Muth Electric, Inc. v. Rice Lake West, Inc., Federal Insurance Company; Rice Lake West, Inc. f/k/a Stanek Constructors, Inc. v. City of Pierre, South Dakota; City of Pierre, South Dakota v. Burns & McDonnell Engineering Company, Inc.

CourtDistrict Court, D. South Dakota
DecidedDecember 12, 2025
Docket4:24-cv-04214
StatusUnknown

This text of Muth Electric, Inc. v. Rice Lake West, Inc., Federal Insurance Company; Rice Lake West, Inc. f/k/a Stanek Constructors, Inc. v. City of Pierre, South Dakota; City of Pierre, South Dakota v. Burns & McDonnell Engineering Company, Inc. (Muth Electric, Inc. v. Rice Lake West, Inc., Federal Insurance Company; Rice Lake West, Inc. f/k/a Stanek Constructors, Inc. v. City of Pierre, South Dakota; City of Pierre, South Dakota v. Burns & McDonnell Engineering Company, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. South Dakota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Muth Electric, Inc. v. Rice Lake West, Inc., Federal Insurance Company; Rice Lake West, Inc. f/k/a Stanek Constructors, Inc. v. City of Pierre, South Dakota; City of Pierre, South Dakota v. Burns & McDonnell Engineering Company, Inc., (D.S.D. 2025).

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF SOUTH DAKOTA SOUTHERN DIVISION

MUTH ELECTRIC, INC, 4:24-CV-04214-RAL Plaintiff, OPINION AND ORDER DENYING vs. FOURTH-PARTY DEFENDANT BURNS & . MCDONNELL’S MOTIONS TO DISMISS RICE LAKE WEST, INC., FEDERAL INSURANCE COMPANY, Defendants, - VS.

RICE LAKE WEST, INC. f/k/a STANEK CONSTRUCTORS, INC., Third-Party Plaintiff,

vs.

CITY OF PIERRE, SOUTH DAKOTA, Third-Party | Defendant and Fourth-Party Plaintiff, vs.

BURNS & MCDONNELL ENGINEERING COMPANY, INC., Fourth-Party Defendant.

Plaintiff Muth Electric, Inc. (Muth) filed a Complaint against Rice Lake West, Inc., f/k/a Stanek Constructors, Inc. (Rice Lake West), and Federal Insurance Company (FIC) asserting diversity jurisdiction pursuant to 28 U.S.C. § 1332(a)(1) and alleging breach of contract and unjust enrichment claims against Rice Lake West and a payment bond claim under S.D.C.L. § 5—21-6 against Rice Lake West and FIC. Doc. 1. Rice Lake West answered, counterclaimed, and filed a Third-Party Complaint against City of Pierre, South Dakota (Pierre) alleging a third-party liability claim pursuant to Federal Rule of Civil Procedure 14 as well as breach of the implied warranty of design adequacy, breach of contract, and unjust enrichment/quantum merit/restitution claims and requesting declaratory judgments. Docs. 7, 22, 25. Third-Party Defendant Pierre answered and filed a Fourth-Party Complaint against Burns & McDonnell Engineering Company (Burns & McDonnell) alleging that should Pierre be liable to Rice Lake West, Pierre is entitled to indemnification from Burns & McDonnell for some or all damages which may be adjudged, and requesting in the alternative, if Pierre is adjudged to be at fault to any degree, for this Court to determine the relative degrees of fault of each party. Doc. 17. Pierre also filed Counterclaims against Rice Lake West alleging breach of contract and negligence. Doc. 16. On June 30, 2025, Muth amended its Complaint and added claims against Fourth-Party Defendant Burns & McDonnell. Doc. 40. With its Answer to the Amended Complaint, Rice Lake West filed an Amended Third-Party Complaint against Pierre, an Amended Counterclaim against Muth, and Crossclaims against Fourth-Party Defendant Burns & McDonnell invoking diversity jurisdiction under 28 U.S.C. § 1332 and supplemental jurisdiction under 28 U.S.C. § 1367. Doc. 48. Fourth-Party Defendant Burns & McDonnell now moves under Federal Rule of Civil Procedure 12(b)(6) to dismiss Muth’s claim against it, Doc. 40, as well as the two claims asserted

by Rice Lake West against it, Doc. 48. Docs. 45, 53. For the reasons explained below, the motions to dismiss are denied. 1 Factual Allegations! This lawsuit arises out of issues concerning a construction project for the City of Pierre. Doc. 40 ¢ 13. In 2021, Pierre solicited bids for a project to improve its existing wastewater treatment plant. Id. Burns & McDonnell was Pierre’s “engineer and authorized representative for the Project,” and it “developed the design for the Project, including preparing the plans, specifications, notice and call for bid, instructions to bidders, general conditions, agreement between owner and contractor, and other contract documents (collectively, the ‘Contract Documents’).” Id. 9] 14-15. Muth alleges that Burns & McDonnell “did not complete an adequate site investigation of existing conditions prior to finalizing the Contract Documents.” Id. 16. On April 20, 2021, Rice Lake West submitted its bid for the prime contract for the Project, Pierre accepted its bid, and Rice Lake West and Pierre executed the prime contract. Id. 17-19. FIC then issued a bond assuring Rice Lake West’s performance and payment bond of the Project. Id. § 20. On May 24, 2021, Rice Lake West and Muth executed a subcontract? for the Project. Id. 21. Muth’s original scope of work included “Division 26 (complete), Division 40 (complete), Division 22 (connections only), Division 23 (connections only), and installing vendor control panels shipped loose with specified equipment, including electrical connections to vendor-

! This Court makes no factual findings in ruling on a motion to dismiss but draws the factual allegations relevant to the pending motions from the Amended Complaint, Doc. 40, and Amended Third-Party Complaint and Crossclaim, Doc. 48, as well as documents necessarily embraced by those pleadings. 2 “The Subcontract incorporated by reference the Prime Contract, including any Contract Documents incorporated therein, to the extent the Prime Contract and Contract Documents apply to the Subcontract Work.” Doc. 40 { 24.

supplied equipment.” Id. § 23. Under the terms of the subcontract, “Muth was required . . . to furnish, deliver, and install all labor and material necessary to complete the Subcontract Work in accordance with the plans and specifications in the Contract Documents prepared by” Burns & McDonnell. Id. 25. Around the end of July 2021, Muth discovered there was an error in the plans and specifications within the Contract Documents prepared by Burns & McDonnell. Id. 26. The

original duct bank design “was incomplete, defective, and would not have produced a fully functional facility” as it contained “incorrect quantities of conduits in the existing and planned duct banks, incorrect sizes of conduits in the existing and planned duct banks, duct banks depicted in the plans and specifications that did not actually exist, and routing of existing duct banks inconsistently with the plans and specifications.” Id. J] 26-27. These errors “constituted a physical condition at the Project site that differed materially from that shown and indicated in the Contract Documents.” Id. § 28. After Muth completed a walk-through of the Project site with —

Burns & McDonnell personnel on or around August 6, 2021, Pierre and Burns & McDonnell, “acting through Rice Lake West, directed Muth to stop work on the Project while they reviewed the Duct Bank Design Error.” Id. ff 31-32. The discovery of what Muth calls the “Duct Bank Design Error” required substantial extra work for Muth “outside the original scope of [Muth’s] Subcontract and required additional time outside of the original scope of the Subcontract,” all of which was necessary to complete the Project. Id. J 33-37. The delays resulting from the design error were compounded by Pierre and Burns & McDonnell, “acting through Rice Lake West, . . . refusing to approve design changes, to accept proposed change orders, or to provide clear and effective direction in a timely manner.” Id.

438. Muth alleges that Pierre and Burns & McDonnell did not address the Duct Bank Design Error in a timely manner or in good faith. Id. J] 39-40. Muth then proceeded with construction and performed extra work “[iJn an effort to maintain the Project’s schedule and to mitigate delays on the Project .. . by following [Burns & McDonnell’s] limited direction.” Id. § 44. On or around June 29, 2022, Pierre and Burns & McDonnell, “acting through Rice Lake West, directed Muth to stop work again.” Id. □ 45. Following this second pause on Muth’s work, “Muth, Rice Lake West, and [Burns & McDonnell] exchanged further information about the Duct Bank Design Error and potential design changes” during the summer and fall of 2022. Id. 46.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Udall v. Tallman
380 U.S. 1 (Supreme Court, 1965)
Scheuer v. Rhodes
416 U.S. 232 (Supreme Court, 1974)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
United States v. Miguel Carrillo
380 F.3d 411 (Eighth Circuit, 2004)
Hagemann v. NJS Engineering, Inc.
2001 SD 102 (South Dakota Supreme Court, 2001)
Casillas v. Schubauer
2006 SD 42 (South Dakota Supreme Court, 2006)
Hendrix v. Schulte
2007 SD 73 (South Dakota Supreme Court, 2007)
Cole v. Wellmark of South Dakota, Inc.
2009 SD 108 (South Dakota Supreme Court, 2009)
Jorgensen Farms, Inc. v. Country Pride Cooperative, Inc.
2012 S.D. 78 (South Dakota Supreme Court, 2012)
Noble Systems Corp. v. Alorica Central, LLC
543 F.3d 978 (Eighth Circuit, 2008)
Waldor Pump & Equipment Co. v. Orr-Schelen-Mayeron & Associates, Inc.
386 N.W.2d 375 (Court of Appeals of Minnesota, 1986)
Muhlenkort v. Union County Land Trust
530 N.W.2d 658 (South Dakota Supreme Court, 1995)
Mid-Western Electric, Inc. v. DeWild Grant Reckert & Associates Co.
500 N.W.2d 250 (South Dakota Supreme Court, 1993)
Lien v. McGladrey & Pullen
509 N.W.2d 421 (South Dakota Supreme Court, 1993)
Ebert v. FORT PIERRE MOOSE LODGE 1813
312 N.W.2d 119 (South Dakota Supreme Court, 1981)
Lee v. Beauchene
337 N.W.2d 827 (South Dakota Supreme Court, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
Muth Electric, Inc. v. Rice Lake West, Inc., Federal Insurance Company; Rice Lake West, Inc. f/k/a Stanek Constructors, Inc. v. City of Pierre, South Dakota; City of Pierre, South Dakota v. Burns & McDonnell Engineering Company, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/muth-electric-inc-v-rice-lake-west-inc-federal-insurance-company-sdd-2025.