Muskatell v. City of Seattle

116 P.2d 363, 10 Wash. 2d 221
CourtWashington Supreme Court
DecidedAugust 25, 1941
DocketNo. 28337.
StatusPublished
Cited by15 cases

This text of 116 P.2d 363 (Muskatell v. City of Seattle) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Muskatell v. City of Seattle, 116 P.2d 363, 10 Wash. 2d 221 (Wash. 1941).

Opinion

Jeffers, J.

This is an appeal by plaintiff, Morris Muskatell, from an order made ánd entered by the superior court for King county, granting the motion of defendant, city of Seattle, for a new trial, upon the specific ground that the court erred in giving instructions Nos. 7, 8, and 9, and in refusing to give defendant’s requested instructions Nos. 4, 6, 7, and that portion of No. 8 not contained in instruction No. 10 as given.

*223 This action, predicated upon § 16, of Art. I, of the state constitution, was instituted by plaintiff against the city of Seattle to recover damages to plaintiff’s building, claimed to have resulted from the construction of a sewer, by the city, in front of plaintiff’s property.

The complaint alleges that, prior to June, 1938, the city determined that it would construct a trunk sewer on East Marginal Way, extending along the westerly side of the street; that, pursuant to such determination, the city retained the Queen City Construction Company to do the necessary excavation and construction work; that, on or about June 14, 1938, the construction company commenced work in front of plaintiff’s property; that this work was all done and performed under the direct supervision, inspection, and direction of the city’s engineer; that, as the proximate result of the construction of the sewer, a subsidence in the soil and earth upon plaintiff’s property and beneath his building occurred, resulting in the sinking of the concrete floor in his building and in the cracking and twisting thereof.

The amended answer admitted that the work was done under the direct supervision, inspection, and direction of the city, and denied the allegations as to the damage, if any, to plaintiff’s building, by the construction of the sewer.

As a first affirmative defense, defendant alleged that the work was done in accordance with the approved and up-to-date engineering and sanitary practices.

It is alleged in the second affirmative defense that the injuries, if any, sustained by plaintiff were caused by his own contributory negligence, in that his building was constructed on soil that was largely of filled-in sand, and is located on the old tideland area, which is subject to the inflow and outflow of the tidal waters *224 and underground percolating waters daily; that plaintiff, knowing of this condition, erected his building without proper foundation, and, after having erected his building, plaintiff further aggravated the improper construction by storing great quantities of canned salmon upon the floors, and driving heavily loaded trucks over the floor, all of which caused the building to subside and cracks to appear in the floor; that all of these acts were the proximate cause of the subsidence of the building and the damage claimed by plaintiff.

Third, fourth, and fifth affirmative defenses were also set up in the answer, but, in view of the action taken by the trial court, the allegations contained in those affirmative defenses are not material herein.

The material facts may be stated as follows: Plaintiff’s property, a one story frame building, sheeted with corrugated iron, and used as a fish reconditioning warehouse, is located on the tide flats. The land upon which the building stands is similar to that throughout the entire tideland area. About six feet below the surface, the soil, composed mostly of sand, is impregnated with what is described as percolating waters. This water originates from rainfall upon the surrounding area, especially on Beacon hill, and seeps underground towards the Duwamish river and the sound.

Under plaintiff’s property, as well as under other property in the district, is a water table, which rises when the tide is in, and lowers when the tide is out. When the tide is in, it serves as a dam to check the flow of this ground water, causing the ground to swell, and as the tide goes out and this underground water is allowed to flow, the ground subsides. This ground water is fresh water, and not tidal waters. Engineers and contractors, testifying for plaintiff, stated that, while the sewer was being constructed in front of plain *225 tiff’s property, they saw sand, mud, and water coming into the sewer excavation through the cribbing at the side of the excavation, and coming in from the bottom of the trench from under plaintiff’s building.

Plaintiff and other witnesses testifying in his behalf stated that the cracks in the floor were not there prior to the construction of the sewer, and these witnesses further testified that, in their opinion, the sinking of the floor,' the cracks in the floor, and the injury to the building, for which damages were asked, were caused by the sand, silt, and water which was forced out from under plaintiff’s building into the sewer trench.

Mr. Lennox, one of the operators of the reconditioning plant, testified that, while the work on the sewer was progressing, he observed a settling of the building and the development of cracks in the floor; that he notified the engineer in charge of construction, and the engineer inspected the damage and informed him that he would take care of the matter at once.

Mr. Klaeboe, another of the operators of the reconditioning plant, testified that he notified the construction people of the damage; that he saw the sewer during construction, and that sand, silt, and water were entering the sewer trench through the. sidewalls and from the bottom; that the city had a large pump in the trench which pumped this sand, silt, and water out of the ditch.

The city admits that in digging the sewer trench they affected the underground water, and withdrew the same to some extent from the surrounding area.

Defendant’s witnesses testified that there was very little, if any, sand or silt coming into the trench through the cribbing driven along the sides of the ditch, but that water was coming up from the bottom of the ditch. One witness testified that only water was coming into the ditch. The expert witnesses for the city *226 testified to the effect that the trench in front of plaintiff’s property was dug in accordance with good engineering practice, and that there is no practical method of digging a trench in ground of the nature here encountered, without having water in the bottom thereof.

Mr. Breen, engineer in charge of this work for the city, testified that the ditch was seventeen feet deep; that they struck water at about six feet, and for the remaining eleven feet they were in wet soil and water all the time.

Mr. Sylliaasen, an engineer of long experience, testifying for the city, stated that, in his opinion,

“. . . the cracks in the warehouse floor were caused by settlement in the sand below this structure due to the fact that there was not a foundation under the building which will prevent settlement and that the load which caused the settlement was the dead weight of the building plus loads placed on the building on the floor at various times in years gone past.”

This witness further testified that, in his opinion, based on his examination of the building and known facts in engineering, this building settled and cracked from the day it was constructed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Of Washington v. Derron Patrick Alexis
Court of Appeals of Washington, 2015
State Farm Fire & Casualty Co. v. Municipality of Anchorage
788 P.2d 726 (Alaska Supreme Court, 1990)
Simons v. Tri-State Construction Co.
655 P.2d 703 (Court of Appeals of Washington, 1982)
Bay v. Hein
515 P.2d 536 (Court of Appeals of Washington, 1973)
Bjorvatn v. Pacific Mechanical Construction, Inc.
464 P.2d 432 (Washington Supreme Court, 1970)
Finley v. Teeter Stone, Inc.
248 A.2d 106 (Court of Appeals of Maryland, 1968)
Kelley v. Falangus
388 P.2d 223 (Washington Supreme Court, 1964)
Hagen v. City of Seattle
339 P.2d 79 (Washington Supreme Court, 1959)
Feeley v. ER Butterworth & Sons
259 P.2d 393 (Washington Supreme Court, 1953)
State v. Williams
120 P.2d 496 (Washington Supreme Court, 1941)

Cite This Page — Counsel Stack

Bluebook (online)
116 P.2d 363, 10 Wash. 2d 221, Counsel Stack Legal Research, https://law.counselstack.com/opinion/muskatell-v-city-of-seattle-wash-1941.