Municipal Leasing Corp. v. United States

30 Cont. Cas. Fed. 70,909, 1 Cl. Ct. 771, 1983 U.S. Claims LEXIS 1821
CourtUnited States Court of Claims
DecidedMarch 17, 1983
DocketNo. 428-82C
StatusPublished
Cited by8 cases

This text of 30 Cont. Cas. Fed. 70,909 (Municipal Leasing Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Municipal Leasing Corp. v. United States, 30 Cont. Cas. Fed. 70,909, 1 Cl. Ct. 771, 1983 U.S. Claims LEXIS 1821 (cc 1983).

Opinion

ORDER

MEROW, Judge:

This matter comes before the court on defendant’s motions for summary judgment and for a protective order, plaintiff’s oppositions to these motions, and defendant’s reply.

Facts

The controversy at issue concerns a contract executed on July 14,1980 between the United States (Base Contracting Division, Offutt Air Force Base) and Municipal Leasing Corporation. The contract provided for the “lease to ownership” of 10 Intecolor Terminals at rates to be paid monthly by the Air Force as follows: $634 for one ISC Model 8052 Desk Top Computer 13" CRT; $839 for one ISC Model 8052 Desk Top Computer 19" CRT; and $3,521 for the remaining 8 ISC Model 8052 Desk Top Computers 19" CRT. The total monthly payment contemplated was $4,994. The basic contract period was for the two months remaining in the 1980 fiscal year — August 1 through September 30, 1980. The contract [772]*772provided for an additional “option year one,” from October 1,1980 through September 30, 1981, and an additional “option year two” from October 1,1981 through September 30, 1982. By paying the prorated monthly rates over the life of the contract through September 30, 1982 (later modified to November 30,1982), the Air Force would gain the ownership of the equipment.1

The contract, in Part I, Section H, contained three provisions concerning performance and payment during option years one and two as follows:

SP-04: OPTION TO EXTEND THE TERM OF THE CONTRACT DAR 7-104.27(c) (Undated)
This contract is renewable, at the option of the Government, by the Contracting Officer giving written notice of renewal to the Contractor by the first day of each fiscal year or within 30 days after funds for that fiscal year become available, whichever date is the later; provided that the Contracting Officer shall have given preliminary notice of the Government’s intention to renew at least 30 days before this contract is to expire. Such a preliminary notice shall not be deemed to commit the Government to renewals. If the Government exercises this option for renewal, the contract as renewed shall be deemed to include this option provision. However, the total duration of this contract, including the exercise of any options under this clause, shall not exceed 26 months.
SP-05: AVAILABILITY OF FUNDS FOR NEXT FISCAL YEAR (1975 JUN) DAR 7-104.91(b)
Funds are not presently available for performance under this contract beyond 30 SEP 80. The Government’s obligation for performance of this contract beyond this date is contingent upon the availability of appropriated funds from which payment for the contract purposes can be made. No legal liability on the part of the Government for payment of any money for performance under this contract beyond 30 SEP 80 shall arise unless and until funds are made available to the Contracting Officer for such performance and notice of such availability, to be confirmed in writing by the Contracting Officer, is given to the Contractor.
SP-06 * * * Government’s Intentions:
It is the intent of the Air Force to exercise the options as specified in SP-04 above. The Air Force shall use its best efforts to obtain appropriations of the necessary funds to meet its obligations and to continue this contract in force. The Air Force shall not replace the leased equipment with functionally similar equipment during the term of this contract.

In addition, the contract contained a standard (1968) “Termination for Convenience of the Government” clause provided for service contracts.

Under the contract plaintiff was required to submit invoices and it was specified (Part I- Section G) that, “2. Payment will be based on certified invoices for actual number of units completed during each invoice period.” Part I-Section D, Item 2, of the contract provided that plaintiff “shall be responsible for the necessary packing, unpacking and placement of equipment required by the initial installation of the equipment and the removal of the equipment at the end of the contract.” Part II- Section E provided that “Inspection and final acceptance of the equipment will be at destination, Hq SAC/ADXPO, Bldg 500, Room 2E23, Offutt AFB, NE 68113.”

By an amendment to the contract effective October 1, 1980, its term was extended to cover the 1981 fiscal year period of October 1, 1980 through September 30, 1981. The amendment expressly called attention to the “Availability of Funds” provision of the contract.

On November 18, 1980 plaintiff submitted an invoice for $4,994 for the period of October 1-30, 1980. The amount paid to [773]*773plaintiff was $3,495.80 based upon a handwritten notation placed on the invoice that “THERE WAS ONLY 7 INSTALLED FOR THE MONTH OF OCTOBER 80. C. HAM-BY.” Similar reduced payments were made for several subsequent months. For example, on invoices submitted, notations were made that only 9 were “INSTALLED” for December 1980 whereas only 6 were “installed” for January 1981. According to the documents filed to date in this matter, payments made by the Air Force totaled $8,987.20 less than the amounts plaintiff invoiced.

By a letter dated July 27, 1981 to plaintiff, the contracting officer provided notice of “the government’s intentions to renew this contract for the period 01 Oct 81 through 30 Sep 82.” The letter also stated “You are advised, however, that this preliminary notice will not be deemed to commit the government to a renewal.” An internal Air Force memorandum dated August 26, 1981 references the SP-04 and SP-05 clauses of the contract and states “Funds will not be made available for renewal of the subject contract beyond 30 September 1981.” The memorandum also requested that plaintiff be advised to provide shipping instructions for the leased equipment “within 30 days after receipt of your official termination notification.”

On September 8, 1981 the contracting officer sent a letter to plaintiff stating (in part):

This contract * * * will terminate as of 30 Sep 1981 in accordance with Special Provisions 04 and 05 as cited on page H-3. It is requested that you provide shipping instructions no later than 30 days after receiving this notification. * *

By a letter dated July 1, 1982 the contracting officer denied a claim plaintiff had submitted. The decision stated (in part):

3. Pursuant to Special Provision 04, the Government reserved the option to renew the contract at the close of the fiscal year in accordance with DAR 7-104.27(c). The Air Force availed itself of this option at the close of the fiscal year 1980 thereby extending payment and performance duties to 30 September 1981.
4. Although the Air Force agreed to use its best efforts to exercise the contract’s options by Special Provision 06, ultimately, any renewal of the subject contract was totally contingent upon the availability of funds. DAR 7-104.91(b)
5. Despite our efforts, when the United States Government determines that Air Force requirements no longer exist, it will not appropriate funds. This is evidenced by the fact that the Air Force did not replace the equipment with functionally similar equipment during the term of the contract, nor has it been replaced to date.
6.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vion Corporation v. United States
122 Fed. Cl. 559 (Federal Claims, 2015)
Northrop Grumman Computing Systems, Inc. v. United States
93 Fed. Cl. 144 (Federal Claims, 2010)
Government Systems Advisors, Inc. v. United States
36 Cont. Cas. Fed. 75,937 (Court of Claims, 1990)
Erwin v. United States
36 Cont. Cas. Fed. 75,766 (Court of Claims, 1989)
Pacificorp Capital, Inc. v. United States
35 Cont. Cas. Fed. 75,579 (Court of Claims, 1988)
Government Systems Advisors, Inc. v. The United States
847 F.2d 811 (Federal Circuit, 1988)
Municipal Leasing Corp. v. United States
32 Cont. Cas. Fed. 73,129 (Court of Claims, 1984)
United States v. Board of Educ. of City of Chicago
588 F. Supp. 132 (N.D. Illinois, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
30 Cont. Cas. Fed. 70,909, 1 Cl. Ct. 771, 1983 U.S. Claims LEXIS 1821, Counsel Stack Legal Research, https://law.counselstack.com/opinion/municipal-leasing-corp-v-united-states-cc-1983.