Mutual of Enumclaw Insurance v. T&G Construction, Inc.

165 Wash. 2d 255
CourtWashington Supreme Court
DecidedOctober 23, 2008
DocketNo. 80420-6
StatusPublished
Cited by1 cases

This text of 165 Wash. 2d 255 (Mutual of Enumclaw Insurance v. T&G Construction, Inc.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mutual of Enumclaw Insurance v. T&G Construction, Inc., 165 Wash. 2d 255 (Wash. 2008).

Opinion

Chambers, J.

¶1 — We are asked to balance the interests of an insured defendant in reaching a reasonable settlement with a claimant against the insurer’s interest in fully [259]*259litigating its insured’s legal obligation to that claimant. In the case before us, Mutual of Enumclaw Insurance Company (MOE), the insurer, vigorously defended its insured, a construction corporation, almost to the end. However, MOE declined to participate in the final round of settlement talks. After the talks concluded, MOE challenged the settlement at the reasonableness hearing. Now, in this separate coverage action, MOE challenges its obligation to pay. MOE’s principal argument is that under the insurance policy, it is obligated to pay only damages that its insured is legally obligated to pay. It believes its insured should have prevailed on an affirmative defense in the liability case. The judge in the underlying liability case rejected the proffered affirmative defense several times, including at summary judgment and at the reasonableness hearing. In this coverage dispute, the insurer seeks to raise the issue again.

¶2 While MOE is correct that its insured’s affirmative defense was never litigated to absolute finality, it was substantially resolved in the underlying liability case. We hold that if a coverage question turns upon the same facts or law at issue in the underlying dispute between the claimant and the insured, the insurer will be bound by the results of a trial or settlement judicially approved as reasonable, absent a showing of collusion or fraud. We reverse the Court of Appeals to the extent it holds otherwise. However, we are unable to determine on the briefing or record whether two policy exclusions apply. Accordingly, we remand to the trial court to reconsider consistent with this opinion the applicability of those two exclusions and to decide attorney fees.

FACTS

¶3 Villas at Harbour Pointe Owners Association (homeowners) sued the developer of their homes for poorly installed siding leading to rot and mold. The developer brought the general contractor into the lawsuit. In due course, the general contractor brought in the subcontrac[260]*260tors, including the siding subcontractor, T&G Construction, Inc. T&G in turn sued its own subcontractors. All in all, there were several dozen parties to the underlying suit.

¶4 T&G’s insurer, MOE, defended T&G under a reservation of rights. More than a year into the underlying litigation, counsel discovered that T&G, a corporation, had been administratively dissolved by the secretary of state for failure to file corporate documents about two years and eight months before it had been sued. At the time, the general statute of limitations for claims against a dissolved corporation was two years. Former RCW 23B. 14.340 (1995). Since this lawsuit was filed more than two years after T&G had been administratively dissolved, its counsel moved for summary judgment dismissal. Among other things, the homeowners argued that the general two year statute of limitations did not apply to known claimants who were not given notice of the dissolution and submitted evidence that the general contractor had informed T&G of the defects prior to its dissolution. Former RCW 23B. 14.060 (1989). The trial court agreed with the homeowners and denied summary judgment.1

¶5 Over several mediations in 2004, almost all parties settled their underlying claims for a net $5.7 million. While T&G settled with and released its subcontractors at about that time, it did not participate in the larger final settlement talks, perhaps because MOE balked at the numbers. MOE appeared to believe that the potentially covered faulty work was limited to specific, remediable mistakes in installing siding around windows, which could be corrected with “spot” or “surgical” repairs costing about $300,000. The homeowners believed that because of T&G’s faulty work [261]*261and the damage that it caused, all buildings needed to be stripped and re-sided.

¶6 Pursuant to court order and presided over by a professional mediator, T&G entered into negotiations with the remaining parties. With MOE’s knowledge, but without its consent or participation, the remaining parties settled their claims against T&G for an additional $3.3 million and the customary assignment of claims against the insurer. The parties sought a reasonableness determination from the Snohomish County Superior Court. MOE appeared in the subsequent reasonableness hearing and objected to the settlement. One of the many issues considered at the hearing was whether an ultimate trier of fact was likely to find that the statute of limitations applied to bar claims against T&G. The judge concluded that the trier of fact was likely to find that the statute of limitations did not apply.2 The Snohomish County judge also concluded that T&G’s proposed limited repair was not a sufficient remedy and that all siding needed to be removed and the buildings re-sided. The experts estimated that the cost of reclading the buildings ranged between about $2 million and $4.6 million; the median of these estimates was the amount of the settlement: $3.3 million. In determining that the settlement was reasonable, the judge also took into consideration that the homeowners had spent $850,000 on the litigation and that, should the case go to trial, T&G was at risk for some or all of these expenses as well as its own costs in conducting a three to five week trial. Although the court initially found that the settlement of $3.3 million was reasonable, upon a motion for reconsideration by MOE, the judge reduced it to $3 million.

¶7 Meanwhile, MOE brought this declaratory judgment action in King County Superior Court against the surviving [262]*262parties, including its insured, arguing that its insured was not liable on the grounds that the statute of limitations had run, that the insured’s damages were outside the coverage provisions, that T&G had breached its obligation to cooperate, and that several policy exceptions applied. In a sequence of decisions, Judge Spector granted summary judgment against MOE on all issues.

¶8 The Court of Appeals reversed. It concluded that given the lack of bad faith, MOE should be allowed to litigate to finality whether the statute of limitations had run on the underlying claims and, if the trial court concluded that the statute of limitations had not run, directed it to consider whether MOE had been prejudiced by its insured’s failure to cooperate at the end of the liability case. Mut. of Enumclaw Ins. Co. v. T&G Constr., Inc., 143 Wn. App. 667, 199 P.3d 984 (2007). Simultaneously, the Court of Appeals upheld the settlement in the liability suit. Villas at Harbour Pointe Owners Ass’n v. Mut. of Enumclaw Ins. Co., 137 Wn. App. 751, 154 P.3d 950 (2007), review denied, 163 Wn.2d 1020 (2008).

¶9 The homeowners and T&G sought review of the coverage case while MOE separately sought review of the underlying liability case. We accepted review of this coverage dispute. We reverse in part, affirm in part, and remand to the trial court for further proceedings consistent with this opinion.

ANALYSIS

¶10 Since only questions of law are presented, our review is de novo. Sherry v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Green v. City of Wenatchee
148 Wash. App. 351 (Court of Appeals of Washington, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
165 Wash. 2d 255, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mutual-of-enumclaw-insurance-v-tg-construction-inc-wash-2008.