Mutual Reserve Association v. Zeran

277 P. 984, 152 Wash. 342, 1929 Wash. LEXIS 606
CourtWashington Supreme Court
DecidedMay 28, 1929
DocketNo. 21154. En Banc.
StatusPublished
Cited by10 cases

This text of 277 P. 984 (Mutual Reserve Association v. Zeran) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mutual Reserve Association v. Zeran, 277 P. 984, 152 Wash. 342, 1929 Wash. LEXIS 606 (Wash. 1929).

Opinions

Tolman, J.

The plaintiff, Mutual Reserve Association, instituted this action to foreclose two trust deeds given to secure the payment of certain negotiable bonds executed by the defendants Zeran and wife. The Massachusetts Mortgage Company was made a party defendant because of its being the holder of two mortgages, also made by Zeran and wife, which mortgages were junior to the trust deeds held by the plaintiff. By answer and cross-complaint, the mortgage company sought foreclosure of its mortgages, subject only to the trust deeds. The individual defendants, doing business as the Francis Construction Company, were made defendants because they claimed a lien upon the property covered by the trust deeds and the mortgages, accruing because of labor and material furnished by them as contractors for the construction of a building on the mortgaged property. By answer and cross-complaint, they sought the foreclosure of their lien as superior to both the trust deeds and the mortgages. The remaining parties who are now before this court came in by intervention, seeking foreclosure of liens for labor and material furnished as subcontractors, which were also claimed to be superior to the trust deeds and mortgages. The cause was tried out on the merits, resulting in a decree which first awarded judgments against Zeran and wife in favor of Mutual Reserve Association for $78,534.35, in favor of Massachusetts Mortgage Company for $20,248, in favor of Francis Construction Company for $37,642.34, and awarded *345 priority of lien rights upon the real estate, and foreclosure thereof, in the following order:

First, to the Mutual Reserve Association, upon its trust deed lien; second, to the intervenors to the extent of their various liens; third, to the Massachusetts Mortgage Company upon its mortgage lien; and fourth, to the Francis Construction Company upon its general contractor’s lien.

By appeal and cross-appeal, a number of these priorities are questioned, and, after outlining the general situation in order to avoid confusion, each claim will be treated separately, so far as possible.

Early in 1926, Zeran and wife were the owners of the real estate in question, which was then improved only by an old building of very little value. Zeran caused plans and specifications to he prepared for remodeling and rebuilding the old structure into a modern apartment house. These plans and specifications were submitted to the Francis Construction Company, and negotiations were had between Zeran, Francis Construction Company, the reserve association and the mortgage company,“resulting in an understanding that negotiable bonds to the amount of $62,500 would be executed by the Zerans secured by a trust deed, as a first lien on the property, running to the reserve association as trustee for the bond holders. A mortgage, junior and subordinate to the trust deed, was also agreed upon, to secure the payment of $15,-000 to be made by the Zerans to the mortgage company, and the proceeds of these loans were to he used to discharge prior liens then against the property, and the overplus was to he advanced to construct the new building. The Francis Construction Company was to have the contract for the construction of the new building on a cost-plus basis, and, according to the plans and specifications then agreed upon, it was estimated *346 that the cost of the new building would, by a small amount, exceed the proceeds of the loans, and that such small balance was to be carried by the contractor until the building was completed, and the excess cost repaid to the contractor out of rentals received from the completed building.

Accordingly, the trust deed to secure the payment of $62,500 was executed April 27, 1926, and recorded May 24,1926. The $15,000 mortgage was executed and recorded May 27, 1926. The Francis Construction Company entered into an agreement with Zeran to erect the building on the cost-plus plan, in which agreement was a provision to the effect that, if the borrowed money proved insufficient to complete and pay for the building, the contractor who was bound to pay for all labor and material should be reimbursed out of the accruing rents from the completed building. Up to this time, no change in the plans had been made or suggested.

The contractor started work on May 20,1926. After the work had progressed for some time, and the contractor had become thoroughly obligated, it was found that the city’s building department made certain objections to some of the features specified for the new building, and, in meeting these objections, the architect made radical changes in the plans which added to the cost of the work something like $10,000, and which would increase the value of the improvement to a like extent.

The contractor and the owner Zeran took this matter up with the representative of the Mutual Reserve Association and the mortgage company,, and it was finally agreed that the loans should be increased; that of the Mutual Reserve Association from $62,500 to $65,000, and that of the Massachusetts Mortgage Company from $15,000 to $18,000, thus making $5500 more avail *347 able for construction purppses. Thereupon a new trust deed was executed to secure a bond issue of $65,000, dated August 18, 1926, and on August 20, 1926, a new note and second mortgage to the Massachusetts Mortgage Company calling for $18,000 was also executed. Both instruments were recorded on August 21, 1926, and the original second mortgage for $15,000 running to the Massachusetts Mortgage Company was released of record on that same day. The original trust deed was not released. The first advance to the contractor under the trust deed was made at just about this time in the amount of $12,000.

It rather clearly appears that the building, as originally contemplated, was estimated to cost in the neighborhood of $60,000. The new revised and detailed plans, to which we have just referred, were submitted to the contractor about a month after he had begun his work, and thereafter these plans seem to have been expanded constantly as the work progressed, and the cost of the building greatly added to without any arrangement as to where the money was to come from to meet the increased costs. The nature of these changes was a complete departure from the original plans, so that, instead of expending $60,000, or less, and having a deficiency of perhaps $2,000 or $3,000 to be repaid out of accruing rentals, the contractor, when the building was finally completed, found it had cost him $91,661.23, and he had a deficit of upwards of $30,-000, for which he filed his lien and asked judgment against the owner.

Coming now to the particular questions here presented, we shall discuss them in what seems to be their logical order.

The contractor undertook the work with full' knowledge of the plan of financing, and knew that $62,500, to be secured by trust deed, was to be a first *348 lien, and $15,000, secured by second mortgage, was to be a second lien, both to be superior to any lien which might accrue in his favor. We can find nothing in the record (barring a special defense hereinafter discussed) which will permit him or the subcontractors under him to take precedence over these liens.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Landover Corp. v. Bellevue Master LLC
252 F. App'x 800 (Ninth Circuit, 2007)
A.A.R. Testing Laboratory, Inc. v. New Hope Baptist Church
50 P.3d 650 (Court of Appeals of Washington, 2002)
Draper MacHine Works, Inc. v. Hagberg
663 P.2d 141 (Court of Appeals of Washington, 1983)
Mead School District No. 354 v. Mead Education Ass'n
534 P.2d 561 (Washington Supreme Court, 1975)
Portland Ass'n of Credit Men, Inc. v. Earley
254 P.2d 758 (Washington Supreme Court, 1953)
PORTLAND ASS'N ETC. v. Earley
254 P.2d 758 (Washington Supreme Court, 1953)
Estate of Wind v. Wind
178 P.2d 731 (Washington Supreme Court, 1947)
Moore v. Tumwater Paper Mills Co.
42 P.2d 29 (Washington Supreme Court, 1935)
Spokane Merchants' Ass'n v. Spokane Dry Goods Co.
299 P. 371 (Washington Supreme Court, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
277 P. 984, 152 Wash. 342, 1929 Wash. LEXIS 606, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mutual-reserve-association-v-zeran-wash-1929.