Murphy v. Amoco Production Co.

590 F. Supp. 455, 83 Oil & Gas Rep. 108, 1984 U.S. Dist. LEXIS 17055
CourtDistrict Court, D. North Dakota
DecidedMay 2, 1984
DocketCiv. A1-82-91
StatusPublished
Cited by6 cases

This text of 590 F. Supp. 455 (Murphy v. Amoco Production Co.) is published on Counsel Stack Legal Research, covering District Court, D. North Dakota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Murphy v. Amoco Production Co., 590 F. Supp. 455, 83 Oil & Gas Rep. 108, 1984 U.S. Dist. LEXIS 17055 (D.N.D. 1984).

Opinion

MEMORANDUM AND ORDER

VAN SICKLE, District Judge.

This diversity case involves two oil and gas leases. The complaint has three counts, but the third count, a claim for an accounting, was severed from the main trial. See Order dated February 24, 1984. The remaining counts were tried before the Court on February 28-29, 1984, with the parties stipulating to certain background facts.

Plaintiff owns the mineral interests in the S% of Section 2, all of Section 3, the E% of the NE'/i of Section 10, the SEV4 of Section 10, the EV2 of the SWV4 of Section 10, the SW 1 /) of Section 11, the NV2 of Section 14, and the NV2 of Section 15 of Township 146 North, Range 96 West, Dunn County, North Dakota. Defendant held leases on these interests at all times material to the case. The property is located in the Rattlesnake Point-Duperow field.

The disputes between plaintiff and defendant pertain to two wells drilled by defendant: the Murphy B-l in the EV2 of the NEV4 of Section 10 and the Lubke well in the NW!/4 of Section 11. The Court will discuss the counts relating to each of these wells.

COUNT ONE: THE MURPHY B-l WELL

The lease on the EV2 of the NEV4 of Section 10 ran for a primary term ending *458 January 16, 1980, at midnight, but could be automatically extended if drilling operations were commenced before the primary term expired. See Paragraphs 2 and 5 of Exhibit 7 to the parties’ stipulated facts. Plaintiff claims that defendant wrongfully, willfully and maliciously trespassed on its property by spudding the Murphy B-l after the lease expired. It also claims that defendant breached an implied covenant to use reasonable care and diligence in drilling operations.

Preparatory activities for drilling the Murphy B-l began in December 1979. Around December 11, the well location was staked and surveyed. On December 18, defendant prepared an application for a well permit, which was approved on December 26. Negotiations with the surface owner, Hugh Murphy, began at least by December 21. And work on the access road and well location commenced on December 26 or 29.

By January 8, 1980, a drilling rig, work-over rig capable of drilling to a depth of 16,000 feet, and other equipment were on the site. A 60-70 foot hole was drilled for the conductor pipe. On January 15, 1980, defendant’s drilling contractor was within three to five hours of spudding the well, when it was served with an ex parte temporary restraining order (TRO), enjoining further drilling. The contractor complied with the TRO. On January 16, 1980, defendant filed an affidavit of lease extension with the appropriate county recorder.

The TRO issued from a district court for the State of North Dakota and was effective until defendant gave Hugh Murphy the written notice required by N.D.C.C. § 38-11.1-05. Defendant had intentionally failed to give such notice, on advice of counsel that the statute was unconstitutional.

On February 1, 1980, a show cause hearing was held, which resulted in the issuance of a preliminary injunction to the same effect as the TRO. Defendant served written notice on Hugh Murphy on February 2, 1980, and proceeded to spud the well that same day. Drilling continued for a total of 84 days until a depth of 14,288 feet at the Red River level was reached. The well was then plugged at 11,866 feet in the Duperow formation. Drilling to the Red River level took the ordinary and expected amount of time for the industry.

The drilling rig and workover rig remained on site until early 1981. The well was finally plugged on March 4, 1981, and around that same time defendant released the lease.

Hugh Murphy later sued defendant for damages to the surface. Defendant challenged the constitutionality of N.D.C.C. § 38-11.1-05 in the suit, and the Eighth Circuit ultimately ruled that the statute is constitutional. See Murphy v. Amoco Production Co., 729 F.2d 552 (1984).

This Court finds that defendant did not trespass on plaintiff’s property, because defendant’s operations automatically extended the lease term. Drilling operations commence when (1) work is done preparatory to drilling, (2) the driller has the capability to do the actual drilling, and (3) there is a good faith intent to complete the well. See Muth v. Aetna Oil Co., 188 F.2d 844 (7th Cir.1951); Geier-Jackson Inc. v. James, 160 F.Supp. 524 (E.D.Tex.1958); Le-Bar v. Haynie, 552 P.2d 1107 (Wyo.1976). It is not necessary that the drill bit actually penetrate the ground. See Humphrys v. Skelly Oil Co., 83 F.2d 989 (5th Cir.1936).

Prior to the expiration date of the primary term, defendant had undertaken substantial activities in preparation for spud-ding the well. The work had progressed so far that the preliminary drilling for the piping was done. A workover rig capable of spudding was in place and operating. And defendant had a good faith intent to complete the well, as evidenced by the advanced stage of drilling operations reached on the eve of expiration and by defendant’s actually and timely completing the well. 1

*459 The Court also finds that defendant did not breach its implied covenant to develop the well with reasonable diligence. This covenant is implied in an oil and gas lease where such construction would not be inconsistent with its express provisions. See Hermon Hanson Oil Syndicate v. Bentz, 77 N.D. 20, 27, 40 N.W.2d 304, 308 (1949). It is part of the implied obligation of a lessee to do everything that a reasonably prudent operator would do in developing, marketing and protecting the property, giving due consideration to the interests of both lessor and lessee. See Olson v. Schwartz, 345 N.W.2d 33, 38-40 (1984). The covenant is appropriately implied in the lease between plaintiff and defendant.

A temporary set-back in drilling operations is not necessarily a breach of this implied covenant. Gf Sorum v. Schwartz, 344 N.W.2d 73, 76 (1984) (temporary cessation of production will not automatically terminate the lease). Rather, the Court must look to a totality of the circumstances to determine whether a lessee met the reasonably prudent operator standard. See Olson, 345 N.W.2d at 39-40.

Plaintiff contends that defendant failed to act reasonably when it chose to spud the well so close to the expiration date. As seen above, spudding is not the only act which triggers an automatic extension such as the one in this lease. Defendant began sufficient preparatory acts a reasonable time before the expiration date.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hess Bakken Investments II v. AgriBank
2020 ND 172 (North Dakota Supreme Court, 2020)
Anderson v. Hess Corp.
649 F.3d 891 (Eighth Circuit, 2011)
Anderson v. Hess Corp.
733 F. Supp. 2d 1100 (D. North Dakota, 2010)
Greenfield v. Thill
521 N.W.2d 87 (North Dakota Supreme Court, 1994)
Eason Oil Co. v. Howard Engineering, Inc.
1990 OK 101 (Supreme Court of Oklahoma, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
590 F. Supp. 455, 83 Oil & Gas Rep. 108, 1984 U.S. Dist. LEXIS 17055, Counsel Stack Legal Research, https://law.counselstack.com/opinion/murphy-v-amoco-production-co-ndd-1984.