Murtland v. Atlantic City

65 A. 1049, 75 N.J.L. 592, 46 Vroom 592, 1907 N.J. LEXIS 258
CourtSupreme Court of New Jersey
DecidedMarch 4, 1907
StatusPublished

This text of 65 A. 1049 (Murtland v. Atlantic City) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Murtland v. Atlantic City, 65 A. 1049, 75 N.J.L. 592, 46 Vroom 592, 1907 N.J. LEXIS 258 (N.J. 1907).

Opinion

The opinion of the court was delivered by

Seed, J.

On June 7th, 1904, the board of water commissioners of Atlantic Oily entered into a contract with Murtland by the terms of which Murtland was to construct a pump well at such times and points and with such force as might be directed by the engineer. It was agreed that the word “engineer” was understood to refer to the engineer and superintendent of the water department of Atlantic City or his successors in office.

The well was to be twenty-five feet in diameter and about thirty feet in depth. A concrete floor was to be laid on the bottom and a curbing of brick and cement built up on the required line.

The contractor was to provide power and piping for pumping and draining the pit. The price for the work was fixed at $4,475.

The point where the well was to be constructed was located by Mr. Myers, assistant engineer for the Atlantic City Water Works.

Mr. Murtland began to excavate for the work on June 24th. He says he had excavated to the depth of sixteen feet below the surface when a column of water burst through the hole in the bottom of the excavation. He says he at once asked Mr. Myers what it meant, and that Mr. Myers told him it was an old test well; that they had been testing for water in that vicinity for the purpose of artesian wells, and not finding any, they had withdrawn the pipe. Mr. Murtland says he fought the inflow of water as well as he could, and dug on until he reached a depth of twenty-seven feet six inches, and had only two feet six inches more to excavate when the test well burst out with such force that he was unable to continue his work. [594]*594This occurred on Tuesday afternoon, and until Saturday he tried every method suggested by himself or Mr. Myers to arrest the flow of water so as to make it possible to resume work, and was unable, to do so. On Monday he returned and found affairs as before. The water department assisted in the endeavor to obviate the difficulty, and sunk an artesian well outside of the excavation to see if it would relieve the pressure upon the old test well, so that the pumps could take care of the water in the well Murtland was trying to construct.

This was a failure also, and in August Murtland announced to the board that he would not go on with the work.

The well was afterwards completed by the board of water commissioners, but not to the depth or according to the mode provided in the contract with Murtland.

In January, 1905, this action was brought. The declaration set out the contract of June as executed by Atlantic City, the defendant, by its agent, the Atlantic City water department. It set out that by this contract it became the duty of the defendant to designate the location for the construction of a well, where the construction thereof, to the best of its knowledge, should be possible of performance; that defendant selected a location over land on which it had previously constructed an artesian well, the piping in which had been withdrawn from the ground and no evidence thereof appeared on the surface of the ground; that the defendant did not notify the plaintiff of the existence of said well; that the plaintiff, in ignorance of its existence, purchased material and excavated to the depth of sixteen feet or thereabouts when the old well broke out; that the plaintiff still continued to dig until it became impossible to excavate to the depth of thirty feet; that the plaintiff, about September 1st, 1904, notified defendant of the impossibility of constructing said well, and then and there rescinded said contract. Another count of the declaration set out the same facts as the preceding count, except the fact of tire rescission of contract, and then charges that, by reason of the impossibility of performance of the contract, the plaintiff became released by the act of defendant from further construction of the well.

[595]*595Iii still another count the plaintiff, after setting out the facts charged as before, further charged that by reason of the-deceptive, false, fraudulent and impossible designation of location for said pump well, the agreement became null and void.

Upon the trial of the cause the only question submitted to the jury aside from the question of damages was whether the presence of the old test well made the execution of the plaintiff’s contract impossible. The trial court charged that if the jury believed that the existence of that sunken well made the performance of this contract impossible, Murtland was justified in rescinding his contract, and would have a right, under the circumstances, -to bring his action. To this judicial statement there, was an exception.

It is observed that the contract was not to construct a well at any particular point. It was to build at such point as might be directed by the engineer and superintendent of the water department of Atlantic City. This was a complete contract, which I assume would have given Mr. Murtland a right of action had the defendant’s engineer refused to designate any point for construction, and this contract was possible of performance if there was any point where the work could have been executed. When the designation, however, was made by the servant of the water company the contract became one to build a well at that particular point.

The plaintiff’s case rested entirely upon the proposition that to build the well described was at that point impossible. The contrariety of judicial sentiment respecting the obligation of one who covenants to do that which is impossible in respect of the question whether the impossibility nullifies the contract, or whether having covenanted he is bound to perform because he has covenanted, need not be discussed. For is there any reason for discussing the effect of such impossibility had the action been brought by the board of water commissioners of Atlantic City against Murtland for failure to perform his contract. This action is brought, as it is perceived, by Murtland against Atlantic City, although he, Murt[596]*596land, has not executed his contract according to the terms of • his agreement.

So far as concerns the plaintiff’s right to recover for the amount of work he had already done when the impossibility of continuing the work became a demonstrated fact, recovery might rest upon the conduct of the defendant in adopting'and using all or a portion of the work which Murtland had already done. The city, while not completing the work in conformity with the specifications under which Murtland was to work, did use the excavation which Murtland had already made.

The proposition is that Atlantic City shall pay Murtland not only for all the work he has done, but also damages for all the work he has not done, although by reason of the impossibility of performance the work may have been of no advantage to Atlantic City.-

It is entirely clear that if both parties stand upon the same footing in respect to that element in the’ contract which made it impossible of execution, no such liability can rest upon Atlantic City.

To impose a liability upon either party there must be something in the covenant which expressly or impliedly provides for such a contingency, or there must be some conduct of the one which amounts to fraud upon the other party.

The vendor who knows of the non-existence of a thing he contracts to deliver is liable for his non-performance. Hills v. Sughue, 15 M. & W. 253.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
65 A. 1049, 75 N.J.L. 592, 46 Vroom 592, 1907 N.J. LEXIS 258, Counsel Stack Legal Research, https://law.counselstack.com/opinion/murtland-v-atlantic-city-nj-1907.