Munson Hardisty, LLC v. Legacy Pointe Apartments, LLC

CourtCourt of Appeals for the Sixth Circuit
DecidedMarch 28, 2025
Docket23-5732
StatusUnpublished

This text of Munson Hardisty, LLC v. Legacy Pointe Apartments, LLC (Munson Hardisty, LLC v. Legacy Pointe Apartments, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Munson Hardisty, LLC v. Legacy Pointe Apartments, LLC, (6th Cir. 2025).

Opinion

NOT RECOMMENDED FOR PUBLICATION File Name: 25a0171n.06

No. 23-5732

UNITED STATES COURT OF APPEALS FILED FOR THE SIXTH CIRCUIT Mar 28, 2025 KELLY L. STEPHENS, Clerk ) MUNSON HARDISTY, LLC, ) Plaintiff-Appellee, ) ON APPEAL FROM THE ) UNITED STATES DISTRICT v. ) COURT FOR THE EASTERN ) DISTRICT OF TENNESSEE LEGACY POINTE APARTMENTS, LLC, ) Defendant-Appellant. ) OPINION ) )

Before: BATCHELDER, BUSH, and BLOOMEKATZ, Circuit Judges.

ALICE M. BATCHELDER, Circuit Judge. Legacy Pointe Apartments hired Munson

Hardisty to build an apartment complex in Tennessee. As with most construction contracts,

however, plans often change, and this project was no exception. Indeed, as the project progressed,

the parties made many changes to the project’s plans and specifications, which ultimately forced

Munson Hardisty to do extra work. But when the parties made these changes to the contract, they

did so without following the contract’s explicit requirements for change orders. When it later came

time to pay Munson Hardisty for its extra work, Legacy Pointe refused to do so. Munson Hardisty

then sued, and a jury awarded it almost $1.3 million in damages. For the reasons below, we affirm.

I.

In 2007, Legacy Pointe hired Munson Hardisty to build an apartment complex in

Knoxville, Tennessee. The two parties agreed to a so-called “cost-plus” construction contract,

under which the Department of Housing and Urban Development (HUD) would guarantee the loan

given to Legacy Pointe, and Legacy Pointe would pay Munson Hardisty a little more than No. 23-5732, Munson Hardisty v. Legacy Pointe Apartments

$18 million to build the apartment complex. Because HUD agreed to guarantee the loan given to

Legacy Pointe, the contract required that any changes to the project be submitted to HUD and the

lender for their approval.

As the project progressed, Legacy Pointe began to change the plans and specifications

outlined in the contract, and that, in turn, required Munson Hardisty to do extra work. But rather

than submit these change orders to HUD and the lender for their approval, as the contract required,

the parties instead agreed to make these changes to the project on the side. And so, perhaps

unsurprisingly, when it eventually came time for Legacy Pointe to pay Munson Hardisty for the

extra work that it had performed, Legacy Pointe refused to do so.

After Legacy Pointe refused to pay for the extra work, Munson Hardisty sued, alleging

both that an implied contract for the work existed, and that Legacy Pointe had been unjustly

enriched when it received the benefits of Munson Hardisty’s work without paying. The case

eventually proceeded to trial, which resulted in a jury’s awarding Munson Hardisty $350,000 on

its implied-contract claim and $930,000 on its unjust-enrichment claim. Legacy Pointe now

appeals.

II.

Legacy Pointe raises two main challenges to the jury’s verdict: (1) that the jury could not

award Munson Hardisty implied-contract and unjust-enrichment damages when an express

contract between the parties existed; and (2) that the jury could not award damages to Munson

Hardisty under both its implied-contract and unjust-enrichment theories because the award is

duplicative. We disagree and address each issue in turn.

First, Legacy Pointe maintains that Munson Hardisty could not recover any implied-

contract damages here because the express contract between the parties covered all claims for extra

-2- No. 23-5732, Munson Hardisty v. Legacy Pointe Apartments

work. But Legacy Pointe never raised this argument in the district court, and it even conceded

during its opening argument at trial that any work performed by Munson Hardisty without approval

from HUD was “not part of the construction contract.” So Legacy Pointe cannot now claim—for

the first time on appeal—that the express contract between the parties precluded Munson Hardisty

from recovering implied-contract damages. See, e.g., Barner v. Pilkington N. Am., Inc., 399 F.3d

745, 749 (6th Cir. 2005) (“Our function is to review the case presented to the district court, rather

than a better case fashioned after a district court’s unfavorable order.”).

Besides, even if Legacy Pointe had raised and preserved this argument below, the outcome

here would still be the same. That is because whether a contract covers a particular subject matter

is a question of fact for the jury under Tennessee law, see Bratton v. Bratton, 136 S.W.3d 595, 601-

02 (Tenn. 2004), and we cannot overturn a jury’s factual finding unless “there [was] no material

evidence to support the [jury’s] verdict,” Campbell v. Fla. Steel Corp., 919 S.W.2d 26, 35 n.3

(Tenn. 1996). Here, the district court instructed the jury that it could not award damages under the

implied-contract and unjust-enrichment theories unless it found that an express contract did not

cover the extra work performed by Munson Hardisty, and we cannot say that the jury had no

material evidence to support such a finding when both parties seemingly agreed not to follow the

contract’s requirements for change orders and extra work.

Second, Legacy Pointe’s argument that Munson Hardisty received duplicative damages

awards also fails because the district court instructed the jury at trial that it could award damages

under both Munson Hardisty’s implied-contract theory and unjust-enrichment theory, and Legacy

Pointe never objected to those instructions. And when, as here, a party does not object to the

district court’s jury instructions, we review the accuracy of those instructions for plain error.

Craddock v. FedEx Corp. Servs., Inc., 102 F.4th 832, 842 (6th Cir. 2024). To prevail under the

-3- No. 23-5732, Munson Hardisty v. Legacy Pointe Apartments

plain-error standard, Legacy Point must establish four elements: (1) that there was an error; (2) that

the error was plain; (3) that the error affected a substantial right; and (4) that the error “seriously

affected the fairness, integrity, or public reputation of the judicial proceedings.” United States v.

Tragas, 727 F.3d 610, 616 (6th Cir. 2013).

Here, we do not believe that the district court’s jury instructions failed this test. For one

thing, it is not clear that the district court’s jury instructions even misstated Tennessee law, which

does appear to distinguish between unjust-enrichment and implied-contract claims. See Fam. Tr.

Servs. LLC v. Green Wise Homes LLC, 693 S.W.3d 284, 305-06 (Tenn. 2024). But in any event,

even if the district court’s jury instructions had misstated Tennessee law, that purported error would

not be plain.

III.

Because Legacy Pointe failed to preserve its arguments and never objected to the district

court’s jury instructions, we AFFIRM the judgment of the district court.

-4-

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Joanne Tragas
727 F.3d 610 (Sixth Circuit, 2013)
Bratton v. Bratton
136 S.W.3d 595 (Tennessee Supreme Court, 2004)
Campbell v. Florida Steel Corp.
919 S.W.2d 26 (Tennessee Supreme Court, 1996)
Yvonne Craddock v. FedEx Corp. Servs., Inc.
102 F.4th 832 (Sixth Circuit, 2024)

Cite This Page — Counsel Stack

Bluebook (online)
Munson Hardisty, LLC v. Legacy Pointe Apartments, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/munson-hardisty-llc-v-legacy-pointe-apartments-llc-ca6-2025.