Munson Hardisty, LLC v. Legacy Pointe Apartments, LLC
This text of Munson Hardisty, LLC v. Legacy Pointe Apartments, LLC (Munson Hardisty, LLC v. Legacy Pointe Apartments, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
NOT RECOMMENDED FOR PUBLICATION File Name: 25a0171n.06
No. 23-5732
UNITED STATES COURT OF APPEALS FILED FOR THE SIXTH CIRCUIT Mar 28, 2025 KELLY L. STEPHENS, Clerk ) MUNSON HARDISTY, LLC, ) Plaintiff-Appellee, ) ON APPEAL FROM THE ) UNITED STATES DISTRICT v. ) COURT FOR THE EASTERN ) DISTRICT OF TENNESSEE LEGACY POINTE APARTMENTS, LLC, ) Defendant-Appellant. ) OPINION ) )
Before: BATCHELDER, BUSH, and BLOOMEKATZ, Circuit Judges.
ALICE M. BATCHELDER, Circuit Judge. Legacy Pointe Apartments hired Munson
Hardisty to build an apartment complex in Tennessee. As with most construction contracts,
however, plans often change, and this project was no exception. Indeed, as the project progressed,
the parties made many changes to the project’s plans and specifications, which ultimately forced
Munson Hardisty to do extra work. But when the parties made these changes to the contract, they
did so without following the contract’s explicit requirements for change orders. When it later came
time to pay Munson Hardisty for its extra work, Legacy Pointe refused to do so. Munson Hardisty
then sued, and a jury awarded it almost $1.3 million in damages. For the reasons below, we affirm.
I.
In 2007, Legacy Pointe hired Munson Hardisty to build an apartment complex in
Knoxville, Tennessee. The two parties agreed to a so-called “cost-plus” construction contract,
under which the Department of Housing and Urban Development (HUD) would guarantee the loan
given to Legacy Pointe, and Legacy Pointe would pay Munson Hardisty a little more than No. 23-5732, Munson Hardisty v. Legacy Pointe Apartments
$18 million to build the apartment complex. Because HUD agreed to guarantee the loan given to
Legacy Pointe, the contract required that any changes to the project be submitted to HUD and the
lender for their approval.
As the project progressed, Legacy Pointe began to change the plans and specifications
outlined in the contract, and that, in turn, required Munson Hardisty to do extra work. But rather
than submit these change orders to HUD and the lender for their approval, as the contract required,
the parties instead agreed to make these changes to the project on the side. And so, perhaps
unsurprisingly, when it eventually came time for Legacy Pointe to pay Munson Hardisty for the
extra work that it had performed, Legacy Pointe refused to do so.
After Legacy Pointe refused to pay for the extra work, Munson Hardisty sued, alleging
both that an implied contract for the work existed, and that Legacy Pointe had been unjustly
enriched when it received the benefits of Munson Hardisty’s work without paying. The case
eventually proceeded to trial, which resulted in a jury’s awarding Munson Hardisty $350,000 on
its implied-contract claim and $930,000 on its unjust-enrichment claim. Legacy Pointe now
appeals.
II.
Legacy Pointe raises two main challenges to the jury’s verdict: (1) that the jury could not
award Munson Hardisty implied-contract and unjust-enrichment damages when an express
contract between the parties existed; and (2) that the jury could not award damages to Munson
Hardisty under both its implied-contract and unjust-enrichment theories because the award is
duplicative. We disagree and address each issue in turn.
First, Legacy Pointe maintains that Munson Hardisty could not recover any implied-
contract damages here because the express contract between the parties covered all claims for extra
-2- No. 23-5732, Munson Hardisty v. Legacy Pointe Apartments
work. But Legacy Pointe never raised this argument in the district court, and it even conceded
during its opening argument at trial that any work performed by Munson Hardisty without approval
from HUD was “not part of the construction contract.” So Legacy Pointe cannot now claim—for
the first time on appeal—that the express contract between the parties precluded Munson Hardisty
from recovering implied-contract damages. See, e.g., Barner v. Pilkington N. Am., Inc., 399 F.3d
745, 749 (6th Cir. 2005) (“Our function is to review the case presented to the district court, rather
than a better case fashioned after a district court’s unfavorable order.”).
Besides, even if Legacy Pointe had raised and preserved this argument below, the outcome
here would still be the same. That is because whether a contract covers a particular subject matter
is a question of fact for the jury under Tennessee law, see Bratton v. Bratton, 136 S.W.3d 595, 601-
02 (Tenn. 2004), and we cannot overturn a jury’s factual finding unless “there [was] no material
evidence to support the [jury’s] verdict,” Campbell v. Fla. Steel Corp., 919 S.W.2d 26, 35 n.3
(Tenn. 1996). Here, the district court instructed the jury that it could not award damages under the
implied-contract and unjust-enrichment theories unless it found that an express contract did not
cover the extra work performed by Munson Hardisty, and we cannot say that the jury had no
material evidence to support such a finding when both parties seemingly agreed not to follow the
contract’s requirements for change orders and extra work.
Second, Legacy Pointe’s argument that Munson Hardisty received duplicative damages
awards also fails because the district court instructed the jury at trial that it could award damages
under both Munson Hardisty’s implied-contract theory and unjust-enrichment theory, and Legacy
Pointe never objected to those instructions. And when, as here, a party does not object to the
district court’s jury instructions, we review the accuracy of those instructions for plain error.
Craddock v. FedEx Corp. Servs., Inc., 102 F.4th 832, 842 (6th Cir. 2024). To prevail under the
-3- No. 23-5732, Munson Hardisty v. Legacy Pointe Apartments
plain-error standard, Legacy Point must establish four elements: (1) that there was an error; (2) that
the error was plain; (3) that the error affected a substantial right; and (4) that the error “seriously
affected the fairness, integrity, or public reputation of the judicial proceedings.” United States v.
Tragas, 727 F.3d 610, 616 (6th Cir. 2013).
Here, we do not believe that the district court’s jury instructions failed this test. For one
thing, it is not clear that the district court’s jury instructions even misstated Tennessee law, which
does appear to distinguish between unjust-enrichment and implied-contract claims. See Fam. Tr.
Servs. LLC v. Green Wise Homes LLC, 693 S.W.3d 284, 305-06 (Tenn. 2024). But in any event,
even if the district court’s jury instructions had misstated Tennessee law, that purported error would
not be plain.
III.
Because Legacy Pointe failed to preserve its arguments and never objected to the district
court’s jury instructions, we AFFIRM the judgment of the district court.
-4-
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
Munson Hardisty, LLC v. Legacy Pointe Apartments, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/munson-hardisty-llc-v-legacy-pointe-apartments-llc-ca6-2025.