M.V.N. Homes, Inc. v. Mohamed Aly

CourtNew Jersey Superior Court Appellate Division
DecidedJune 8, 2026
DocketA-0372-24
StatusUnpublished

This text of M.V.N. Homes, Inc. v. Mohamed Aly (M.V.N. Homes, Inc. v. Mohamed Aly) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
M.V.N. Homes, Inc. v. Mohamed Aly, (N.J. Ct. App. 2026).

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court ." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited . R. 1:36-3.

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION DOCKET NO. A-0372-24

M.V.N. HOMES, INC., a Corporation of the State of Jersey,

Plaintiff-Appellant,

v.

MOHAMED ALY and REHAM ABDELFATTAH,

Defendants- Respondents.

Submitted April 20, 2026 – Decided June 8, 2026

Before Judges Sabatino and Natali.

On appeal from the Superior Court of New Jersey, Law Division, Monmouth County, Docket No. L-2809-17.

Batcha & Batcha, PC, attorneys for appellant (F. Bradford Batcha, on the briefs).

Robbins & Robbins, LLP, attorneys for respondents (Spencer B. Robbins, on the brief).

PER CURIAM This appeal in a long-ongoing construction dispute arises from the trial

court's findings after a seven-day, non-jury trial that plaintiff/counterclaimant-

appellant MVN Homes, Inc. ("the builder") violated the Consumer Fraud Act

("CFA"), N.J.S.A. 56:8-1 to -227, and awarded defendants/counterclaimants-

respondents Mohamed Aly and Reham Abdelfattah ("the homeowners") $9,792

in treble damages and an additional $9,525.52 in related attorney's fees and costs

under the CFA, for a total of $19,317.25. The trial court rejected the builder's

breach of contract claims against the homeowners, and, for different reasons,

the homeowners' opposing breach of contract claims against the builder.

The underlying facts and procedural history are well-known to the parties

and need not be stated here comprehensively. The homeowners are a married

couple who, in the fall of 2014, purchased three acres of land in Millstone, with

the intention of building a new single-family home and relocating there. The

builder is a corporation led by its president, Murtaza Khan, which is licensed by

the Department of Community Affairs ("DCA") to construct new homes within

the State.

Over eleven years ago in November 2014, the homeowners entered into a

three-page contract with the builder to construct a new home on their lot. The

builder drafted the contract. Among other things, the contract specified that:

A-0372-24 2 (1) the homeowners agreed to pay the builder $360,000 for the home's

construction; (2) five percent of that amount was to be paid to the builder as an

initial deposit, with additional progress payments to be made pursuant to the

construction payment schedule developed by the homeowners' chosen bank; and

(3) all work on the house was to be substantially completed by the builder "no

later than 250 days after the work commences," subject to unanticipated delays

in construction caused by events outside of the builder's control, including those

related to adverse weather conditions. The contract contained no "time is of the

essence" clause.

Originally, the builder had told the homeowners that construction was

anticipated to begin in late April 2015, with an expected completion date

sometime in January 2016. However, because the homeowners were unable to

secure financing until late July 2015, work on the project did not begin until July

28, 2015.

In or around the latter part of 2015, the builder apparently suspended work

on the construction of the homeowners' new home. Allegedly, the builder

became increasingly unresponsive to the homeowners' inquiries regarding the

status of the work that had yet to be completed, with the builder citing cold

weather as the reason for halting construction. Work resumed in March 2016,

A-0372-24 3 but the relationship between the parties deteriorated thereafter, due in part to the

builder's ongoing alleged lack of communication and continued project delays,

as well as the homeowners' own periodic withholding of payments owed to the

builder.

In the spring of 2016, the homeowners listed their then-residence for sale.

They accepted an offer from a buyer, with a closing date of June 6, 2016. As

the builder had yet to complete construction on their new home, the homeowners

temporarily moved into an Airbnb and kenneled their pet dog, costing them a

total of $3,264 for the period that they were unable to take occupancy.

Months later, at some point in time during the fall of 2016, the

homeowners provided the builder with a punch-list of many items. By the time

that litigation commenced, this number would grow to thirty-four specific

punch-list items.

On December 7, 2016, the homeowners obtained a temporary Certificate

of Occupancy ("C.O."), which allowed them to move into their new home. A

final C.O. was issued the following month on January 9, 2017.

When all was said and done, 498 days had lapsed between the time that

construction first began in June 2015 and December 2016, when the

homeowners took occupancy.

A-0372-24 4 In February 2017, the builder filed a construction lien against the

homeowners' property, claiming a sum of $72,730 the homeowners allegedly

still owed under their contract. One month later, a state-appointed lien arbitrator

approved a lien in the builder's favor for $56,438, which the homeowners

thereafter paid.

The homeowners next filed a warranty claim under the DCA's New Home

Warranty Program ("NHWP") in May 2017, alleging that the thirty-four punch-

list items had yet to be addressed by the builder in a satisfactory manner.

After a hearing, the DCA's Bureau of Homeowner Protection issued a

written decision on September 12, 2017, ruling in favor of the homeowners for

half (seventeen) of the thirty-four warranty claims. As to the seventeen other

claims that were not granted, the DCA determined that nine of those seventeen

claims comprised "incomplete" items and/or "contractual disputes" that were

beyond the purview of the NHWP program. Neither party appealed the DCA's

decision.

In June 2017, the builder filed a breach-of-contract suit against the

homeowners in the Law Division, seeking to recover the remaining balance it

claimed was owed after the lien had been satisfied. The following month, the

homeowners filed counterclaims of their own against the builder, broadly

A-0372-24 5 alleging the builder's work to have been untimely, improperly completed, and

performed in an unworkmanlike manner.

After the lawsuit lingered on the docket for six-and-a-half years with

failed efforts to arbitrate or settle the case, the court heard the builder's motion

to dismiss the homeowners' counterclaims. In an oral decision on February 16,

2024, a pretrial judge permitted the homeowners to pursue litigation only as to

the nine specific punch-list item claims previously identified by the DCA as

being "incomplete and/or contractual disputes." The pretrial judge precluded

the homeowners from litigating damages for all other punch-list item-related

claims.

About a week after the pretrial judge's decision, on February 27, 2024, a

different judge who was assigned to try the case ("the trial judge") denied two

motions in limine filed by the builder. First, the trial judge denied the motion

to limit testimony to only those specific claims that the pretrial judge had

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anthony D'agostino v. Ricardo Maldonado (068940)
78 A.3d 527 (Supreme Court of New Jersey, 2013)
Czar, Inc. v. Heath
966 A.2d 1008 (Supreme Court of New Jersey, 2009)
Bosland v. Warnock Dodge, Inc.
964 A.2d 741 (Supreme Court of New Jersey, 2009)
Matter of Trust Created by Agreement Dated December 20, 1961
944 A.2d 588 (Supreme Court of New Jersey, 2008)
Cox v. Sears Roebuck & Co.
647 A.2d 454 (Supreme Court of New Jersey, 1994)
Manalapan Realty v. Township Committee of the Township of Manalapan
658 A.2d 1230 (Supreme Court of New Jersey, 1995)
State v. Castagna
901 A.2d 363 (Supreme Court of New Jersey, 2006)
Fitzgerald v. Stanley Roberts, Inc.
895 A.2d 405 (Supreme Court of New Jersey, 2006)
Rova Farms Resort, Inc. v. Investors Insurance Co. of America
323 A.2d 495 (Supreme Court of New Jersey, 1974)
New Mea Const. Corp. v. Harper
497 A.2d 534 (New Jersey Superior Court App Division, 1985)
Gennari v. Weichert Co. Realtors
691 A.2d 350 (Supreme Court of New Jersey, 1997)
Gennari v. Weichert Co. Realtors
672 A.2d 1190 (New Jersey Superior Court App Division, 1996)
MONOGRAM CRED. CARD BANK OF GEORGIA v. Tennesen
914 A.2d 847 (New Jersey Superior Court App Division, 2007)
Seidman v. Clifton Savings Bank
14 A.3d 36 (Supreme Court of New Jersey, 2011)
Cumberland Farms, Inc. v. New Jersey
148 A.3d 767 (New Jersey Superior Court App Division, 2016)
Willner v. Vertical Reality, Inc.
192 A.3d 1011 (Supreme Court of New Jersey, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
M.V.N. Homes, Inc. v. Mohamed Aly, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mvn-homes-inc-v-mohamed-aly-njsuperctappdiv-2026.