BRIGHT, Senior Circuit Judge.
In this insurance subrogation case, Mutuelle Electrique D’Assurances (Mutuelle) appeals from the district court’s
entry of final judgment in favor of Hammermills, Inc. (Hammermills), in a second trial of the case, this time before the bench. Mutuelle alleges that the district court erred in granting a new trial on both liability and damages after the jury in the first trial found by written interrogatory that Hammermills had breached an express warranty to Mutuelle’s insured, but assessed damages far below the amount of the uncontested costs incurred by Mutuelle’s insured. Under the circumstances shown by the record, the district court did not abuse its discretion in granting a new trial on both liability and damages. Therefore we affirm.
1. BACKGROUND.
Mutuelle’s claim arises from the mechanical failure of an automobile shredder which Compagnie Francaise de Ferradles (CFF) had purchased from Hammermills and installed at its plant in Saint-Pierre-de-Chandieu, France. On January 19, 1981, the “outer top breaker bar” of the automobile shredder fractured and fell onto the “intake breaker bar.” Both parts then fell into the machine’s shredding chamber, where they encountered the machine’s shredding hammers, and the machine was effectively torn apart. As a result of this breakdown, Mutuelle paid CFF, pursuant to an insurance policy covering machine breakage and business interruption, $284,-633.10 for repair of the machine, $172,-851.77 for lost profits and fixed overhead, and $9,644.77 for investigation costs, yielding a total payment of $467,129.64. By virtue of paying the loss, Mutuelle was subrogated to CFF’s claims against Hammermills.
Mutuelle then sued Hammermills in federal district court for breach of express and implied warranties, negligence, and strict liability.
The case was tried to a jury from May 29 through June 5, 1984. The district court submitted the case to the jury on a verdict form which asked the jury, if it found for Mutuelle, to identify the ground for Mutuelle’s recovery and the defendant or defendants against whom recovery should be made, and then to indicate the amount of damages awarded for repair costs, fixed overhead and lost profits, and investigation costs. After approximately two hours of deliberation on June 5, the jury sent the following question to the district court:
Under “A.” We find them guilty under Express Warranty against one of the Companies. We want to set a $ amount, but we the jury feel it isn’t one of the three present. Ex.
$_Cost of repairs
$_Cost of fixed overhead
$-Investigation costs
Could we make it some other category? (Over).
/s/ Ernest Brockhohn
Jury foreman
After a lengthy conference, the district court, with the consent of each party’s counsel, sent the jury the following reply: Members of the Jury:
In answer to your question, you may cross out the three categories and write in a single dollar amount without specifying the category.
/s/ Edward J. McManus, Judge
An hour and forty-five minutes later, the jury returned a verdict, by written interrogatory, in favor of Mutuelle, and against Hammermills, solely on the breach of express warranty claim.
In accordance with the district court’s instruction, the jury crossed out the three damage categories and wrote in the sum of $35,000.00 without specifying a category. The verdict was accompanied by the following note from the jury:
Sirs,
The jury feels there was a violation of the Contract. On the Plaintiff’s exhibit # 66 and # 67.
CFF
was not informed in writing in the material change in the upper breaker bar.
/s/ Ernest G. Brockhohn
Jury foreman
After the jury returned its verdict and the district court entered judgment, Mutuelle filed a post-trial motion asking the district court to amend the verdict by increasing the jury’s damage award to the amount of the undisputed cost of investigation and repairs ($294,277.87) and to grant a new trial limited solely to the amount of damages for fixed overhead and lost profits, or, in the alternative, to grant a new trial on all issues of damages only. Hammermills filed a cross-motion asking the district court to grant it a judgment of dismissal, notwithstanding the verdict.
In response to these motions, the district court granted a new trial between Mutuelle and Hammermills on both liability and damages on the express warranty claim. The parties then stipulated that the case would be retried by the district court on the record of the first trial, supplemented with additional memoranda and proposed findings. Upon retrial, the district court found that Mutuelle failed to prove by a preponderance of the evidence that Hammermills’ conduct in designing and manufacturing the automobile shredder proximately caused the January 19, 1981, failure. Therefore, the district court ruled that Hammermills was not liable on the breach of express warranty claim and dismissed the action. Mutuelle now appeals. Mutuelle alleges that the district court erred (1) in refusing either to amend the jury’s verdict by increasing the damage award to the amount of the undisputed cost of investigation and repairs, or to order a new trial on the issue of damages alone, and (2) in granting a new trial on both liability and damages on the express warranty claim.
II. DISCUSSION.
Mutuelle contends that the jury, by its answer to the written interrogatory as well as its two notes to the district court, found Hammermills liable for breach of an express warranty. Mutuelle argues, relying on the seventh amendment and cases such as
Wayne v. New York Life Insurance Co.,
132 F.2d 28 (8th Cir.1942), that when a properly instructed jury returns a finding of liability that is supported by the evidence, then errs in its damage award, the district court as a matter of law may not take the jury’s verdict of liability away from the plaintiff. Mutuelle asserts that this is what the district court did in the present case when it granted a new trial on both liability and damages.
The district court, however, concluded that the jury never in fact made a finding of liability. It noted that while the jury’s response to the written interrogatory indicated that they found Hammermills had breached an express warranty to CFF, this finding does not necessarily entail the further conclusion that Hammermills’ breach constituted the proximate cause of the plaintiff’s damage, as is required for there to be liability.
Free access — add to your briefcase to read the full text and ask questions with AI
BRIGHT, Senior Circuit Judge.
In this insurance subrogation case, Mutuelle Electrique D’Assurances (Mutuelle) appeals from the district court’s
entry of final judgment in favor of Hammermills, Inc. (Hammermills), in a second trial of the case, this time before the bench. Mutuelle alleges that the district court erred in granting a new trial on both liability and damages after the jury in the first trial found by written interrogatory that Hammermills had breached an express warranty to Mutuelle’s insured, but assessed damages far below the amount of the uncontested costs incurred by Mutuelle’s insured. Under the circumstances shown by the record, the district court did not abuse its discretion in granting a new trial on both liability and damages. Therefore we affirm.
1. BACKGROUND.
Mutuelle’s claim arises from the mechanical failure of an automobile shredder which Compagnie Francaise de Ferradles (CFF) had purchased from Hammermills and installed at its plant in Saint-Pierre-de-Chandieu, France. On January 19, 1981, the “outer top breaker bar” of the automobile shredder fractured and fell onto the “intake breaker bar.” Both parts then fell into the machine’s shredding chamber, where they encountered the machine’s shredding hammers, and the machine was effectively torn apart. As a result of this breakdown, Mutuelle paid CFF, pursuant to an insurance policy covering machine breakage and business interruption, $284,-633.10 for repair of the machine, $172,-851.77 for lost profits and fixed overhead, and $9,644.77 for investigation costs, yielding a total payment of $467,129.64. By virtue of paying the loss, Mutuelle was subrogated to CFF’s claims against Hammermills.
Mutuelle then sued Hammermills in federal district court for breach of express and implied warranties, negligence, and strict liability.
The case was tried to a jury from May 29 through June 5, 1984. The district court submitted the case to the jury on a verdict form which asked the jury, if it found for Mutuelle, to identify the ground for Mutuelle’s recovery and the defendant or defendants against whom recovery should be made, and then to indicate the amount of damages awarded for repair costs, fixed overhead and lost profits, and investigation costs. After approximately two hours of deliberation on June 5, the jury sent the following question to the district court:
Under “A.” We find them guilty under Express Warranty against one of the Companies. We want to set a $ amount, but we the jury feel it isn’t one of the three present. Ex.
$_Cost of repairs
$_Cost of fixed overhead
$-Investigation costs
Could we make it some other category? (Over).
/s/ Ernest Brockhohn
Jury foreman
After a lengthy conference, the district court, with the consent of each party’s counsel, sent the jury the following reply: Members of the Jury:
In answer to your question, you may cross out the three categories and write in a single dollar amount without specifying the category.
/s/ Edward J. McManus, Judge
An hour and forty-five minutes later, the jury returned a verdict, by written interrogatory, in favor of Mutuelle, and against Hammermills, solely on the breach of express warranty claim.
In accordance with the district court’s instruction, the jury crossed out the three damage categories and wrote in the sum of $35,000.00 without specifying a category. The verdict was accompanied by the following note from the jury:
Sirs,
The jury feels there was a violation of the Contract. On the Plaintiff’s exhibit # 66 and # 67.
CFF
was not informed in writing in the material change in the upper breaker bar.
/s/ Ernest G. Brockhohn
Jury foreman
After the jury returned its verdict and the district court entered judgment, Mutuelle filed a post-trial motion asking the district court to amend the verdict by increasing the jury’s damage award to the amount of the undisputed cost of investigation and repairs ($294,277.87) and to grant a new trial limited solely to the amount of damages for fixed overhead and lost profits, or, in the alternative, to grant a new trial on all issues of damages only. Hammermills filed a cross-motion asking the district court to grant it a judgment of dismissal, notwithstanding the verdict.
In response to these motions, the district court granted a new trial between Mutuelle and Hammermills on both liability and damages on the express warranty claim. The parties then stipulated that the case would be retried by the district court on the record of the first trial, supplemented with additional memoranda and proposed findings. Upon retrial, the district court found that Mutuelle failed to prove by a preponderance of the evidence that Hammermills’ conduct in designing and manufacturing the automobile shredder proximately caused the January 19, 1981, failure. Therefore, the district court ruled that Hammermills was not liable on the breach of express warranty claim and dismissed the action. Mutuelle now appeals. Mutuelle alleges that the district court erred (1) in refusing either to amend the jury’s verdict by increasing the damage award to the amount of the undisputed cost of investigation and repairs, or to order a new trial on the issue of damages alone, and (2) in granting a new trial on both liability and damages on the express warranty claim.
II. DISCUSSION.
Mutuelle contends that the jury, by its answer to the written interrogatory as well as its two notes to the district court, found Hammermills liable for breach of an express warranty. Mutuelle argues, relying on the seventh amendment and cases such as
Wayne v. New York Life Insurance Co.,
132 F.2d 28 (8th Cir.1942), that when a properly instructed jury returns a finding of liability that is supported by the evidence, then errs in its damage award, the district court as a matter of law may not take the jury’s verdict of liability away from the plaintiff. Mutuelle asserts that this is what the district court did in the present case when it granted a new trial on both liability and damages.
The district court, however, concluded that the jury never in fact made a finding of liability. It noted that while the jury’s response to the written interrogatory indicated that they found Hammermills had breached an express warranty to CFF, this finding does not necessarily entail the further conclusion that Hammermills’ breach constituted the proximate cause of the plaintiff’s damage, as is required for there to be liability.
The district court pointed out that the jury was not specifically asked
to make a finding regarding proximate cause and suggested its inability to structure the award on the three damage categories as well as the wide discrepancy between the damages claimed and the damages awarded militates against concluding that the jury made an appropriate determination of proximate cause to support a full award of damages. Therefore, the district court concluded that the question of liability between Mutuelle and Hammermills had not been satisfactorily resolved by the jury’s verdict, and it granted a new trial on both liability and damages.
Mutuelle, on the other hand, contends that the jury did make a finding of liability. Mutuelle argues that when considering the jury’s verdict a district court must presume that the jury followed the instructions as given. Mutuelle asserts that the instructions given in this case show that the jury necessarily resolved the issue of proximate cause before it found a breach of the express warranty, and therefore that finding constituted a finding of liability.
As discussed above, Mutuelle argues that the district court improperly took away the jury’s finding of liability when it granted a new trial on both liability and damages.
Fed.R.Civ.P. 59(a) provides that “[a] new trial may be granted to all or any of the parties and on all or part of the issues (1) in an action in which there has been a trial by jury * * The granting of a new trial on all issues, or even on some issues, rests with the sound discretion of the district court.
Ryan, By Ryan v. McDonough Power Equipment, Inc.,
734 F.2d 385, 387 (8th Cir.1984);
Ferren v. Richards Manufacturing Co.,
733 F.2d 526, 528 (8th Cir. 1984);
Pitts v. Electro-Static Finishing, Inc.,
607 F.2d 799, 803 (8th Cir.1979). We believe that Mutuelle has failed to demonstrate that the district court abused its discretion. Despite the manner in which the jury was instructed, the verdict and jury communication considered as a whole may have indicated that the jury’s finding of a breach of the express warranty did not include a finding of proximate cause, and hence liability.
The district court’s opinion and the record in this case demonstrates that there were sufficient uncertainties relating to the jury’s verdict to justify the grant of a new trial encompassing both liability and damages on the express warranty claim.
III. CONCLUSION.
For the foregoing reasons, we affirm the judgment of the district court.