Simms, the general contractor.

{¶ 9} Summary judgment may not be granted unless the entire record demonstrates that there is no genuine issue of material fact and that the moving party is, on that record, entitled to judgment as a matter of law. Civ.R. 56. The burden of showing that no genuine issue of material fact exists is on the moving party. Harless v. Willis Day WarehousingCo. (1978), 54 Ohio St.2d 64.

{¶ 10} All evidence submitted in connection with a motion for summary judgment must be construed most strongly in favor of the party against whom the motion is made. Morris v. First National Bank Trust Co. (1970), 21 Ohio St.2d 25. "Because a trial court's determination of summary judgment concerns a question of law, we apply the same standard as the trial court in our review of its disposition of the motion; in other words, our review is de novo." Am. States Ins. Co.v. Guillermin (1996), 108 Ohio App.3d 547, 552.

{¶ 11} Ordinarily, a general contractor who engages the services of an independent contractor owes no duty of care to the employees of the independent contractor. Sopkovich v. Ohio Edison Co. (1998),81 Ohio St.3d 628, 1998-Ohio-341. However, when a general contractor engages the services of an independent sub-contractor and "actually participates in the job operation performed by such contractor and thereby fails to eliminate a hazard which he, in the exercise of ordinary care, could have eliminated, [the general contractor] can be held responsible for the injury or death of an employee of the independent contractor."Hirschbach v. Cincinnati Gas Elec. Co. (1983), 6 Ohio St.3d 206, syllabus.

{¶ 12} "`[A]ctive participation' includes situations in which a property owner exercises control over the work activities of the independent contractor, and also includes situations in which a property owner exercises control over a critical aspect of the employee's place of employment or `working environment.'" Sopkovich, supra at 635.

{¶ 13} Myers argues that Simms owed him a duty of care because it actively participated in the job operation by retaining control of the safety of the workplace premises. He argues that when Simms installed and maintained temporary safety railings where hazards existed, it then had a statutory and common law duty to protect a subcontractor's employees, making it potentially liable for injuries sustained by a subcontractor's employees.

{¶ 14} Myers relies on Cefaratti v. Mason Structural Steel Co.,Inc. (1999), 136 Ohio App.3d 363, 1998-Ohio-279. In Cefaratti, an employee of a subcontractor commenced a negligence action against the general contractor of a construction site for injuries he'd suffered when he fell in an open stairwell. The general contractor had originally installed a guard rail at the work site. It then removed the guard rail and failed to notify the workers of the change and failed to warn them to avoid the location.

{¶ 15} The trial court granted summary judgment in favor of the general contractor. The Eighth District Court of Appeals reversed the trial court's decision. It found that although the general contractor did not actively participate in the employee's specific job activities, there was yet a genuine issue of material fact as to whether the general contractor was responsible for the absence of the guard rail and whether the absence of the guard rail constituted a critical variable in the workplace.

{¶ 16} The Cefaratti decision was based almost exclusively onSopovich v. Ohio Edison Co., supra. Sopkovich was an employee of an independent contractor hired to paint electric substation owned and operated by electric company. He commenced an action against the electric company for injuries he sustained when he came into contact with high voltage electricity. The substation was a "transmission" substation through which high voltage electricity flowed. It was not feasible to shut off the entire flow of electricity through the substation during the painting work. However, the electric company was able to stop the flow of electricity through certain conductors in some areas of the substation so they could be painted.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American States Insurance v. Guillermin
671 N.E.2d 317 (Ohio Court of Appeals, 1996)
Cefaratti v. Mason Structural Steel Co.
736 N.E.2d 913 (Ohio Court of Appeals, 1999)
Morris v. First National Bank & Trust Co.
254 N.E.2d 683 (Ohio Supreme Court, 1970)
Harless v. Willis Day Warehousing Co.
375 N.E.2d 46 (Ohio Supreme Court, 1978)
Hirschbach v. Cincinnati Gas & Electric Co.
452 N.E.2d 326 (Ohio Supreme Court, 1983)
Fyffe v. Jeno's, Inc.
570 N.E.2d 1108 (Ohio Supreme Court, 1991)
Bond v. Howard Corp.
650 N.E.2d 416 (Ohio Supreme Court, 1995)
Dresher v. Burt
662 N.E.2d 264 (Ohio Supreme Court, 1996)
Sopkovich v. Ohio Edison Co.
693 N.E.2d 233 (Ohio Supreme Court, 1998)
Cefaratti v. Mason Structural Steel Co., Inc.
1998 Ohio 279 (Ohio Supreme Court, 1998)
Sopkovich v. Ohio Edison Co.
1998 Ohio 341 (Ohio Supreme Court, 1998)
Dresher v. Burt
1996 Ohio 107 (Ohio Supreme Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
Myers v. Charles Simms Dev. Corp., Unpublished Decision (12-27-2002), Counsel Stack Legal Research, https://law.counselstack.com/opinion/myers-v-charles-simms-dev-corp-unpublished-decision-12-27-2002-ohioctapp-2002.