Murphy v. City of Yonkers

60 N.Y.S. 940, 45 A.D. 621

This text of 60 N.Y.S. 940 (Murphy v. City of Yonkers) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Murphy v. City of Yonkers, 60 N.Y.S. 940, 45 A.D. 621 (N.Y. Ct. App. 1899).

Opinion

GOODRICH, P. J.

The action is brought to recover a balance alleged to have been due from the defendant to one Dennis Murphy on a contract, and for extra work. The plaintiff is the assignee of the contract, and recovered judgment on a verdict for $5,000. From such judgment, and an order denying a motion for a new trial, the defendant appeals.

The contract, dated November 19,1888, provided for the building of a sewer east through Garden street into Nepperhan avenue, and north through that avenue to its intersection with Ashburton avenue. The price was to be $23,750, 10 per cent, of which was to be retained by the city until six months after the completion of the contract, and the acceptance of the work by the city, up to which time the contract- or was to “keep the whole work executed by Mm in perfect order and repair.” The work was to be completed witMn 95 days from its commencement, excluding Sundays and holidays and the time during which work should be suspended in winter; and the contractor was to pay $7 per day as liquidated damages for each day in excess of jthat time. Specifications and plans in accordance with wMch the work was to be done were made part of the contract. The plaintiff alleged completion of the contract on March 20, 1890, and sued to re[941]*941cover the 10 per cent., and certain claims for extra work not included in the contract, only three of which were submitted to the jury. They are: (1) extra work in shoring up and supporting the arch of the Croton Aqueduct where it crossed the line of the sewer, $250; (2) extra work in repairing a completed portion of the sewer at Ashburton avenue, where it had been injured by the negligent acts of the city in causing an overflow of water from its hydrants, $296; (3) extra work at the junction and drop well of Ashburton and Nepperhan avenues, $580. The defendant claims that these items, with interest to the date of the verdict, would amount as follows:

First item....................°............................. $ 250
Interest ................... 130
_ <£ ggQ
Second item............................................... $ 296
Interest................................................... 153
_ 449
Third item................................................$ 580
Interest .................................................. 301
- 881
Fourth item, 10 per cent................................ $2,375
Interest................................................... 1,235
- 3,610
Total ..................................................... $5,320

—And that, as the verdict wras for $5,000, some parts of each of the four items must have been deducted by the jury; and, in general, that the plaintiff was not entitled to a recovery, because the contractor never completed his contract. These several items will be considered in their order. There was a sharp conflict of testimony on each of these questions, and it becomes necessary to refer to the evidence and the charge of the court upon each item.

As to the first, of $250, it appeared in evidence that at the point where the Croton Aqueduct crossed the line of the sewer there was a water main of the city of Yonkers in the center of the street; that the water board, under whose supervision the sewer was built, desired to have this main removed to the side of the street, near the Croton Aqueduct arch; and that the contractor claimed that such work was not within the terms of his contract, but that the city concluded that the work ought to be done, leaving open the question whether or not the work which the removal rendered necessary was outside of the contract. We think the work did not fall within the specifications, but was extra work, and was necessitated by the order to change the location of the water pipe. There was some conflict of evidence on the subject, and as to amount, but the court fairly submitted the matter to the jury.

The second item relates to work which, the plaintiff gave evidence to show, resulted from the letting loose of a large and unusual body of water from one of the city’s hydrants, by employés of the city, at a place where sufficient precautions had been taken by the contractor against injury to the newly-built sewer from the ordinary flow of water. The plaintiff also gave evidence to show that, by reason of the bad condition in which the gutters were maintained by the city, the water was carried upon the sewer construction, and dam[942]*942aged it, and that the extra work occasioned by repairs amounted to the sum of $296. The city claimed that the overflow was an ordinary one, and hence arose another question of fact, which was properly submitted to the jury. It may also be observed that the clause in the contract which required the contractor to keep the work executed by him in repair for six months after the completion did not relate to injuries caused by such acts or omissions on the part of the city.

The third item is somewhat more complicated. It relates to a junction and drop well at the intersection of Ashburton and Nepperhan avenues, where another line of sewer, running through Ashburton avenue, crossed the new sewer.. The plan in evidence, and referred to in the contract, shows no such construction in detail, but the specifications embodied in the contract provided as follows:

“There shah be a junction at Ashburton avenue with 48-inch branch towards the east, to be closed with a bulkhead of brickwork, not less than 12 inches. This junction shall also be provided with a manhole and drop well to receive the discharge from the Ashburton avenue sewer that may hereafter be built on the east side.” .

The counsel for the city contended that the word “east,” last used, was a clerical error for “west,” and cited a clause in the proposals for bids annexed to the contract, and containing these words:

“1 junction at Ashburton avenue, with 48-inch connection towards the east, and with drop well and 36-inch connection towards the west.”

The city contends that the contractor necessarily must have understood that “the only purpose of a drop well in a main line of sewer is to receive the flow from a sewer of higher elevation than the main line of the sewer,” and consequently must have known that the word “east” was a clerical error for “west.” In other words, the contention is that this fact is of common knowledge. At least one of the members of this court (the writer) has no such knowledge, however common it may be, and personally considers the contention of common knowledge to be unsound. Indeed, it may be that a drop well would he of more or less service on either the upper or lower side of the main sewer,—on the upper side, to prevent a forcible inflow of water to the main sewer; and on the lower side, to prevent a forcible outflow from such sewer, if it became overloaded with the discharge from the crossing sewer, or as a result of its own accretions. Within common knowledge, one purpose might be as useful as the other. Be that as it may, the contract is plain, and the contractor had a right, if he acted in good faith, to rely upon the exact words of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dwyer v. Board of Education
27 A.D. 87 (Appellate Division of the Supreme Court of New York, 1898)
Lawrence v. Mayor of New York
29 A.D. 298 (Appellate Division of the Supreme Court of New York, 1898)
Slattery v. Mayor
31 A.D. 127 (Appellate Division of the Supreme Court of New York, 1898)
Lawrence v. Mayor
51 N.Y.S. 416 (Appellate Division of the Supreme Court of New York, 1898)

Cite This Page — Counsel Stack

Bluebook (online)
60 N.Y.S. 940, 45 A.D. 621, Counsel Stack Legal Research, https://law.counselstack.com/opinion/murphy-v-city-of-yonkers-nyappdiv-1899.