Mundy v. Knutson Construction Co.

283 S.W.2d 245, 1955 Tex. App. LEXIS 2117
CourtCourt of Appeals of Texas
DecidedOctober 20, 1955
DocketNo. 12713
StatusPublished
Cited by1 cases

This text of 283 S.W.2d 245 (Mundy v. Knutson Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mundy v. Knutson Construction Co., 283 S.W.2d 245, 1955 Tex. App. LEXIS 2117 (Tex. Ct. App. 1955).

Opinion

CODY, Justice.

This appeal is concerned with what to all intents and purposes are two suits. To avoid unnecessary confusion we will first limit this opinion to the first suit and, after disposing of that, we will take up the second one. The undisputed facts in the first suit were these:

The Knutson Construction Company— the trade-name of Severin Knutson — contracted with the Harris County Water Control and Improvement District for certain sanitary sewer lines and other appropriate facilities, as set out in said contract, a copy of which was attached to Knutson’s petition. Knutson thereafter- subcontracted the performance of the entire contract to J. W. Mundy- Construction Company — the trade-name J- W. Mundy — arid in connection, therewith Mundy furnished Knutson a per-fonnance bond with L. Gene Newman as surety thereon. After Mundy had corn-Pleted tile greater part of the work, he became insolvent -so Knutson had to finish-work-

After he had finished the work, Knutson, brought suit against Mundy and Mundy's surety, Newman, to recover damages in. the sums specified in Knutson’s petition. So far as is now material on this appeal, Knutson sought to recover the sum of $100 a day liquidated damages for 174 days, or $17,400 liquidated damages, for delay, purportedly under the terms of the subcontract. Knutson also claimed the right to recover reasonable attorney’s fees.

Mundy and his surety, Newman, so far as material on appeal, plead a waiver by Knutson of all liquidated damages, and he further denied any right in Knutson to recover attorney’s fees. The case was submitted to the jury upon special issues and it is sufficient to state that the court rendered judgment in favor of Knutson and against Mundy and Newman for the sum of $21,850.98. We take the following statement from the brief of Mundy and Newman, which is not challenged by Knutson:

“In arriving at such net figure in favor of Knutson, the trial court after taking into account all other charges, credits and offsets determined either by the jury verdict or the undisputed evidence, charged Mundy and Newman with the following items of which complaint is made on this appeal:
“(a) The sum of $17,400.00, based upon 174 days delay in the completion of the contract, which called for- liquidated damages for delay at the rate of $100.00 per day.
“(b) The sum of $6,500.00 as attorney’s fees to Knutson for the prosecution of the case at bar.
“It is, of course, obvious that had these two items not been charged [247]*247against Mundy and Newman, then instead of Knutson recovering $21,850.-98, Mundy would have been entitled to judgment against Knutson for $2,049.-02.”

Mundy and Newman predicate their appeal upon five formal points of error, ■complaining (1) of the court’s rejection of special issue No. 9A as answered by the jury, (2) of the court’s rejection of special issue No. 9B as answered by the jury, (3) of the court’s action in awarding Knutson $17,400 as liquidated damages, (4) of the court’s action in awarding attorney’s fees to Knutson because Mundy and Newman had not contracted with Knutson for payment of any attorney’s fees, and (5) of the court’s action in rendering judgment for Knutson for $21,850.98 instead of rendering judgment for Mundy on his cross-action against Knutson for $2,049.02.

We overrule Mundy’s and Newman’s first three points.

Based upon the provision of the sub-contract, Knutson sued Mundy and Newman to recover $100 a day as liquidated damages for each day in excess of 300 calendar days that the work remained unfinished, which was asserted to be 174 days. Mundy and Newman plead that the.delay in completing the work over the 300. day period was the fault of Knutson and the District, and further plead that Knutson agreed during the course of the work that no penalty for delay would be exacted from Mundy if the District exacted no liquidated damages from him, Knutson.

Due to rain and the condition brought about by the work in which Mundy was installing the sewer line, the streets became impassable and the District, at a meeting, where Mundy and Randerson, the duly authorized agent of Knutson, were present, requested Mundy to hold up all further work until the streets could dry out and become passable. Mundy said that he would do so provided Knutson would not hold him for the delay which the Board of the District was requesting; and Rander-son agreed that if the District did not undertake to hold Knutson liable for liquidated damages for such delay, then Knut-son would not undertake to make any charge against Mundy for such damages.

Relative to the agreemeilt made in the presence of the Board, the following questions were asked of Mr. Mundy and he made the following answers:

“Q. What was the reason or the necessity, or rather, why was the Board asking you to shut down and repair those streets? A. Well, why did they want them repaired?
“Q. What was the situation existing that caused them to ask you to do that? A. Well, the streets were in such condition they didn’t want any more streets disturbed until we could get on up to putting the streets in shape to where the people could go up and down them in good shape.
******
“Q. Now, Mr. Randerson was asking you to shut down? A. Yes, sir.
“Q. And you were not willing to shut down without some assurance? A. Without assurance of that; yes, sir.
“Q. Let me ask you this, did Mr. Randerson tell you, if I understood you correctly, that if you would shut down that there would be no liquidated damages charged against you unless the Board charged him, Randerson, for-damages for the delay? A. Yes, sir.
“Q. All right, you did shut down? . A. Yes, sir; I did.
“Q. How long did you shut down? A. Just a little over three weeks; I think it was a couple of days over three weeks.
******
“Q. I wish you would state just what took place at that meeting between you and Mr. Randerson, the Engineers and the Board, with respect to the matter of your shutting down, [248]*248and with respect to anything Mr. Ran-derson stated he would do if you would shut down.
* * * * * *
“A. One thing that was brought up at that meeting was the Engineers and the Owners wanted me to shut down and let the street conditions get better and catch up with some of our cleanup, but to more or less let the streets dry out so we would not be opening up any more streets and the streets wouldn’t be in any worse condition, and I wanted to be sure I wouldn’t get into any more trouble about it, and I brought up the subject of liquidated damages that I might be charged if we did shut down, and we discussed that and it went on and I asked Mr. Ran-derson to definitely state whether he would or would not, and he kept saying he had no intentions of it, and I kept on and I said, ‘May I or may I not?’ He said: ‘If the Board charges us damages, of course, if we are charged any damages, we will have to pass them on to you’, and I said that would be all right.
“Q. Did you shut down, relying on his agreement with you? A. Yes, sir.
“Q.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mundy v. Knutson Construction Company
294 S.W.2d 371 (Texas Supreme Court, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
283 S.W.2d 245, 1955 Tex. App. LEXIS 2117, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mundy-v-knutson-construction-co-texapp-1955.