Municipal Energy Agency v. City of Cambridge

430 N.W.2d 44, 230 Neb. 61, 1988 Neb. LEXIS 362
CourtNebraska Supreme Court
DecidedOctober 7, 1988
Docket87-035
StatusPublished
Cited by2 cases

This text of 430 N.W.2d 44 (Municipal Energy Agency v. City of Cambridge) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Municipal Energy Agency v. City of Cambridge, 430 N.W.2d 44, 230 Neb. 61, 1988 Neb. LEXIS 362 (Neb. 1988).

Opinion

Boslaugh, J.

On August 6, 1979, the defendant, City of Cambridge, Nebraska, entered into a contract, known as an Electrical Resources Pooling Agreement (ERPA), with the Nebraska Municipal Power Pool (NMPP). The contract was assigned to the plaintiff, Municipal Energy Agency of Nebraska (MEAN), the successor to NMPP, on January 11,1982.

Under the ERPA contract a participant was required to choose whether it wanted bulk or service power under the agreement. Under a bulk power arrangement, the participant contracts to deliver its power production to MEAN, pays a standard rate, and MEAN schedules the power.

The city originally intended to become a bulk service power participant, and an ordinance authorizing the mayor to execute the bulk service power agreement was passed. However, disputes arose between the city and MEAN, and the city never executed the bulk service power schedule (schedule K).

Under a service power arrangement, the participant decides on a day-to-day basis how much power it needs and from whom it will purchase the power. The ERPA contract requires that a participant act in accordance with the “service schedules.” Schedule F is used for service power participants. The contract does not require that a participant execute such a schedule, but merely requires that the participant act in accordance with that schedule.

The contract does not require the execution of any other document. The schedules were developed originally by the pool staff and set out the charges to be billed for electrical power services. The management committee of the pool, comprised of a representative of each participant, reviews and approves the schedules and any amendments. In proposing schedules and amendments, the normal practice was to send each participant a copy of the proposed amendment for final approval at a meeting. The defendant city was treated as a service power *63 participant and was billed according to the service schedule adopted on March 6,1981.

The city contends that its authorized representative (Councilman Gufford) was not present at the meetings at which schedule F was adopted and later amended. The city’s powerplant supervisor, Kenneth Fichtner, did attend those meetings, but the city contends Fichtner was not authorized to approve the schedule on behalf of the city.

The service power schedule (schedule F) requires that participants reimburse MEAN for transmission charges (also called “wheeling” charges). Included in those charges is the applicable “billing demand ratchet” (ratchet) in effect, which is based on MEAN’S agreement with the Nebraska Public Power District. The ratchet is fixed by the highest demand for power in a given period. That demand level is in effect for the succeeding 11 months, and MEAN is obligated to pay at that demand level regardless of whether that amount of power is used.

The contract requires each participant to reserve transmission capacity in advance. In effect, the participant is required to nominate a demand amount, which is the maximum the participant will be entitled to receive unless surplus is available because other participants are not using their maximum demand capacity. In August of 1979, Fichtner made a reservation for the city of 800 kilowatts. In 1981 he increased the demand reservation of the city to 1200 kilowatts. Each month a participant is billed for the demand capacity reserved whether it is used or not. The city paid all such charges until October 1982.

From August of 1979 to July 15,1982, the city bought power and transmission services from MEAN. During that time, both parties treated the city as if it were a service power participant. The city bought power on a day-to-day basis, and it was billed for transmission charges as a service power participant. Each day the powerplant manager, Fichtner, called MEAN and reserved the amount of power required for that day. During the course of the 3-year period, the city increased the amount of power it purchased as a service power participant, although Fichtner had no recollection of a long-term agreement between the city and MEAN to purchase power. However, Fichtner *64 testified that he had assumed that MEAN was treating the city as a service power participant.

It is undisputed that the city timely paid its power bills from MEAN until October of 1982. In July of 1982, the city discontinued scheduling and paying for power from MEAN. It paid the ratcheted transmission charges for the months of August and September of 1982, but at that time decided to discontinue paying those charges.

The second amended petition was filed October 16, 1984, to recover unpaid “wheeling” or transmission charges. A bench trial was held on March 5, 1986. On June 23, 1986, the trial court found that ERPA participants could choose whether they would be service power or bulk power participants; that by their actions, the parties chose for the city to be a service power participant; that the schedules necessary for service power participation had been adopted as contemplated in the contract; that the city had been represented at the meetings by Fichtner; and that the city was estopped to deny the contract. The trial court found that the city owed MEAN $14,673.55 plus prejudgment interest, for a total award of $19,994.62.

The city has appealed and has assigned as error the finding that there was a valid contract between the parties with respect to ratcheted transmission charges. The city argues that the trial court’s decision reformed the terms of the contract and that MEAN failed to establish the existence of the schedules necessary to form a complete and binding contract. Finally, the city argues that since it was not billed for any use of power after it canceled service from MEAN, it does not owe MEAN any transmission charges.

This is a suit on a contract and is an action at law. The standard of review for an action at law, tried without a jury, as in this suit, is well settled in Nebraska. In Osmond State Bank v. Uecker Grain, 227 Neb. 636, 637, 419 N.W.2d 518, 519 (1988), we said:

In reviewing an action at law tried without a jury, it is not the role of the Supreme Court to resolve conflicts in or reweigh the evidence. Rather, the court presumes that the trial judge resolved any controverted facts in favor of the successful party. This court will also consider the evidence *65 and the permissible inferences therefrom most favorably to the successful party. Moreover, in such actions the findings and conclusions of the trial judge have the effect of a jury verdict and will not be set aside unless clearly wrong.

This standard was reiterated in Wells Fargo Alarm Serv. v. Nox-Crete Chem., 229 Neb. 43, 424 N.W.2d 885 (1988).

The pleadings show that MEAN was advancing two theories of recovery. The second amended petition alleged a cause of action for breach of contract because of the city’s failure to pay accrued charges for the period of October 1982 through June 1983. The second cause of action was based in quantum meruit for the value of services provided to the city.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Long v. Hacker
520 N.W.2d 195 (Nebraska Supreme Court, 1994)
Wurst v. Blue River Bank
454 N.W.2d 665 (Nebraska Supreme Court, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
430 N.W.2d 44, 230 Neb. 61, 1988 Neb. LEXIS 362, Counsel Stack Legal Research, https://law.counselstack.com/opinion/municipal-energy-agency-v-city-of-cambridge-neb-1988.