M+W Zander, U.S. Operations, Inc. v. Scott Co.

78 P.3d 118, 190 Or. App. 268, 2003 Ore. App. LEXIS 1417
CourtCourt of Appeals of Oregon
DecidedOctober 22, 2003
Docket16-01-16540; A118145
StatusPublished
Cited by8 cases

This text of 78 P.3d 118 (M+W Zander, U.S. Operations, Inc. v. Scott Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
M+W Zander, U.S. Operations, Inc. v. Scott Co., 78 P.3d 118, 190 Or. App. 268, 2003 Ore. App. LEXIS 1417 (Or. Ct. App. 2003).

Opinion

*270 SCHUMAN, J.

Defendant Scott Company (Scott) ordered equipment from plaintiff M+W Zander, U.S. Operations, Inc. (M+W) for use by Scott in a construction project in Eugene. The parties effected the transaction by a purchase order and a later-issued supplemental purchase order both issued by Scott and accepted by M+W. M+W brought this action alleging that Scott breached the contract formed by the purchase orders. Scott moved for summary judgment under the theoiy that M+Ws action was time barred. The trial court granted Scott’s motion, and M+W appeals. Concluding that there is no genuine issue of material fact and that Scott, the moving party, was entitled to judgment as a matter of law, ORCP 47 C, we affirm.

The following facts are not in dispute. The original purchase order from Scott contained, among other things, specifications of the goods M+W was to supply (26 tower fan air handling systems), a date by which their delivery was to be complete (November 7, 1996), and a price ($1,073,502). Delivery was not timely, and, when it did occur, Scott was not satisfied with the condition of the goods. Negotiations ensued. The parties agreed that Scott could deduct $162,378 from the original purchase price to compensate for the additional costs that Scott had incurred due to the fans’ defects. On April 24, 1997, Scott issued a supplemental purchase order reflecting the reduced price. On June 26, M+W applied the requested discount to Scott’s account and billed Scott for the reduced amount ($911,124). Scott made partial payments on August 8 and September 29, 1997, but left a balance of $300,000 owing to M+W. On August 24, 2001, M+Ws demands for payment of the balance remained unmet, and M+W filed this action for breach of contract, quantum meruit for goods sold and delivered, and account stated. The trial court granted Scott’s motion for summary judgment, concluding that M+W had not filed its action within the statute of limitations.

The parties agree that, under the applicable law, the limitations period for an alleged breach of contract for the sale of goods is four years from the date on which the contract *271 is breached. According to M+W, the supplemental purchase order was an offer by Scott to pay the reduced price for the equipment within 45 days of M+Ws acceptance, and that acceptance occurred only when M+W signed the supplemental purchase order and returned it to Scott on August 7,1997. Thus, Scott’s payment became due 45 days later, that is, on September 21, 1997. That being the case, M+W concludes, the limitation period elapsed on September 21, 2001, so M+W’s August 24,2001, filing was timely. In the alternative, M+W argues that, under Oregon law, Scott’s partial payments on August 15 and September 29, 1997, began a new four-year limitation period, which expired on September 29, 2001, again compelling the conclusion that the August 24, 2001, filing was timely.

Scott, for its part, contends that the supplemental purchase order specified that Scott’s payment was due 45 days from the date Scott issued the purchase order, not 45 days from M+Ws written acceptance of it. The date of issue was April 24,1997; 45 days elapsed on June 9,1997. Further, Scott maintains, California’s law, not Oregon’s, applies, and under California law partial payment does not toll the running of the limitation period; thus, according to Scott, it was in breach, the action against it accrued, and the limitation period began on June 9, 1997, and elapsed on June 9, 2001. Therefore M+Ws August 24, 2001, filing was not timely.

We conclude that California law applies. Under that law, M+W accepted the offer made by Scott in the supplemental purchase order when it applied the discount that order contained to Scott’s account on June 26, 1997. Under the terms of the purchase order, Scott’s payment was therefore due 45 days later, on August 10, 1997. When Scott had not made payment on that date, it breached, and the cause of action against it accrued. Because California law applies, nothing tolled the limitation period; therefore it lapsed at the close of business on August 10,2001. The trial court therefore did not err in concluding that M+Ws action was untimely.

I. CHOICE OF LAW

Although the parties disagree about which state’s law applies, they agree that their contract’s choice of law provision is the basis on which that dispute must be determined. *272 When parties specify their choice of law in a contract, that choice will be effectuated subject to the limitations in section 187(2) of the Restatement (Second) of Conflict of Laws (1971 ). 1 Machado-Miller v. Mersereau & Shannon, LLP, 180 Or App 586, 592, 43 P3d 1207 (2002). That Restatement section provides:

“The law of the state chosen by the parties to govern their contractual rights and duties will be applied * * * unless * * *
“(a) the chosen state has no substantial relationship to the parties or the transaction and there is no other reasonable basis for the parties’ choice, or
“(b) application of the law of the chosen state would be contrary to a fundamental policy of a state which has a materially greater interest than the chosen state in the determination of the particular issue and which * * * would be the state of the applicable law in the absence of an effective choice of law by the parties.”

Here, the construction project took place in Eugene, Oregon, and both companies are licensed to do business in Oregon. Scott is a California corporation headquartered in California. The disputed issues involve general rules of contract law that do not implicate either state’s “fundamental policy,” nor does either state have a “materially greater interest” than the other in the disputed issues. We therefore agree with the parties that their contractual choice of law should be given effect.

In interpreting the contract, we begin with the text and context; proceed to extrinsic evidence of the parties’ intent if the text and context do not resolve all ambiguities; and, if ambiguity remains after the second step, resort to maxims of construction. Yogman v. Parrott, 325 Or 358, 361-64, 937 P2d 1019 (1997).

*273 The supplemental purchase order that the parties agree forms the contract in this case contains typewritten terms on the front and a page of preprinted terms on the back. The original purchase order likewise has a typewritten front and the same preprinted terms on the back. One of the preprinted terms, paragraph 13, states, in part, “The definition of terms used, interpretation of this agreement and the right of all parties hereunder shall be construed under and governed by the laws of the State of California.” That term, standing alone, is unambiguous. However, paragraph 11 of the same page of terms and conditions provides:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johnson v. J. G. Wentworth Originations, LLC
391 P.3d 865 (Court of Appeals of Oregon, 2017)
AS 2014-11 5W LLC v. Caplan Landlord, LLC
359 P.3d 1225 (Court of Appeals of Oregon, 2015)
LNG DEVELOPMENT CO., LLC v. Port of Astoria
681 F. Supp. 2d 1279 (D. Oregon, 2010)
MID-CENTURY INS. COMPANY v. Perkins
149 P.3d 265 (Court of Appeals of Oregon, 2006)
Magill v. Schwartz
105 P.3d 867 (Court of Appeals of Oregon, 2005)
Burchett v. MasTec North America, Inc.
2004 MT 177 (Montana Supreme Court, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
78 P.3d 118, 190 Or. App. 268, 2003 Ore. App. LEXIS 1417, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mw-zander-us-operations-inc-v-scott-co-orctapp-2003.