Murphree v. Trinity Universal Insurance

269 P.2d 1025, 176 Kan. 290, 1954 Kan. LEXIS 271
CourtSupreme Court of Kansas
DecidedMay 8, 1954
Docket39,345
StatusPublished
Cited by7 cases

This text of 269 P.2d 1025 (Murphree v. Trinity Universal Insurance) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Murphree v. Trinity Universal Insurance, 269 P.2d 1025, 176 Kan. 290, 1954 Kan. LEXIS 271 (kan 1954).

Opinion

*291 The opinion of the court was delivered by

Price, J.:

This was an action by a subcontractor against the contractor and his corporate surety on what is commonly referred to as a statutory lien bond.

In December, 1950, one Gould and his wife entered into a written contract with one Abney, a contractor, whereby the latter was to construct a home for the Goulds in the city of Newton for the contract price of $25,000. The contract provided for the giving of a bond by Abney to guarantee faithful performance of the contract, but did not provide for a bond to guarantee payment of lienable claims such as is provided for by G. S. 1949, 60-1412. However, such a statutory lien bond was given. It was dated January 31,1951, was signed by Abney as principal and by defendant insurance company as surety, and was in the penal sum of $25,000. It was conditioned that the principal or the subcontractor or subcontractors of the principal shall pay all indebtedness incurred for supplies, materials or labor furnished, used or consumed in connection with or in or about the construction of the house.

The contract between the Goulds and Abney provided that if the latter should be unable to furnish any material called for by the plans and specifications, or substitute material agreed upon, the Goulds might furnish such materials at cost, such cost to be deducted from the stated contract price, and further provided that if construction should not be completed by May 1, 1951, or in the event of abandonment or substantial abandonment or failure of the contractor to proceed with the completion of the building, the Goulds might take over the improvements and procure such materials and labor as were necessary and proper to complete the building and improvements in accordance with the plans and specifications, and that they might then deduct the cost of completing the building from the total contract price. The contract further provided that such provision for completion of the building by the Goulds should in no way affect, release or exonerate any surety or sureties on any guarantee or bond made in connection with the contract.

Abney began work under the contract early in January, 1951. During the early months of construction he had several other construction jobs in progress. He left the Gould project uncompleted, and his last work on it was about the middle of October, 1951.

As is so often the case in a matter of this kind, during the con *292 struction numerous changes and additions were made all over the house. An illustration of this is the case of the plaintiff, Murphree, who. had a written subcontract from Abney to furnish the labor and materials to install the plumbing, heating, electrical system and guttering, at a subcontract price of $4,000. The instant action was filed by him against Abney as principal in the bond and the corporate surety therein to recover a sum in excess of $4,500 for additional labor and materials occasioned by the changes and alterations made as construction of the house progressed.

Service of process was not made on Abney and he is not a party to this litigation. The action therefore stands against only the corporate surety on Abney’s statutory lien bond.

Other claimants for materials and labor furnished by them in the construction of the house were joined as defendants and they filed their answers and cross-petitions seeking recovery on their claims against Abney’s corporate surety.

The trial court made findings of fact and conclusions of law. These findings, insofar as the same are material for a proper disposition of this appeal, are, in substance, as follow:

With respect to Murphree, the court found that he had a written subcontract from Abney to furnish the labor and materials to install the plumbing, heating, electrical system and guttering called for by the building contract, and that he had been paid the full subcontract price of $4,000. The court further found that Murphree furnished several other items of labor and material referred to as “extras,” which went into the construction, and that of such extras items totalling $598.88-were outside his subcontract and were ordered by the contractor Abney, and that other extras were ordered directly by the Goulds and another person who was a stranger to the contract and who was not shown to have had any right to represent either the Goulds or Abney. The court also found there was no evidence that any of the extras claimed by Murphree were agreed upon between the Goulds and Abney.

With respect to claimant Voth, the court found that his testimony showed an “arrangement” with Abney as a subcontractor to furnish millwork and cabinet work for the house which had not already been furnished; that this arrangement or understanding was had with Abney and the Goulds in July, 1951. Voth’s material and time sheets were marked either “Gould”, or “Jim Gould residence.” He did not bill Abney for any of his work but did bill Gould. Voth’s *293 total charges for his mill and cabinet work amounted to $6,207.16, of which amount Gould paid him $5,050.00.

With respect to claimant Anderson’s claim for materials and labor in connection with painting, finishing and decorating of the house, the court found that such claimant had no subcontract with Abney; that the work and materials furnished by him were not ordered by Abney; that the bills for such work and materials were billed to Gould, and that of the total charges of Anderson, amounting to $5,030.32, the sum of $3,407.25 had been paid by Gould.

With respect to claimant Dobson’s claim for labor and material furnished, totalling $624.60, the court found that such labor and materials were furnished by Dobson at the instance and direction of Gould and not under any subcontract or agreement with Abney.

The court’s conclusions of law were as follow:

“1. The bond sued on is ‘for the benefit of all persons in whose favor liens might accrue’ in the absence of the bond. It is a substitute for liens.
“2. The plaintiff and the defendant cross-petitioners assert their claims herein as subcontractors. They may recover only for materials and labor furnished ‘under a subcontract with the contractor.’
“3. No recovery can be had in this action against the surety, Trinity Universal Insurance Company, on any claim for which the principal, John P. Abney, is not hable.
“4. The plaintiff is entitled to recover from the defendant surety the sum of $598.88, being the total of the charges for ‘extras’ which it is stipulated were furnished on the order of the contractor, Abney, with interest at the rate of 6 percent per annum from the 24th day of May, 1952.
“5. None of the cross-petitioners are entitled to any recovery herein.
“6. The costs of this action should be assessed one-half against the defendant surety and one-half against the defendant cross-petitioners.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J. W. Thompson Co. v. Welles Products Corp.
758 P.2d 738 (Supreme Court of Kansas, 1988)
Cedar Vale Co-Op Exchange, Inc. v. Allen Utilities, Inc.
694 P.2d 903 (Court of Appeals of Kansas, 1985)
Bob Eldridge Construction Co. v. Pioneer Materials, Inc.
684 P.2d 355 (Supreme Court of Kansas, 1984)
Toler v. Satterthwaite
434 P.2d 814 (Supreme Court of Kansas, 1967)
Barlite, Inc. v. Trinity Universal Insurance Co.
400 S.W.2d 405 (Court of Appeals of Texas, 1966)
Leidigh & Havens Lumber Co. v. Bollinger
396 P.2d 320 (Supreme Court of Kansas, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
269 P.2d 1025, 176 Kan. 290, 1954 Kan. LEXIS 271, Counsel Stack Legal Research, https://law.counselstack.com/opinion/murphree-v-trinity-universal-insurance-kan-1954.