Murphy v. State Ex Rel. Jackson School Township

168 N.E. 875, 90 Ind. App. 432, 1929 Ind. App. LEXIS 337
CourtIndiana Court of Appeals
DecidedDecember 6, 1929
DocketNo. 13,411.
StatusPublished

This text of 168 N.E. 875 (Murphy v. State Ex Rel. Jackson School Township) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Murphy v. State Ex Rel. Jackson School Township, 168 N.E. 875, 90 Ind. App. 432, 1929 Ind. App. LEXIS 337 (Ind. Ct. App. 1929).

Opinion

Nichols, J.

Action by appellee against appellants, whereby appellee sought to recover from appellants on a bond for the faithful performance of a contract for the construction of a school building.

It appears by the special findings of fact that, prior to June 24, 1922, Jackson School Township of Brown county, Indiana, took all steps required by the statutes of Indiana for the construction of a high-school building in said township prior to the letting of a contract for the construction thereof, and that, on July 1, 1922, appellant Murphy submitted his bid for its construction for $15,947, together with a bidder’s bond in the sum of $1,000, executed by Murphy as principal and appellant *433 Federal Surety Company as surety; that said bond was conditioned that if said principal should be awarded the contract, he would, within 10 days after the notice of such award, enter into a contract and give bond for the faithful performance of the contract; that said bid and bidder’s bond in the sum of $1,000 bore the date of June 24, 1922, and were submitted to said Jackson School Township by appellant Murphy, which bid was opened on July 1, 1922, by said trustee and the advisory board of said township, and that it was the lowest and best bid submitted for such construction; that said bid was accepted by said trustee and advisory board of said township; that, after the acceptance thereof, and within 10 days thereafter, Murphy entered into a written contract which was signed by himself and the trustee of said township, wherein he agreed to construct a school building according to the plans and specifications drawn and prepared by the architect, and approved by the advisory board and trustee. The contract is set out in full in the findings, but, as will appear hereinafter, we need set out only the 14th provision thereof. It is as follows: “It is further mutually agreed by the parties hereto that no certificate given or payment made under this contract, except the final certificate or final payment, shall be conclusive evidence of the performance of this contract, either wholly or in part, against any claim of the owner, and no payment shall be construed to be an acceptance of any defective work.”

It further appears by the findings that, on July 1, 1922, and after appellant Murphy and said trustee had entered into the contract whereby he agreed to construct the high-school building for $15,947, he delivered to the trustee a $21,000 bond, executed by himself as principal and appellant Federal Surety Company as surety, which bond was delivered and accepted as a construction bond *434 to secure the faithful execution of said contract as required by law, which bond is the bond now in suit; that, by a mutual mistake of all the parties thereto, said bond of $21,000 was a “bidder’s bond” instead of a bond to guarantee the faithful performance of the contract entered into and signed by Murphy to construct said school building; and that, by a mutual mistake of all parties thereto, said bond was conditioned as follows: “That if the aforesaid principal shall be awarded the contract, the said principal will, within ten (10) days after the notice of said award, enter into a contract and give bond for the faithful execution of the contract,” instead of the conditions that were provided by the statute, requiring said contractor to execute a bond conditioned that he would faithfully perform the terms of said contract, and that he would pay all labor, material and subcontractors as by law required, which conditions were intended to be used by appellant Murphy and by appellant Federal Surety Company and by Jackson School Township; that, by the mutual mistake of all parties thereto, said bond was executed, delivered and accepted in such defective and erroneous condition as aforesaid, and the relator believed at said time that the bond was in the correct form and to contain the true and correct conditions as provided by law for such bonds, and that appellant Murphy so believed at said time, and said Federal Surety Company, by its agent Charles filing, and that each and all of said parties believed and understood that said bond, at said time, was to guarantee the faithful performance of said contract by said Murphy; that, by the mutual mistake of each and all of said parties, said bond was made payable to the State of Indiana instead of to the trustee of Jackson School Township; that said contract and bond were accepted and approved by said school township by its proper officers, and, immediately thereafter, Murphy entered upon the work, and so con *435 tinued until such work had progressed to the point where he maintained that the same was completed according to the plans and specifications; that on September 4, 1923, the advisory board of said township was called in special session by the trustee at his office for the purpose of considering the making of final payment to Murphy for the construction of said schoolhouse; that said meeting was attended by the trustee, members of the advisory board, the architect and Murphy; that, at said time, the architect made his final certificate, and the trustee paid to Murphy, the contractor, $1,200, being in full of the balance of the contract price; that, at said time, neither the trustee nor the advisory board knew of any defects or omissions made by said contractor in the construction of said building, and neither the trustee nor the advisory board knew that Murphy had failed to construct said building as provided in the said contract; that, after said final payment, it was discovered and learned by said trustee and advisory board that said contract had not been fulfilled according to the terms thereof, and that said building had not been constructed according to said contract and the plans and specifications therein contained, and that the trustee immediately so informed Murphy and demanded of him that he correct the defects and omissions made by him in such construction, which Murphy refused to do, and, immediately thereafter, relator informed appellant surety company in writing of the defects and omissions of Murphy in the construction of the school building, which notice was received by the surety company, and that such surety company thereafter failed to correct the defects and omissions made by Murphy in the construction of such building; that, thereafter, on August 5,1925, the trustee advertised in the manner required by law that bids would be received at the office of the trustee of said township on August 5,1925 for the completion of said school *436

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Board of Commissioners
148 N.E. 198 (Indiana Supreme Court, 1925)
State, Ex Rel. v. Martin, Aud.
154 N.E. 284 (Indiana Supreme Court, 1926)
Hull v. Board of Commissioners
143 N.E. 589 (Indiana Supreme Court, 1924)
Linville v. State ex rel. Board of Commissioners
29 N.E. 1129 (Indiana Supreme Court, 1892)

Cite This Page — Counsel Stack

Bluebook (online)
168 N.E. 875, 90 Ind. App. 432, 1929 Ind. App. LEXIS 337, Counsel Stack Legal Research, https://law.counselstack.com/opinion/murphy-v-state-ex-rel-jackson-school-township-indctapp-1929.