Municipality of Upper St. Clair v. Boyce Road Partnership

531 A.2d 111, 109 Pa. Commw. 398, 1987 Pa. Commw. LEXIS 2470
CourtCommonwealth Court of Pennsylvania
DecidedSeptember 17, 1987
DocketAppeal, No. 1322 C.D. 1986
StatusPublished
Cited by1 cases

This text of 531 A.2d 111 (Municipality of Upper St. Clair v. Boyce Road Partnership) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Municipality of Upper St. Clair v. Boyce Road Partnership, 531 A.2d 111, 109 Pa. Commw. 398, 1987 Pa. Commw. LEXIS 2470 (Pa. Ct. App. 1987).

Opinion

Opinion by

Judge Palladino,

This is an appeal by the Municipality of Upper St. Clair (Appellant) from an order of the Court of Common Pleas of Allegheny County (trial court) reversing a denial by the Upper St. Clair Board of Commissioners (Board) of a conditional use permit for the construction of a planned office center (POC) to Boyce Road Partnership (Developer). For the reasons which follow, we reverse.

In 1975, Developer purchased a parcel of real property approximately forty-two (42) acres in size and located in Upper St. Clair Township. At all times relevant hereto, this parcel was zoned RM-P Planned Restricted Light Industrial District.

Pursuant to a master plan for the development of the entire tract, Developer applied for tentative approval of Phase I of the POC in 1977. A POC is permitted in an RM-P district as a conditional use.1 Approval is obtained in two phases, tentative and final. Tentative approval often contains conditions which must be satisfied prior to the grant of final approval.

After both tentative and final approvals were secured, Developer constructed two office buildings, completing the first in 1979 and the second in 1981. On February 6, 1984, Boyce Plaza. Road, abutting these office buildings, was accepted by Appellant.

[401]*401In February of 1981, Developer started the application process for Phase II. Phase II consisted of an office building and a hospital. Amended tentative approval was granted on October 4, 1982, subject to, among others, the following conditions:

11. That the following phasing schedule for filing for'final approvals be followed:
Phase 2—Lot 3A—not later than 12 months from filing of Phase I (the parcel of land lying west of the Stop N Go building adjacent to Chartiers Creek) and after satisfactory completion of installation of all public and private improvements serving Boyce Road POC (that parcel of land containing the Stop N. Go headquarters building) and Phase I of Boyce Plaza Complex including installation of the 8 inch water line with a crossover and direct point of connection for the Stop N Go Office Building.
Phase 3—Lot 5—not later than 12 months from the filing of the previous phase and after satisfactory completion of the installation of all public and private improvements for prior phases.
Phase 4—Lot 6—same condition as for phase 3.

(Emphasis added.) Appellant granted final approval for this phase by ordinance enacted July 5, 1983, subject to the condition “THAT Final Approval of the plan is subject to all conditions of amended Tentative Approval granted October 4, 1982 by Decision—USC-POC 1-82 of the Board of Commissioners.” The office building was completed in 1983 and the hospital in 1984. On September 26, 1984, Appellant refused to accept the dedication of the additional portion of Boyce Plaza Road and the Phase II public improvements, abutting the hospital.

[402]*402Appellants stated reason for rejection was that Developer failed to install the electric lines serving the hospital underground, in violation of Section 114-16B of the Upper St. Clair subdivision ordinance. Appellant stated:

Unfortunately, the overhead installation of electric did not come to our attention until it was finished. The approved construction drawings did not indicate the proposed electric installation, and the utility company failed to apply for and obtain the required Township Street Opening Permit for the installation.
Nevertheless, unless there is some technical reason why it is impossible or unadvisable, we must insist that the Township requirements and standards be complied with and that the electric along Boyce Plaza Road be placed underground prior to Township acceptance of Boyce Plaza Road Extension or the consideration of any other application for final approval of additional phases of Boyce Plaza Complex Planned Office Center, including Phase III which you have told me you intend to file in October, 1984. This is consistent with the phasing schedule for Boyce Plaza Complex Planned Office Center.

In October, 1984, Developer filed for final approval of Phase III of the POC.2 Phase III consists of two 15,000 sq. ft. buildings. After a February 4, 1985 hearing, the Board denied the application for final approval as incomplete. Specifically, the Board cited three items:

1) The failure to produce a financing commitment for both office buildings (Developer had [403]*403produced a commitment from Union National Bank for one building);
2) The failure to substantiate compliance with the Upper St. Clair Interim Flood Plain Ordinance; and
3) The failure to remove the existing aerial electrical lines abutting the hospital in Phase II and place them underground.

Developer filed a notice of appeal with the trial court.

On appeal, the trial court identified the removal of the aerial electrical lines as the primary issue, quickly disposing of the other two grounds for denial of the final approval for Phase III.3 Concluding that the Board was attempting to hold the land in question hostage, and that it was an unreasonable condition imposed too late, the trial court held that Appellant acted unconstitutionally in refusing to give final approval to its plan because Developer failed to replace aerial electric lines.4 By order dated April 4, 1986, the trial court reversed the Boards decision, provided that Developer submit proof of financing within 30 days therefrom. Appellant timely appealed to this court.

[404]*404As a result of the appeal by Appellant, Pa. R.A.P. 1736 provides for an automatic supersedeas in favor of the Muncipality. Pursuant to Pa. R.A.P. 1732, Developer petitioned the trial court for relief from supersedeas, asserting that no damage to Appellants position would occur by allowing them to develop this parcel. The trial court granted relief from supersedeas and ordered the Township to issue Developer a building permit5 by order dated July 18, 1986. On appeal to this court, by order dated August 21, 1986, the Honorable Theodore O. Rogers, Senior Judge, denied Appellants application for reinstatement of the automatic stáy provided by Pa. R.A.P. 1736(b). . ’

Our scope of review, in an appeal from the denial of a conditional use permit, where the trial court took no additional evidence, is limited to a determination of whether the Board of Commissioners committed an error of law or manifestly abused its discretion. In Re: Appeal of Stagebrush Promotions, Inc., 98 Pa. Commonwealth Ct. 634, 512 A.2d 776 (1986).

Construction Financing Commitment

Section 130-22(c)(l)(k) of the Upper St.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Highfield II, Inc. v. Municipality of Upper St. Clair
560 A.2d 294 (Commonwealth Court of Pennsylvania, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
531 A.2d 111, 109 Pa. Commw. 398, 1987 Pa. Commw. LEXIS 2470, Counsel Stack Legal Research, https://law.counselstack.com/opinion/municipality-of-upper-st-clair-v-boyce-road-partnership-pacommwct-1987.