Muskogee Refining Co. v. Waters Pierce Oil Co.

1923 OK 270, 215 P. 766, 89 Okla. 279, 1923 Okla. LEXIS 1074
CourtSupreme Court of Oklahoma
DecidedMay 15, 1923
Docket10479
StatusPublished
Cited by18 cases

This text of 1923 OK 270 (Muskogee Refining Co. v. Waters Pierce Oil Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Muskogee Refining Co. v. Waters Pierce Oil Co., 1923 OK 270, 215 P. 766, 89 Okla. 279, 1923 Okla. LEXIS 1074 (Okla. 1923).

Opinion

McNEILL, J.

This action was commenced in the superior court of Muskogee county by the Muskogee Refining Company against the Waters Pierce Oil Company and the Pierce Oil Corporation to reform a written contract entered into between the Muskogee Refining Company and the Pierce-Fordyee Oil Association, and by the Pierce-Fordyce Oil Association assigned to the Waters Pierce Oil Company, and by the latter company assigned to the Pierce Oil Corporation, and to recover judgment for money due under the contract after the same was reformed.

The Muskogee Refining Company by the terms of said contract agreed to sell, all the gasoline, naphtha, and burning oil refined, made, or manufactured by its refinerías at Muskogee and Okmulgee, and the defendant company agreed to purchase the same for a period of three years commencing October 31, 1911. The assignees of the contract do not on appeal contend the question of innocent purchaser is involved. Section 3 of the contract fixed the price to be paid for gasoline, naphtha, and burning oil, so long as the. prices of crude oil purchased by (he plaintiff remained at 54 cents per barrel. Section 6 of the contract is as follows:

“6. Prices to be charged by the first party and .paid by the second party for the commodities sold hereunder are based on the present cost of 54 cents per barrel of 42 gallons for crude oil delivered at the refineries of the first party, which is the present cost *280 lo the first party for the crude oil used in ils refineries.
“And it is lierteby agreed and understood that if the cost of crude oil to tire first party advances or declines during the operation of this contract, that then for each advance or decline in the cost of said crude oil, readjustment of the aforesaid prices shall be' made, so that the prices to be paid for the commodities sold hereunder shall bear the same proportion to the cost to the first party of crude oil as the presen 1 prices bear to the cost of 54 cents per barrel; provided, however, that no readjustment of said prices shall ‘be made unless the cost of said crude oil to the first party shall advance or decline five cents per barrel. A schedule is attached hereto and made a part hereof, marked ‘Schedule A,’ showing the prices to be paid for gasoline, naphtha, and binning oils when the cost of crude oil to the first party advances or declines above the said, present cost of 54 cents per barrel.”

Schedule A attached thereto is as follows:

‘^Schedule A.
“Prices to be paid for gasoline, naphtha and burning oil on advance or decline of crude oil as set forth in paragraph 6 of this contract.” .
“Following figures are based on 56 per cent, of an advance or decline of.5c per barrel from 54 cents as the three products named above constitute 55 per cent, of the crude oil, distributed as follows: gasoline 10 per cent, naphtha 7 per cent, and burning oil 38 per cent.:
Crude: Gasoline: JNapbttia: .Burning Oil
30c bbl, .0530 gal. .0275 gal. .0148 gal.
44o bbl. .0561 gal. .0292 gal. .0157 gal.
40c bbl. .0593 gal. .0308 gal. .0166 gal.
54c bbl. .0625 gal. .0325 gal. .01175 gal.
59c bbl. .0657 gal. .0342 gal. .0184 gal.
04c bbl. .0689 gal. .03-58 gal. .0193 gal.
09c bbl. .0720 gal. .0375 gal. .0202 gal.

The plaintiff’s original petition asked to have the contract reformed by eliminating schedule “A,” for the following reasons: First, the minds of the parties thereto had never met regarding the same; second, the same had not been assented to by the Pierce-Fordyee Oil Association, nor assented to by the board of directors of the plaintiff company ; and third, because the president of the company had no authority to attach schedule “A” to the contract; fourth, because schedule “A” was attached to the contract by mutual mistake of both parties; fifth, because said schedule was repugnant to section 6 of the contract. The original petition was filed in November, ,1912, and was amended after the expiration of the contract, and recovery sought for the full amount claimed due under the contract after schedule “A” was eliminated. It was alleged the plaintiff company delivered the three products manufactured during the term of the contract, which were received by the defendants.

The defendants in their answer admit the execution of the contract, deny there was any mutual mistake in the preparation of schedule “A,” but allege that schedule “A” was prepared by the plaintiff in conformity with the agreement entered into by' the Pierce-Fordyce Oil Association and the plaintiff, and that the plaintiff wasi fully advised of the contents of schedule “A,” which was attached to the contract at the time of the execution and when the same was delivered to the defendant. The defendants further answered that they had purchased the products for a period of two and one-half years under the contract and defendants had paid for said products under schedule “A,” and that plaintiff was estopped from denying the same was not the true contract of the parties.

Wilh the issues thus framed, the case was tried to the court without a jury. The court made findings of fact and conclusions of law and rendered judgment for the defendants. From said judgment the plaintiff has appealed. For reversal, the plaintiff assigns numerous assignments of error. -The first question for consideration is whether the contract should be reformed and schedule “A” eliminated. The trial court fpund that schedule “A” was attached to, the contract by mutual mistake, and further found that the plaintiff by itr-j conduct had ratified the contract with schedule “A” attached, by delivering the products with full knowledge of said mutual mistake. The defendants excepted to the finding of the court that schedule “A” was attached to the contract by mutual mistake, and the plaintiff excepted to the finding of the court that the plaintiff had ratified the contract by complying with its terms with full knowledge of said mistake, if any. It will be necessary to first consider whether the finding that schedule “A” was attached to, the contract by mutual mistake of the parties is clearly against the weight of the evidence, when the evidence is weighed according to the law applicable to reformation of contracts made by mutual mistake. Plaintiff contends this finding is supported.by the evidence, while defendants contend the evidence is insufficient to support said finding; and the plaintiff further contends that the defendants, not having filed a motion for new trial and followed the same by a cross-appeal, cannot question (he correctness of the trial court’s finding that schedule “A” was attached to the contract by mutua) mis *281 take. With this contention we cannot agree. Plaintiff’s position is true when applied to an appellant, but does not apply to the defendants in error, who do not seek to modify the judgment, but only seek to sustain the same.

The Supreme Court of Missouri, in the case of St. Charles Sav. Bank v. Denker, 205 S. W. 208. in the 9th, 10th, and 11th paragraphs of the syllabus, stated as follows:

“!)th.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hough v. Leonard
867 P.2d 438 (Supreme Court of Oklahoma, 1993)
Corn Belt Bank v. Baker
1942 OK 90 (Supreme Court of Oklahoma, 1942)
Martin v. Carman
183 Okla. 177 (Supreme Court of Oklahoma, 1938)
In Re Martin's Estate
1938 OK 322 (Supreme Court of Oklahoma, 1938)
Cunningham v. North British Merc. Ins. Co.
1937 OK 120 (Supreme Court of Oklahoma, 1937)
W. T. Rawleigh Co. v. Cate
1934 OK 726 (Supreme Court of Oklahoma, 1934)
Wilson v. Olsen
1934 OK 52 (Supreme Court of Oklahoma, 1934)
Bush v. Bush
1930 OK 117 (Supreme Court of Oklahoma, 1930)
Bardwell v. Riverside Oil & Refining Co.
1929 OK 382 (Supreme Court of Oklahoma, 1929)
Hawkins v. Ferguson
1928 OK 272 (Supreme Court of Oklahoma, 1928)
Barrows v. Alford
1928 OK 124 (Supreme Court of Oklahoma, 1928)
American Nat. Bank v. Ardmoreite Publishing Co.
253 P. 81 (Supreme Court of Oklahoma, 1926)
Teachers Conservative Investment Ass'n v. England
1926 OK 27 (Supreme Court of Oklahoma, 1926)
Schaff v. Kramer
1925 OK 264 (Supreme Court of Oklahoma, 1925)
Wilkerson v. Wasson
1924 OK 969 (Supreme Court of Oklahoma, 1924)
Naill v. Order of United Commercial Travelers of America
1924 OK 872 (Supreme Court of Oklahoma, 1924)
Loveland v. Loafman
1923 OK 636 (Supreme Court of Oklahoma, 1923)

Cite This Page — Counsel Stack

Bluebook (online)
1923 OK 270, 215 P. 766, 89 Okla. 279, 1923 Okla. LEXIS 1074, Counsel Stack Legal Research, https://law.counselstack.com/opinion/muskogee-refining-co-v-waters-pierce-oil-co-okla-1923.